Project Name :

Location :
Trade : Fire Protection System

MATERIAL COST LABOR COST


ITEMS DESCRIPTION OF WORK QTY UNIT TOTAL COST
UNIT COST AMOUNT UNIT COST AMOUNT
I. General Requirements
A Temporary Facilties, Utilities & Expenses 1 lot
B Mobilization / Demobilization 1 lot
C Contractors tax 1 lot
D Plans 1 lot
E Mechanical Permit (Professional Fee) 1 lot
F Bonds & insurances
Surety bond 1 lot
Performance bond 1 lot
Warranty bond 1 lot
CARI 1 lot
G Supervsion 1 lot
H Safety Requirements 1 lot
I Testing and Commssioning 1 lot
Others Specify; -

Sub-Total I. -
II A Black Iron Pipe (Eagle,Supreme,Superior or Approved equal)
50 mm Ø lm
40 mm Ø lm
32 mm Ø lm
25 mm Ø lm
Fittings lot
B Adjustable Ring Hanger & Support lot
C Miscellaneous Materials & Consumables lot
Others Specify

Sub-Total II. -
III Sprinkler Heads (UL Listed/FM)
A Pendent Head w/ Escutcheon pc/s
B Upright Head w/ Escutcheon pc/s
C Side Wall Head w/ Escutcheon pc/s
D Miscellaneous Materials & Consumables lot
Others

Sub-Total III. -
IV Fire Hose Cabinet Assembly (UL Listed/FM) pc/s
Miscellaneous Materials & Consumables lot
Others Specify;

Sub-Total IV. -

GRAND TOTAL AMOUNT


-

Prepared by: