Professional Documents
Culture Documents
Aggregate Planning and MPS - Module - IV
Aggregate Planning and MPS - Module - IV
GADAG
Level
strategy Chase
strategy
8
Level strategy
The firm maintains a level workforce and a steady
rate of output when demand is low. This allows the
firm to establish higher inventory levels than are
currently needed.
9
Chase strategy
A chase strategy implies matching demand and
capacity period by period.
10
Aggregate Planning Strategies
Varying the work force.
Using OT or accepting IT
Varying inventory level.
Accepting back orders.
Subcontracting work to others
Changing the use of existing capacity
Illustrated Example
Paris candy company has estimated its quarterly demand
(cases) as shown in table below. It expects the next
demand cycle to be similar to this one and wishes to
restore ending inventory, employment, etc., to beginning
levels accordingly.
Quarter Demand
1st 500
2nd 900
3rd 700
4th 300
Histogram of Demand
Demand
1000
900
900
800
700
700
600
500 Demand
500
400
300
300
200
100
1st 2nd 3rd 4th
0
Strategy 1- Vary workforce
Lets take incremental cost of Rs. 2000 for every change in
200 units per quarter.
Production information :
Current no. of. workers: 10
Worker time / month: 160 Hrs.
Time to produce one unit: 40Hr/ unit
Individual worker output:
(160 hr/month / 40 Hr per unit): 4 units / month
Safety stock of inventory Reqd :10 Units
Cost information:
Hiring cost: Rs. 600/ employee
Layoff cost: Rs. 500 / employee
Regular-time cost: Rs. 30 / hr
Overtime cost: Rs. 45 / hr
Subcontract labor cost: Rs. 50 / hr
Inventory carrying cost. Rs. 35 / period
Cost calculation for varying workforce
Period 1 2 3 4 5 6 7 8 9
forecast 40 25 55 30 30 50 30 60 40
No of Workforce Reqd 10 7 14 8 8 13 8 15 10
No. hired 0 0 7 0 0 5 0 7 0
COSTS
RT Cost 48,000 33,600 67,200 38,400 38,400 62,400 38,400 72,000 48,000
Inventory carrying cost 350 350 350 350 350 350 350 350 350
Unused
PERIOD OF PRODUCTION 1 2 3 4 Capacity Capacity
Beginning 0 3 6 9
Inventory 300 — — — 300
20 23 26 29
1 Regular 600 300 100 — 1000
25 28 31 34
Overtime 100 100
28 31 34 37
Subcontract 500
20 23 26
2 Regular 1200 — — 1200
25 28 31
Overtime 150 150
28 31 34
Subcontract 250 250 500
20 23
3 Regular 1300 — 1300
25 28
Overtime 200 — 200
28 31
Subcontract 500 500
20
4 Regular 1300 1300
25
Overtime 200 200
28
Subcontract 500 500
•The master production schedule formalizes the production plan and translate it in to
specific end-item requirements over a short to intermediate planning horizon.The end
items are then exploded in to specific material and capacity requirements by the
Material Requirement Planning (MRP) and Capacity Requirement Planning (CRP)
systems. Thus the MPS essentially drives the entire production and inventory system.
Importance of MPS
A production plan is an aggregate plan that schedules product families in relatively long time
intervals. Master production schedule is used for individual end products and in shorter time
intervals.
MPS is important in the following aspects:
• It is the link between what is expected (production planning) and what is actually to be built,
i.e., material requirement planning and final assembly schedule (FAS, to be discussed).
• It develops data to drive the detailed planning, MRP. MPS is a priority plan for manufacturing. It
keeps priorities valid.
• It is the basis for calculating the resources available (capacity) and the resources needed
(load). It provides devices to reconcile the customers’ demand and the plant’s capability
Importance of MPS
•It makes possible reliable delivery promises.
•It provides salespeople information on available-to-promise (ATP) indicating when
end products are available.
•It is a tool that can be used to evaluate the effects of schedule changes. It is a
device for communication and a basis to make changes consistent with the
demands of the marketplace and manufacturing capacity.
•It is a contract between marketing and manufacturing departments.
•It provides management with the means to authorize and control all resources
needed to support integrated plans.
•In the short horizon, MPS serve as the basis for planning material requirement,
production of components, order priorities, and short-term capacity requirements.
•In the long horizon, MPS serves as the basis for estimating long-term demands on
the company resources such as people, equipment, warehousing, and capital.
Major inputs to MPS
Question:
For given sales forecast and customer details calculate Master Production Schedule and ATP (Available to Promise)
Note: Opening inventory is: 100 Units
Production lot size: 70 Units
Minimum inventory level allowed: 0 Units
Week: 01 02 03 04 05 06 07 08
Forecast: 50 50 50 50 50 50 50 50
Actual order 52 40 20 10 5
Opening inventory (Initial Inventory) 100 48 68 18 38 58 8 28
Requirement 52 50 50 50 50 50 50 50
Net inventory before production 48 -2 18 -32 -12 8 -42 -22
Planned production volume (MPS) 0 70 0 70 70 0 70 70
Projected inventory (PAB or ending inventory) 48 68 18 38 58 8 28 48
Available to promise (ATP) 48 10 * 60 65 * 70 70
Complete the MPS and ATP
Question: Complete the following MPS
Demand period: 1 2 3 4
Units: 100 50 70 80
Inventory:
Initial: 20 units, Final: 25 units
Carrying cost: Rs. 2 / unit-period
12 3
130 0 1,000
SC 1,000
RT 100 102 50 60
60 0
Period 3
OT 125 127 0 18
10 8 0
SC 130 0 1,000
1,000
RT 100 50 65
65 0
Period 4
OT 125 0 20
20
SC 130 0 1,000
0 1,000
Demand 100 50 70 105 4,001 4,326
Total cost=
(20X0+60X100+18X125+2X130)+(50X100)+(60X100+10X125)+(65X100+20X125+8X127+12X129)