Material Delivery Gantt Chart
Material Delivery Gantt Chart
1 Dismantling Activities
1.2
Material Delivery NIL
1.3
Construction Activity Dismantling of existing Outlet Cone
1.4
Material Delivery NIL
1.5
Construction Activity Dismantling of the existing Outlet cone PDPL/GD screen
1.6
Material Delivery NIL
1.7
Construction Activity Dismantling of existing Inlet PDPL-03
1.8
Material Delivery NIL
1.9
Construction Activity Dismantling of existing Inlet PDPL-02 middle portion
1.10
Material Delivery NIL
1.11
Construction Activity Dismantling of existing hopper baffles for 4 hoppers
1.12
Material Delivery NIL
1.14
Material Delivery NIL
1.15
Construction Activity Dismantling of outlet duct supports and access platforms if any
1.16
Material Delivery NIL
1.17
Construction Activity Dismantling of existing chimney
1.18
Material Delivery NIL
2
Erection Of Supporting Structure
2.1
Construction Activity Erection Of Foundation Bolts
2.2
Material Delivery
2.3
Construction Activity Erection Of Columns
2.4
Material Delivery
2.5
Construction Activity Erection Of Tie Beams
2.6
Material Delivery
2.7
Construction Activity Erection Of Vertical bracings
2.8
Material Delivery
Page 1
Muzyr Refinery ESP Material delivery vs Construction Material Delivery Construction Dates
S. AUGUST SEPTEMBER OCTOBER NOVEMBER
ACTIVITY DESCRIPTION
No. 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
3.1
Construction Activity Erection Of PTFE Bearings
3.2
Material Delivery Available at Site
4
Erection Of Casing
4.1
Construction Activity Erection of lower part of Casing LHS and RHS
4.2
Material Delivery
4.3
Construction Activity Erection Of Bottom Girder Beams
4.4
Material Delivery
4.5
Construction Activity Erection of Middle and Top portion of the casing ( LHS & RHS)
4.6
Material Delivery
4.7
Construction Activity Erection Of Top Girder Beams
4.8
Material Delivery
4.9
Construction Activity Erection Of Internal walkways
4.10
Material Delivery
4.11
Construction Activity Erection Of Flue struts and Sway bracings
4.12
Material Delivery
5
Erection Of Hoppers
5.1
Construction Activity Erection Of Hoppers For F-3
5.2
Material Delivery
5.3
Construction Activity Erection of New Hopper baffles in the existing fields
5.4
Material Delivery
6.1
Construction Activity Erection of New intermediate flue gas duct
6.2
Material Delivery
7
Inlet Cone Area
7.1
Construction Activity Erection Of partial Inlet PDPL -02 Screen with attachments
7.2
Material Delivery Available at Site
7.3
Construction Activity Erection Of Inlet PDPL -03 Screen with attachments
7.4
Material Delivery Available at Site
8.1
Construction Activity Erection Of Outlet Cone
8.2
Material Delivery GD screens Available at site
Page 2
Muzyr Refinery ESP Material delivery vs Construction Material Delivery Construction Dates
S. AUGUST SEPTEMBER OCTOBER NOVEMBER
ACTIVITY DESCRIPTION
No. 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
8.3
Material Delivery Attachments
9.1
Construction Activity Erection of Outlet Duct with Supports
9.2
Material Delivery
10.1
Construction Activity Erection Of CE's with Internals For F-3 ( new Field)
10.2
Material Delivery Available at Site
11.1
Construction Activity Erection Of DE's with Internals For F-3 ( new Field)
11.2
Material Delivery Available at Site
12.1
Construction Activity Alignments of CE and DE
12.2
Material Delivery NIL
13.1
Construction Activity Erection Of Hot Roof for F-3 ( new Field)
13.2
Material Delivery
14.1
Construction Activity Erection Of Pent House / HT Room ( new Field)
14.2
Material Delivery
15.1
Construction Activity Erection Of CE Rapping System (Migi)
15.2
Material Delivery Available at Site
16.1
Construction Activity Erection Of DE Rapping System (Migi)
16.2
Material Delivery Available at Site
17.1
Construction Activity Erection of staircase & Landing platforms
17.2
Material Delivery
18.1
Construction Activity Erection Of Approach Platforms
18.2
Material Delivery
19.1
Construction Activity Erection Of Supporting Insulators with Arrangements for F-3
19.2
Material Delivery
20.1
Construction Activity Erection Of Transformers with its accessories
20.2
Material Delivery Available at Site
21.1
Construction Activity Erection Of Chimney
21.2
Material Delivery Mozyr Scope
Page 3
Muzyr Refinery ESP Material delivery vs Construction Material Delivery Construction Dates
S. AUGUST SEPTEMBER OCTOBER NOVEMBER
ACTIVITY DESCRIPTION
No. 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
22
Erection Of Miscellaneous
22.1
Construction Activity Erection Of Hopper heaters along with enclosures
22.2
Material Delivery Available at Site