Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

78 QUALITY CONTROL

Preventing build-ups and rings


The increased use of petcoke and alternative fuels has led to higher sulphur and chloride
inputs into cement production. Effective prediction and control requires a thorough
understanding of the development of such cycles.
n by Tom Lowes, OPECS, UK and Joana Bretz de Souza, Cinar, Brazil

W ith the need to use lower-cost fuels


such as petcoke and alternative fuels
(AFs), the sulphur (S) and chloride (Cl)
Figure 1: SO3- and Cl- data from an air-through calciner with 100 blasters

inputs into the cement production process


can increase to levels where the preheater
build-up and kiln rings become untenable
and their removal requires a plant
shutdown. At this point, several options
become available:
1. Cut back on the S and Cl inputs until a
trouble-free operation is possible.
2. Optimise process operation from a
fundamental knowledge of SO3- and
Cl- cycles, install up to 100 blasters and
carry out focussed shift cleaning of the
kiln.
3. Install a Cl by-pass for either the kiln
gases or the hot meal.
4. A combination of both process
optimisation and by-pass installation.
The conventional rule based on the
maximum input of Cl- in hot meal (HM) form that are also more susceptible to SO3- cycling it produces hard
being 300mg Cl/kg clinker is also tied to the reduction and volatilisation. build-ups based on CaSO4.
SO3- input by the equation: • Hence the higher the alkalis, the • It should be noted that 0.2 per cent
higher level of SO3- input a plant can carbon (C) (normal target: 0.1 per cent
Cl-max, HM = 2 - 0.4 • SO3-HM [Eq 1] go to before major build-ups occur, C) volatilises 1.4 per cent SO3- and 0.2
for the same level of Cl. While Na and per cent C is at 96 per cent burn-out of a
where two per cent ClHM equates to K sulphates produce soft build-ups, calciner fuel.
400mg Cl/kg clinker. compounds based on CaSO4 produce • For 0.5tph of tyres with 35 per cent
This can be exceeded by optimising the hard build-ups and rings. volatiles this is at 0.3 per cent C on the
process operation (option 2), as shown in • The hot meal chemistry in terms of MR feedshelf for 100tph clinker and will
Figure 1 for an air-through (AT) calciner or excess SO3- is an important first area drive the SO3- cycles for a calciner kiln.
with 25 per cent tyre-derived fuel (TDF) fed of focus. It is in the hot meal and not in • At the higher SO3- cycling rates,
into the riser. The equation becomes: the clinker, where Cl takes the alkalis in 2C2S•CaSO4 (ie sulpho-spurrite) is
preference to SO3-, hence making way formed, and is responsible for kiln rings.
Cl-max, HM = 4 - 0.4 • SO3-HM [Eq 2] for the less thermally stable species. • But without avoidance of reduction
in both the burner and the after-
The fundamentals and control of Key drivers calcination zone plus hard burning, high
SO3- cycles and build-up Two key compounds that form in the SO3- inputs will produce bad build-ups
To understand the reasons for the build- calciner and after calcination zone drive and/or rings.
up on a plant it is necessary to look at the SO3- cycles: • When there is an excess of SO3- over
fundamentals of SO3- cycles: • langbenite (KL) – K2SO4.2CaSO4 – is alkalis in the clinker, then hard burning
• Na2SO4 and K2SO4 are quite thermally thermally stable to 1520˚C in O2. or a combinability temperature (CT)
stable and need temperatures greater • calcium sulphate – CaSO4 – is greater than 1450˚C breaks down the
than 1600˚C for complete volatilisation, thermally unstable >1420˚C in O2 but CaSO4 and increases SO3- cycles. This
but when there is an excess of SO3- – at 900˚C (end of calcination zone in then increases the excess SO3- in the hot
molar ratio (MR) >1 – over alkalis, less the kiln) under reducing conditions, C meal and increasing build-up can often
thermally-stable SO3- compounds + CaSO4 = CaO + SO2 + CO. Due to more lead to kiln rings.

