526P338-002
145 PMC Tank Mounted Density Monitor Checklists
Page 4
145 PMC Installation and Commissioning Checklist (page 1)
Date:
‘Substation: Breaker ID Number:
Line or Bus:
Item/Conditions to Check (Units) Check
Breaker Data:
Breaker Type: Serial Number:
Maximum Rated Voltage (kV) kv
Maximum Rated Continuous Current (A) A
Maximum Short Gircuit Current (kA) KA
Control Voltage (VDC) voc
Auxiliary Voltage (VAC) vac
‘SF6 Pressure at 68°F (20°C)
87 psig (0.60 MPaG)
Mechanism Type:
Serial Number:
Breaker leveled and properly anchored?
All grounding connections properly made?
Control wiring landed?
CTs connected to relaying or metering burden (or short
circuited?)
If optional capacitors provided, are they installed?
‘SFE Gas Filing Pressure (psig) (MPaG) and
Filling Temperature
1) For breakers with three tank-mounted density
monitors, measure all three poles.
2) For breakers with only one tank-mounted density
monitor, measure the pole with the density gauge.
—__psig
Pole 1
°F oor
—___ psig
Pole 2:
°F oor
—___ psig
Pole 3:
MPaG
MPaG
MPaG
and Maintenance module.
Note: The breaker must be filled was specified on the Density Monitor Calibration Chart as shown in the Installation
@danuary 2005526P338-002
145 PMC Tank Mounted Density Monitor Checklists
Page 5
145 PMC Installation and Commissioning Checklist (page 2)
Date:
‘Substation:
Line or Bus:
Breaker ID Number:
Item/Conditions to Check (Units)
Check
‘Check for loose hardware
Clean entrance bushings
Check bushing insulators for any cracks
‘Touch up chipped or scratched paint
Check the anti-pumping circuit
‘Check control cabinet anti-condensation heaters
If your breaker has tank heaters, check that they are oper-
ating
‘Check alarms and lock-outs
Leak Check Testing
Leak check any gas connections and fittings
Leak check the SF6 Gas Density Monitor(s)
Leak check the pressure gauge fittings
Leak check the rupture disks
Leak check the bushing flanges.
Leak check the rear tank cover assemblies
Leak check the bellcrank housings:
Leak check the interphase shaft seals with the breaker in
the OPEN and CLOSED positions
Contact resistance terminal to terminal (Refer to the
Customer Data module for specified contact resistance
values.)
Pole 1
Pole 2:
Pole 3:
microohms
imicroohms
imicroohms
SF6 Gas Moisture Content (to be taken no sooner than 3
days after filing the breaker with gas)
"200 PPMV maximum - Refer to the installation & Mainte-
nance module
For Breakers with 3 tank-mounted density monitors mea-
sure all 3 poles, For breakers with only one, measure the
pole with the density gauge.
Pole 4
PPMV_at,
°F or °C
Pole 2:
PPMV_at,
°F or. c
Pole 3:
PPMV at,
°F or c
‘Complete the Mechanism Commissioning Checklist (in the
Mechanism module)
Check the breaker timing - complete the Timing Checklist
in the Customer Data module. (Refer to the Timing mod-
ule for procedures on performing timing tests.)
Reading on the operations counter
Pole 4
Pole 2:
Pole 3:
‘Test performed by:
“Refer to the Installation & Maintenance module for further details
vanuary 2005