Professional Documents
Culture Documents
Kick Tolerance Paper 4
Kick Tolerance Paper 4
Summary. The minimum acceptable kick tolerance can be quantified on the basis of the likelihood and consequences of an underground-
flow well-control incident. Safe and economical casing points can be selected on the basis of the minimum acceptable kick tolerance
required to drill the next hole section. For sections with a known but manageable underground flow potential, necessary unconventional
well-control contingency plans can be developed. This new approach to well control has the potential to reduce drilling costs by signifi-
cantly reducing the likelihood of major drilling-related well-control incidents.
Introduction
The progressive stages of a well-control incident that gets out of than the intersection point of a gas gradient line drawn from total
control may be as follows: drill into a permeable gas zone under- depth (TD) and the fracture gradient line on a depth-vs.-pressure
balanced, take a kick, shut in, exceed the maximum allowable shut- plot (Fig. 1) will enable a well to be shut in on any size kick without
in casing pressure, watch drillpipe pressure drop to zero as an under- fracturing the formation. If the well does not fracture in the open
ground flow begins, and watch casing pressure increase until equip- hole after taking a kick, then an underground flow situation cannot
ment failure leads to a surface blowout. During drilling at a given develop. In most cases, this will require the casing to be set only
depth below the last casing shoe, a measure of the potential for such a short distance above zones that can flow. This conservative prac-
a scenario is the remaining kick tolerance. 1 However, a direct tice is very costly, and there is a risk of reaching the final available
tradeoff exists between kick tolerance and weIl cost: specifying casing point before reaching the well's planned TD. On the other
higher-than-necessary minimum acceptable kick tolerances can in- hand, having zero shut-in kick tolerance is the least conservative
crease the weIl cost because additional casing strings will be re- approach to casing-point selection. This will barely allow mud to
quired. Specifying smaller-than-necessary minimum acceptable kick be circulated. Any pressure increase from a kick in the wellbore
tolerances can lead to costly well-control incidents. annulus will cause a fluid loss at the shoe-i.e., underground flow.
This paper presents a new strategy for determining the adequacy There is no safety factor for this scenario.
of a given kick-tolerance value that is based on the well-control The greater the shut-in kick tolerance desired at any given depth,
consequences of underground flows from gas zones in the given the deeper the last casing must be set. For a given shut-in kick toler-
hole section. This strategy helps to optimize well costs by manag- ance, any combination of a larger kick volume or a higher forma-
ing the well-control risks better than selecting an arbitrary minimum- tion pressure would result in underground flow. Consequently, in
kick-tolerance value. the well-design process, the shut-in kick tolerance used has to be
acceptable for well-control purposes but also allow the well to be
Well Control In the Well.Planning Phase drilled economically with the required minimum casing size across
The well-control consideration is an important aspect in casing-point the pay zone. For example, Fig. 2 shows a casing point selected
selection during the well-planning procedure. The casing scheme on the basis of a specified shut-in kick tolerance value with a spec-
is developed as a function of pore pressures, fracture gradients, ified influx volume of gas. (Notice that the resulting casing point
wellbore stability considerations, and well-control aspects. to reach TD is shallower in Fig. 2 than in Fig. 1.)
The well-control aspect is expressed by the minimum acceptable The criterion for the minimum acceptable shut-in kick tolerance
kick tolerance required during drilling to the next casing point. for a wellbore section must be set according to how well the pore
pressures are known and the risk one is willing to take. The risk
Shut-In Kick Tolerance. It is defined as the kick intensity (for- of setting too little casing is that underground flow will result. The
mation pressure increment above the mud weight in use, usually risk of being too conservative is having to set additional strings of
expressed in pounds per gallon) that can be shut in without exceeding casing to reach TD. Both will increase drilling costs. Hence, there
the fracture pressure of the weakest exposed formation after a given is an optimum shut-in kick tolerance that minimizes the cost of each
kick volume of a given fluid density has entered the wellbore. 1-4 hole section of a well. Fig. 3 illustrates that the optimum shut-in
Dc(PmF-P m ) Z(Pm-Pj) kick tolerance depends on the underground flow potential of zones
K=----- - - - - " - . . .................... (1) in the hole section being considered.