©Copyright Tradeship Publications Ltd 2017


INTERNATIOINAL CEMENT REVIEW JULY 2017
QUALITY CONTROL 79

Figure 2: combinability temperature of clinker as a function of LSF and +90µm AIR Figure 4: kiln ball formation

Figure 3: coating behaviour • there is insufficient liquid phase (LP),


which should be between 25-26 from:
LP [%] = 3.0 • Al2O3 + 2.25 • Fe2O3 + MgO
AR
(max 2%) + Na2O+ K2O
Thick coating clinker ball Very thin coating • there is a MR in the clinker >1.5,
or sinter ring formation Dusty clinker due to the excess SO3- going into the
(plenty of viscous melt phase) (little of viscous melt phase) LP (and not into the alkali sulphate
1.9 liquid phase). This reduces the LP’s
Normal viscosity and surface tension and hence
1.6 coating produces less nodular clinker.
• when reducing conditions occur in the
1.3 burning zone. This does not allow the
Thin coating Thin coating SO3- to combine with alkalis and hence
refractories attack (little of fluid melt phase) more goes into the LP.
(plenty of fluid melt phase) • the CT is high and hence the surface
tension and viscosity are less.
Resolving build-up and ring issues will
2.2 2.5 2.8 SR generally make the clinker less dusty.

Kiln balls
Excess SO3- in the hot meal • reducing conditions from the kiln Kiln balls are the most difficult of build-up
Excess SO3- in the hot meal is increased by: burner issues to resolve. They have two causes.
• AF dropping through to the feedshelf • hard burning or a high CT. Figure 2 Firstly, the clinker chemistry is such that it
or unburnts in the hot meal shows how the variation in clinker is in the ball formation region (see Figure
• tyres on the feedshelf lime saturation factor (LSF) and acid 3). Secondly, poor combustion in the kiln
• unburnt matter from the calciner in insoluble residue (AIR) for the raw and calciner are such that a circulation of
the hot meal (>0.1 per cent C) material +90µm (quartz) can readily high amounts of alkalis and SO3- is building
Target excess SO3- to less than one per cent drive the CT greater than 1520˚C. up and breaking away so intensely that it
in hot meal. • Even when the SO3- is not in excess nodulises and produces balls.
• The calculation of excess SO3- is: in the clinker, a low-momentum kiln As kiln balls are not often found
SO3-exc = SO3-HM - 1.29 • (Na2OHM, eq - 0.9 • burner, low kiln back end (KBE) O2 (see Figure 4), it is difficult to produce
Cl- HM) and or a fuel (normally an AFR) being general rules. However, based on limited
• The excess SO3- to the KL as CaSO4 is: allowed to drop into the burning zone experience, it is possible to conclude the
2 • (K2O HM - 1.33 • Cl- HM) • 80/92 can drive SO3- to the hot meal. It then following:
• SO3- in excess of this is CaSO4 on its becomes excess SO3- over alkalis and • A poor control of Fe2O3 can take an
own and very susceptible to carbon gets driven into higher SO3- cycles and average normal clinker composition to
reduction greater than 900˚C. build-up by the reducing conditions in the clinker ball region by decreasing its
the hot meal or on the feedshelf. silica ratio (SR).
Excess SO3- in the clinker • Unburnt matter in the hot meal and
Excess SO3- in the clinker can be volatilised Dusty clinker low KBE O2 can produce internal cycles,
by: Dusty clinker is produced when: leading to kiln balls.

