Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Muzyr Refinery ESP Material delivery vs Construction Material Delivery Construction Dates

S. AUGUST SEPTEMBER OCTOBER NOVEMBER


ACTIVITY DESCRIPTION
No. 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1 Dismantling Activities

Dismantling of Existing Outlet cone approach platform including


1.1
Construction Activity grating and handrails

1.2
Material Delivery NIL

1.3
Construction Activity Dismantling of existing Outlet Cone

1.4
Material Delivery NIL

1.5
Construction Activity Dismantling of the existing Outlet cone PDPL/GD screen

1.6
Material Delivery NIL

1.7
Construction Activity Dismantling of existing Inlet PDPL-03

1.8
Material Delivery NIL

1.9
Construction Activity Dismantling of existing Inlet PDPL-02 middle portion

1.10
Material Delivery NIL

1.11
Construction Activity Dismantling of existing hopper baffles for 4 hoppers

1.12
Material Delivery NIL

Dismantling of existing outlet duct ( From outlet cone to


1.13
Construction Activity Chimney)

1.14
Material Delivery NIL

1.15
Construction Activity Dismantling of outlet duct supports and access platforms if any

1.16
Material Delivery NIL

1.17
Construction Activity Dismantling of existing chimney

1.18
Material Delivery NIL

2
Erection Of Supporting Structure

2.1
Construction Activity Erection Of Foundation Bolts

2.2
Material Delivery

2.3
Construction Activity Erection Of Columns

2.4
Material Delivery

2.5
Construction Activity Erection Of Tie Beams

2.6
Material Delivery

2.7
Construction Activity Erection Of Vertical bracings

2.8
Material Delivery

Page 1
Muzyr Refinery ESP Material delivery vs Construction Material Delivery Construction Dates
S. AUGUST SEPTEMBER OCTOBER NOVEMBER
ACTIVITY DESCRIPTION
No. 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

3.1
Construction Activity Erection Of PTFE Bearings

3.2
Material Delivery Available at Site

4
Erection Of Casing

4.1
Construction Activity Erection of lower part of Casing LHS and RHS

4.2
Material Delivery

4.3
Construction Activity Erection Of Bottom Girder Beams

4.4
Material Delivery

4.5
Construction Activity Erection of Middle and Top portion of the casing ( LHS & RHS)

4.6
Material Delivery

4.7
Construction Activity Erection Of Top Girder Beams

4.8
Material Delivery

4.9
Construction Activity Erection Of Internal walkways

4.10
Material Delivery

4.11
Construction Activity Erection Of Flue struts and Sway bracings

4.12
Material Delivery

5
Erection Of Hoppers

5.1
Construction Activity Erection Of Hoppers For F-3

5.2
Material Delivery

5.3
Construction Activity Erection of New Hopper baffles in the existing fields

5.4
Material Delivery

6.1
Construction Activity Erection of New intermediate flue gas duct

6.2
Material Delivery

7
Inlet Cone Area

7.1
Construction Activity Erection Of partial Inlet PDPL -02 Screen with attachments

7.2
Material Delivery Available at Site

7.3
Construction Activity Erection Of Inlet PDPL -03 Screen with attachments

7.4
Material Delivery Available at Site

8.1
Construction Activity Erection Of Outlet Cone

8.2
Material Delivery GD screens Available at site

Page 2
Muzyr Refinery ESP Material delivery vs Construction Material Delivery Construction Dates
S. AUGUST SEPTEMBER OCTOBER NOVEMBER
ACTIVITY DESCRIPTION
No. 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

8.3
Material Delivery Attachments

9.1
Construction Activity Erection of Outlet Duct with Supports

9.2
Material Delivery

10.1
Construction Activity Erection Of CE's with Internals For F-3 ( new Field)

10.2
Material Delivery Available at Site

11.1
Construction Activity Erection Of DE's with Internals For F-3 ( new Field)

11.2
Material Delivery Available at Site

12.1
Construction Activity Alignments of CE and DE

12.2
Material Delivery NIL

13.1
Construction Activity Erection Of Hot Roof for F-3 ( new Field)

13.2
Material Delivery

14.1
Construction Activity Erection Of Pent House / HT Room ( new Field)

14.2
Material Delivery

15.1
Construction Activity Erection Of CE Rapping System (Migi)

15.2
Material Delivery Available at Site

16.1
Construction Activity Erection Of DE Rapping System (Migi)

16.2
Material Delivery Available at Site

17.1
Construction Activity Erection of staircase & Landing platforms

17.2
Material Delivery

18.1
Construction Activity Erection Of Approach Platforms

18.2
Material Delivery

19.1
Construction Activity Erection Of Supporting Insulators with Arrangements for F-3

19.2
Material Delivery

20.1
Construction Activity Erection Of Transformers with its accessories

20.2
Material Delivery Available at Site

21.1
Construction Activity Erection Of Chimney

21.2
Material Delivery Mozyr Scope

Page 3
Muzyr Refinery ESP Material delivery vs Construction Material Delivery Construction Dates
S. AUGUST SEPTEMBER OCTOBER NOVEMBER
ACTIVITY DESCRIPTION
No. 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

22
Erection Of Miscellaneous

22.1
Construction Activity Erection Of Hopper heaters along with enclosures

22.2
Material Delivery Available at Site

22.3 Construction Activity Erection Of Hopper level sensors & Vibrators


22.4 Material Delivery Available at Site

22.5 Construction Activity Erection Of all Manhole doors


22.6 Material Delivery

22.7 Construction Activity Erection Of SAS


22.8 Material Delivery Available at Site

22.9 Construction Activity Erection of anti-sneakage plates


22.10 Material Delivery

22.11 Construction Activity Safety Inter locking system


22.12 Material Delivery Available at Site

22.13 Construction Activity RAV's


22.14 Material Delivery

22.15 Construction Activity Slide gates


22.16 Material Delivery

22.17 Construction Activity Telescopic chutes


22.18 Material Delivery

23.1 Construction Activity Insulation


23.2 Material Delivery Mozyr Scope

24.1 Electrical Activities Rapper panel Modification


24.2 Material Delivery Available at Site

25.1 Electrical Activities Erection of TR Panel


25.2 Material Delivery Available at Site

26.1 Electrical Activities Cable trays installation


26.2 Material Delivery Mozyr Scope

27.1 Electrical Activities Cable laying


27.2 Material Delivery

28.1 Electrical Activities Terminations for cables


28.2 Material Delivery Mozyr Scope

29.1 Electrical Activities Earthing


29.2 Material Delivery Mozyr Scope

Page 4

You might also like