D D
Circulating Kick Tolerance. It is defined as the kick intensity that
By specifying the expected influx density and the influx volume
can be circulating out without rupturing the formation or bursting
that can be readily detected and shut in by a given rig drilling a
the casing after a given gas kick volume has been allowed to enter
given hole size, the shut-in kick tolerance can be calculated and
the wellbore. 3 ,4 Gas expansion is responsible for the increasing
monitored continuously as drilling operations progress. Unless there
annular pressures required when the kick is circulated out to main-
is a pore-pressure regression, the next casing string has to be set
when the shut-in kick tolerance has fallen to a specified minimum tain constant bottornhole pressure (BHP). The larger the gas kick
acceptable value. A minimum shut-in kick tolerance of 0.5 Ibm/gal volume, the larger the volume of mud that has to be bled off and
is a common design criterion used as a starting point for selecting the higher the resulting backpressure that has to be maintained during
casing points in Mobil wells. 5 For wells linked to the Drilling Data circulation of the kick out of the well.
Center in Dallas, the shut-in kick tolerance is computed and moni- The four factors that control the magnitude of the pressure load
tored in real time. 6 The default influx volumes used by the Drilling imposed on the wellbore while a gas kick is circulated out are the
Data Center are 20 bbl of 2-lbm/gal gas for 12IA-in. and larger influx volume, the wellbore geometry, the kick intensity indicated
hole sizes and 10 bbl of 2-lbm/gal gas for smaller hole sizes. by the initial shut-in drillpipe pressure (SIDPP), and the kill proce-
The most conservative approach to casing-point selection is to dure used to circulate the kick out. Hence, for a given well design
prevent any possibility of underground flow. Setting casing deeper and kill procedure, downhole loads from circulating out a gas kick
can be limited in magnitude only by limiting the kick intensity and
Copyright 1991 Society of Petroleum Engineers the kick volume.
GAS GRADIENT
~
w
o
~w
o /
Fig. 1-Casing-point selection for no flow at the shoe. Fig. 2-Casing-point selection using shut-in kick tolerance.
If the formation pressure is much larger than the mud hydrostatic (e.g., at a depleted zone), or at the surface. If the combination of
pressure (indicated by a high SIDPP), this high differential pres- the initial kick volume and the kick intensity (initial SIDPP) lies
sure will produce a high initial shut-in casing pressure so that only to the right of the boundary curve and an attempt is made to circu-
a small gas-kick volume can be circulated out. On the other hand, late out the kick, formation or casing rupture and underground flow
if the mud weight is adequate for the formation pressure, the re- could result. An underground kill procedure would then be nec-
sulting very low shut-in casing pressure (with zero SIDPP) will per- essary.
mit circulation of a large swabbed gas-kick volume out of the well. The evaluation of the circulating-kick-tolerance curve, as part
Because the combination of only intensity and volume dictates the of the normal well-design process, determines whether the allowa-
effective loads on the wellbore, a spreadsheet calculation can de- ble kick tolerances are within a reasonable range or whether an al-
termine the maximum allowable kick volume that can safely be cir- ternate well design must be considered. Additionally, an up-to-date
culated out as a function of the kick intensity (and vice versa) for well-depth-dependent circulating-kick-tolerance curve, similar to
a predetermined maximum load on a known weak point in the well- Fig. 4, would be very useful for a rig supervisor. It could be used
bore. 7 A series of maximum kick-volume/intensity combinations immediately after taking a gas kick to determine whether to pro-
can be determined as functions of the changing hydraulic pressures ceed immediately with a conventional kill procedure or whether
in the annulus during circulating out a kick such that, when ex- preparations should be made to implement an underground-flow
ceeded, the wellbore will break down at the specified weak-point kill procedure.
depth (generally the last casing shoe).
As illustrated in Fig. 4, the higher the initial shut-in pressure, Underground Flow Potential Evaluation
the lower the tolerable gas-kick volume before the circulating-kick- Some situations require drilling with a very low kick tolerance, thus
tolerance boundary is reached. The critical weak point of the well- increasing the chance of taking a kick that will break down the casing
bore may be in a formation with a low fracture strength, in the casing shoe. The determination of "adequate" kick tolerance is a difficult
3000
i 2500
W
II:
Minor Underground :::>
~ 2000
Flow Potential UI
g:
~ 1500
~
,:
~ 1000
Z
No Underground 5 500
Flow Potential : No flow Kick Tolerance ill
!/
Kick Tolerance
50 100 150
KICK SIZE, bbl
200 250
Fig. 3-Risk evaluation for casing-point selection. Fig. 4-Example circulating-kick-tolerance boundary.