©Copyright Tradeship Publications Ltd 2017


JULY 2017 INTERNATIONAL CEMENT REVIEW
80 QUALITY CONTROL

Figure 5: sticky factor values for different cement plants • K2O = 0.6
• Na2O = 0.2
• Cl- = 0.04 per cent
resulting in hot meal
values of:
• SO3- = 2
• K2O = 1.2 + 2.66
• Na2O = 0.3
• Cl- = 2 – (HM Cl- can be
predicted from: 50 • % Cl-
on clinker input without a
bypass)
This gives a SF of 8.16.
Generally, from experience
an SF of 8 is the maximum
a plant can run at without
severe disruption or
stoppages.
Figure 5 shows data
from a range of preheater
and calciner plants,
compared to predicted
values. This highlights
several plants to have
• A low burner momentum can set up Predict the required hot meal severe build-up issues with sticky factor
cycles that produce balls. SO3-, Na2O, K2O and Cl- values greater than they should be for a
The authors have resolved kiln ball The volatilisation factors (VF) are simply: well-managed and controlled operation.
issues by modifying the plant’s operation. • for SO3-: VF SO3 = SO3-HM / SO3-clk Table 1 shows a typical calculation
One cement plant received assistance to • for K2O: VF K2O = K2O HM / K2O clk where the green values represent the
eliminate each of the above issues. Initially • for Na2O: VF Na2O = Na2O HM / Na2O clk. predicted hot meal values from the clinker
the burner momentum was increased and For a well-operated calciner or data and Cl- input, the orange values
the AFR injection in the calciner modified, preheater kiln the target volatilisation are the plant hot meal data, and the red
which solved the presence of kiln balls. factors for its volatile compounds are: highlighting danger.
However, the issue returned six months • SO3- = 2
later and improved Fe2O3 control resulted • K2O = 1.8 Solving build-ups
in the required outcome. • Na2O = 1.5 To solve build-up issues, it is
In another cement plant, kiln balls • Cl- = 50. recommended that cement plant
developed when SO3 circulation became However, in the presence of Cl-, K2O is operators adhere to the following
too high, driven by a poor calciner fuel much more volatile and its volatilisation is methodology:
burn-out, as indicated by an increased increased by 1.33 • Cl- HM. • First check with the plant and its
SO2- (and picked up by the plant’s online All these added together is an indication of operators what the build-up or ring
SO2 measurement) and increased hot the sticky factor (SF) of the preheater. issue is and where it is occurring, so the
meal carbon. Balls were eliminated by the The plant in Figure 1, has values on problem to be solved is clear in one’s
operators increasing the KBE O2 until the clinker input of: mind.
SO2 levels came to < 3000ppm. • SO3- = 1 • Calculate the daily average VF SO3,

Table 1: sticky factor calculation

It is possible to calculate a good sticky factor from the Cl-HM and the clinker chemistry, plus HM KL and CaSO4

VF VF target Plant data Predicted from VFs Actual plant info and calculations

VF SO3- 2 Clk SO3- 0.72 HM SO3- 1.44 9.95


VF Na2O 1.5 Clk Na2O 0.35 HM Na2O 0.53 0.33
VF K2O 1.8 Clk K2O 0.91 HM K2O 1.64 2.97
VF K2O Cl -
Cl HM x 1.33
-
HM Cl -
0.90 HM K2O w Cl -
1.21
Clk MR 0.59 HM Cl- 0.90 0.90
Inputs HM SF 5.72 14.15
Calculations Na2O eq 2.40 2.29 As KL As CaSO4
Calculations of danger levels Excess SO3 -
-0.61 8.05 3.08 4.97

©Copyright Tradeship Publications Ltd 2017


ICR JULY 2017
82 QUALITY CONTROL

Figure 6: SO3 in raw meal (RM – blue) and clinker (CLK – orange) • Check KBE NOx and CO vs KBE O2. The
NOx peak should be at two per cent O2
and the CO should not begin to increase
before 1.5 per cent O2.
• Check the CT of the raw material. The
acid insoluble residue and clinker LSF
are the main drivers of high CT, first
target less than 1470˚C.
Following this methodology it should be
possible to ascertain if the problem is due
to: a. reducing conditions in the hot meal/
feedshelf, b. driven by the kiln burner and
its operation, or c. down to a combination
between raw material chemistry and its
combinability temperature.

Case studies
Below are three recent case studies where
the solution to build-up and rings have
been outside the problem-solving scope
of the plant or corporate resources and
Figure 7: excess SO3- over soluble alkalis and potassium langbenite SO3- capture potential the authors were asked to help resolve the
issue.

Case 1 – intermittent ring formation,


causing up to 10 shutdowns per year
Looking at the hot meal, raw meal and
clinker it was found that the VF SO3 was six
and the total SO3- in was not being seen in
the clinker as shown in Figure 6.
The plant was a preheater plant with no
combustion in the riser. The assessment
of the kiln burner showed the momentum
and the O2 to be adequate. However, it
was found that the input SO3 from the raw
materials was variable, which often meant
that the clinker MR was >1 and sufficiently
high to saturate the KL level and from
CaSO4 as shown in Figure 7.
This became an issue when it was
found that the clinker LSF had a standard
deviation (SD) of two per cent and the
which should be two with a maximum MW) against burning zone thermal +90µm AIR for the RM varied from three to
of three. Plot the clinker SO3- measured load (should be twice this level or O2 six per cent, meaning CTs well in excess of
against the expected clinker SO3- from stratification will occur in the kiln back 1500˚C.
the mass balance. This should match on end and not assist in burnout of hot The solution was first to add alkalis to
a daily average basis. Calculate SF and meal carbon). the mix as needed to avoid excess SO3- as
compare to what it should be. • Look for reducing conditions in the required. Then longer-term action was
• Check the calciner combustion clinker. Keep in mind that often there taken to improve the LSF control and
performance from a plot of CO vs O2. is reduction that cannot be detected reduce the +90µm AIR to <2 per cent.
The CO should be <500ppm at two per by visual inspection or FeO test.
cent O2 with hot meal carbon (HMC) Hence, checking XRD for orthorhombic Case 2 – plant targets full thermal
below 0.1 per cent. A visual inspection C3A, clinker for insoluble alkalis plus substitution in riser but build-up
of the sample on a white paper can be microscopy may be necessary. limits rate
used in the absence of a Leco. It should • The maximum insoluble alkalis for a The second case study shows a plant
be noted that depending on the calciner good flame is 0.01 • C2S if the SO3- is in that is seeking to achieve a thermal
type, its fuel and residence time, as well excess of the remaining alkalis, with the substitution rate (TSR) of 100 per cent, but
as the exit O2, the stratification in the maximum orthorhombic C3A being: as a result of build-up issues is unable to
calciner may need to be overcome to C3A OR, max = (Na2O eq - 0.01 • C3S - SO3- reach beyond the 50 per cent mark.
meet the target 0.1 per cent HMC. /1.29) • 11.75 when the alkalis are in Figure 8 shows the current plant’s
• Check kiln burner momentum (N/ excess. hot meal operation well above the

©Copyright Tradeship Publications Ltd 2017


INTERNATIONAL CEMENT REVIEW JULY 2017
QUALITY CONTROL 83

Figure 8: plant hot meal Cl- vs SO3- Figure 9: combustion of TDF and nutshells – (a) TDF <25mm, (b) TDF
>25mm, (c) nutshells

established easy-to-operate region. The • Stop using


plant has no by-pass and uses >50mm whole tyres or
TDF and nutshells in the calciner from the install the fingers
same feed points and whole tyres on the system developed
feedshelf. by Blue Circle data were checked to see whether the SD
Figure 9 shows the combustion of the Industries of the LSF was at an acceptable level and
TDF and the nutshells. Only the ≤25mm • Relocate the AFR feed to below the showed no trend with free lime. The hot
TDF fraction combusts in the calciner, the splash boxes and modify the splash meal was checked and found to be OK and
>25mm fraction drops to the feedshelf. boxes to a two-step meal approach as below the Cl-HM = 2 - 0.4 • SO3- rule, with a
The nutshells reach the exit and only developed by PM-Technologies. VFSO3 of 1.7 and SF of only 4.7.
achieve a burn-out of 70 per cent. This • Increase the momentum in the sleeves However, on detailed checking of the
poor combustion, together with the whole of the calciner burners. normal hot meal data it was found that the
tyres on the feedshelf and the SO3- and Cl- • Install a bypass to take out 300mg excess SO3- in the form of CaSO4 was close
levels in the hot meal, lead to a difficult to Cl/kg clinker which is at three per to the danger level of >1 per cent, as shown
operate situation. cent. This can be easily implemented in Figure 10.
The AFR is inserted from only one inlet with a hot meal by-pass (80 per cent The set-up at the plant is as follows:
above the splash boxes. This quenching less expensive than a gas bypass) as • The burner has a low momentum. •
plus the mixing of the O2 results in developed and installed on several The calciner – similar to Case 2 – has the
combustion issues. To achieve a 100 per plants by PM-Technologies. coal just below the splash boxes on the
cent TSR the plant will need to: back wall.
• Install a venturi with approximately Case 3 – plant with intermittent rings • The tertiary air duct (TAD) setting and
2m length to promote gas velocities of and high free-lime flushes operation can deprive the kiln burner
35m/s to stop the TDF dropping to the Intermittent phenomena are the most of O2.
feedshelf. difficult to resolve. In this case, the clinker • The coal, some of which is sourced
locally, can be difficult to grind to the
Figure 10: hot meal excess SO3-, potassium langbenite and CaSO4 required fineness.
This combination of these factors can
result in the low burner momentum to give
a stratified KBE O2 at a low level depending
on TAD damper setting, which with a
difficult to burn coal will have a C HM of
>0.1 per cent. This will not burn out the
kiln, setting up bigger SO3- cycles that will
lead to flushes and rings.
Currently two measures are being
taken to resolve the issue. Firstly, a kiln
burn design has been selected to give a
non-stratified KBE O2, with a momentum
of 10N/MW. In addition, the coal injectors
have been moved to below the TAD’s
inclined down at 30˚ and a primary air (PA)
sleeve has been installed around the coal
injectors with seven per cent at 200m/s. n