killmud
after a successful
OH section is
kill, the open hole
lull of influx
seciion is full of kill
medium mud
Substituting Eq. 2 into Eq. 3 and dividing by the drawdown gives mud pumped out of the drillpipe reaches the fractured formation,
the downhole PI, J, in gal/(min-psi): the required pump rate, qmOH, is given by Eq. 7.
kh(pws +Pwf)
J -----'---"---. . ........................... (4)
9.69/1ln(re/r w)pwf
The fluid properties and the radius of drainage for a given gas
reservoir are less important factors and can be estimated without
introducing significant errors into the downhole productivity cal-
C
_2J(Pmk +PF-PWS)(Pmk
Pf Pf
C
-c) ] ........... (6)
culation. On the other hand, the factors of reservoir permeability,
k (in darcies) and reservoir thickness, h (in feet) are significant vari- J(C+PF-Pws)2
ables. The product kh (also called flow capacity) varies significantly and qmOH= -(-Pm-k-- - - - ) - ' .................... (7)
from one reservoir to another. By substituting re/rw=2,OOO ft and C
2 --+PF-Pws
/1=0.027 cp (values typical for gas reservoirs 9 ) into Eq. 4 and con-
Pf
sidering only small drawdowns (i.e., Pws+Pwf"",2Pwf), a simpli-
fied PI equation as a function of only kh is obtained:
where C=(VanPfcos Q> )/A.
J"", 1.006kh. . ..................................... (5)
Hence, the PI of a gas zone flowing underground is approximately Note that to evaluate the "killability" of underground flows in-
proportional to the product of the formation's permeability and thick- vol ving gas reservoirs, substituting J = 1.006 kh from Eq. 5 and
ness, kh. If this product is low, there is a good probability of stop- Pf =2.0 Ibm/gal (gas density at downhole conditions 9 ) into Eqs.
ping the flow with the available rig equipment. The chances diminish 6 and 7 will produce reasonable first approximations for the range
if the number is high. By estimating the kh value for a potential of kill mud flow rates required.
gas zone to be drilled, you can determine whether an underground Fig. 7 shows example plots of pumping rate required vs. kill mud
gas flow from the zone could be controlled (i.e., killed) with the weight. The flow-rate/mud-weight combinations on the lower,
available rig equipment or whether additional pumping units or a "infinite-volume" curve, developed from Eq. 6, may be relatively
relief well would be required. The adequacy of a given kick toler- easy to achieve on location. However, an infinite or very large
ance can be evaluated on the basis of these results. volume of kill mud would be needed. The Eq. 7 combinations (de-
By neglecting any two-phase-flow liquid-holdup effect and any fined by the upper "1 OH annulus" curve in Fig. 7) will kill the
friction in the openhole annulus while an underground flow is killed underground flow as soon as the first kill mud reaches the frac-
(these are small pressure-drop effects compared with the hydro- tured formation-usually at the previous casing shoe. These high-
static pressure of the kill-fluid/influx mixture), it can be shown that flow-rate requirements, however, may not be achievable because
the kill-mud density/rate combination required to kill underground of rig equipment limitations. Any flow-rate/mud-weight combina-
flows is dependent on the volume of kill mud available. To calcu- tion within the shaded area between the two curves would fulfill
late the volume needed for a given kill-mud density/rate combina- the requirements to kill the flow; larger volumes of kill mud are
tion requires a timestep numerical integration procedure to track required as the selected point becomes closer to the lower, infinite-
the changing influx flow rate that results from the changing density volume curve.
of the fluid mixture in the annulus. 10 However, explicit equations If the pump rate required for an effective kill with a given kill
can be derived for two extremes of mud volume available. 10 To weight mud can be provided by the available rig equipment, then
stop the flow with an infinite volume of kill mud, the required pump the result of an underground flow would not be too serious. Fig.
rate, qmf¥)' is given by Eq. 6. To stop the flow when the first kill S shows an example case where the flow capacity of the rig equip-
7800
w
a: 7600
~w
BHP reqUIred to kill well
If B 7400
a.
::e
::;)
H
a. P
7200
p
s Mud enters tracture
i 7000
Fig. 11-Pump pressure curves for an underground flow kill 4600 Initial Pump Pressure
operation.