©Copyright Tradeship Publications Ltd 2017 JULY 2017 INTERNATIONAL CEMENT REVIEW
SUBSCRIPTION PACKAGE INCLUDES:
12
 ISSUES OF INTERNATIONAL CEMENT
REVIEW (ICR) – the cement industry’s leading Annual subscription rates:
monthly publication, delivered direct to your
desk by 1st Class Airmail with early access
GBP 195 / USD 315 / EUR 260
via CemNet.com. Each issue of ICR includes
market reports, technical articles, informed
commentary and much more...

 FR
EE HANDBOOK! Choose either the
Cement Plant Environmental Handbook,
2nd Edition or The Cement Plant Operations
Handbook, 6th Edition (fully-revised).
Building
 bulletin newsletter
Monthly newsletter covering the latest
developments in the building materials sector –
complimentary to all ICR subscribers.
ICR
 SUBSCRIBER DISCOUNTS
on all other reference works published by ICR.

PLUS For further information or to


Unlimited access to CemNet.com subscribe, please contact:
the leading industry website Tel: +44 (0) 1306 740 363
Fax: +44 (0) 1306 740 660
n Full
 digital issues of ICR available in
advance of the print edition Email: subscribe@CemNet.com
Website: www.CemNet.com/subscribe
n Over
 five years of online back issues
n Daily
 news service and 12-year The monthly new OCTOBER 2016

searchable ICR news database sletter covering ISSUE 226


n
the building materials
sector
Housing start jitte
rs in UK, USA, Canada
THE NUMBER
OF housing starts
and Japan Contents

Access to Corporate Watch and


significantly in and new planni
the first six month ng applications

n real estate service s of 2016, accord in central Londo


s and investment ing to JLL, a specia n dropped Lime industry contin
starts across centra management.
The closing quarte
list in commercial ues to innovate
l London, falling r of 2015 saw 5260 Steel decline hits
representing a to 1840 in 1Q16 sector hard
slowdown of 65

Market Reports section
and declining 2
area also contra per cent. The numbe further to 1830
cted, falling from r of units under in 2Q16, Aggregates consum
recorded in four 34,300 in 1Q16 construction in
the
ption to hit 62Bnt
years. to 33,920 in 2Q16, Growing trend
“It is true to say the first quarte for recycl ed
that the numbe rly drop
of 2015, but the r of starts was aggregates
new additional beginning to ease 2
reverse all the home Stamp Duty slightly toward
good work of the charge and the s the end Cemex opens new
JLL. The perfor past few years,” says Brexit decisio n look set to UK quarry
mance is report Neil Chegwidden, New sand and
gravel quarry

Cement Plant Directory


US housing starts edly representativ director of researc
also fell more e of the wider h, serve Nottingham to
trend across Greate

n
than expected


two straight month in August as buildin r London. shire
s of growth. Accord g activity decline 2
fell 5.8 per cent
in August, compa
ing to the US Comm
erce Department, d after New concrete standa
Building permit red to the previo housing starts rd from ASTM
s also dropped, us month, to an
annual rate of
International stand
Both came in below falling 0.4 per 1.142m ard to improve
economist predic cent to a seasonally-ad . concrete produ
part by a sharp tions. The August justed level of ction
decline in the south, decrease was 1.139m.
reportedly driven 2
There was some which was hit CECE congress predic

Video presentations
good news with by heavy rain and in
in August, its largest permits for single- flooding. ts growth

n the year so far,


Housing starts
gain since June
with single-family
in Canada also
2014. This put
starts also record
declined in August
family homes
single-family permit
ing a rise of 9.1
increasing by 3.7
s up by 8.4 per
per cent in 8M16.
per cent
cent in
European constr
sector to expan
uction machinery
d by 5-10% in
2016 3
slowed in most
regions, led by as construction Zimbabwe tackle
Mortgage and lower activity of multi-unit dwellin s pavement crisis
Housing Corpor in Alberta and Manitoba, gs Calls for concre
adjusted annua ation (CMHC).
August housin according to Canad te to replace aspha
l rate (SAAR) of g starts were at a as road netwo lt
six-month moving 182,703, down a seasonally- rk crumbles
average for housin 6.5 per cent from 3
July’s rate of 194,66
cent when compa g starts in August 3. The Accenture launch
111,378, falling
red to July’s rate
of 201,379. Multip
was a SAAR of
195,640, a fall es new apps
in the Prairies, le urban starts of 2.8 per New digital servic
in Quebec. Single British Columbia, slowed by 7.3 per es for OEMs
detached urban Ontario and Atlanti cent to 3
were estimated starts were record c Canada but increas Breedon Group scoops
at 14,824 units. ed at 56,501 units
while rural starts
ing AIM award
Meanwhile, in
Japan, although Recog nised for Hope

Daily and weekly


lower pace than housing starts transaction
expected. Follow rose in August 3
a rise of 7.29 per ing a spike in July the growth was Caterpillar: US$1b
cent in August of 8.9 per cent, at a much n Africa expansion
the Ministr y of , but the real figure analysts had predic Reveals long-t
Land, Infrastructure came in at 2.5
per cent,
ted erm investment
contractors, howev and Transport.
Construction orders according to
3
er, surged by 13.8
received by 50
CDE and Cemex clean
the previous month per cent in August up aggregates

newsletters
. , following a 10.9 big
per cent plunge Four new UK washi
in ng projects
4
Japan hikes infrastru LafargeHolcim and
XtreeE
in 3D first
cture spend by extr
Choice of a
3D printed concre
JAPAN’S PARLIA
MENT HAS approv
a US$32bn
te structure
British Gypsum upgrad
4
under Prime Ministe ed a further US$34 es Selby site 4
r Shinzo Abe’s bn to fund infrast UK pledges GBP3b
US$61bn pledge economic stimul ructure spendi
d in August this us package. This ng n to tackle housin
number of tourist year to revive the is in addition to
the New initiative g
Japanese econom from Kier Living

FREE handbook
s visiting the countr y by doubling the
Summer Olymp y. With the aim 4
ics in 2020, the
spending will be
of reaching 40m
visitors by the EQAR win for GB
accommodate
large cruiseships concentrated Tokyo Energy Holding
2020, boosting and increase passen on expanding
ports to 4
airport capaci ger numbe rs from 1.1m in
transportation ty in the Tokyo 2015 to 5m by Building Bulleti
hubs. area and region n is published
al economies, monthly by:
The government and strengthenin International

www.CemNet.com
Osaka magnetic
will also provid
e loans to help
g Old King’s Head Cement Review
levitation link bring forward Court, 15 High
Tokyo-Nagoya by eight years, the completion Dorking, Surrey Street,
segment of the from its origina of a Nagoya- , RH4 1AR, UK.
route is due to l completion date Tel: +44 (0) 1306
to start constr open in 2027 while of 2045. The 740363/383
uction in 2035. the extension Fax: +44 (0) 1306
to Osaka is set Email: info@C 740660
ICR BUILDING BULLET emNet.com
IN n OCTOBER www.CemNet
2016 .com

Delivering business insight, market knowledge and technical expertise to the global cement industry

You might also like