Professional Documents
Culture Documents
Environmental and Waste Management Plan (EMP) - 1
Environmental and Waste Management Plan (EMP) - 1
Client’s Logo
PROJECT TITLE:
DOCUMENT TITLE:
ENVIRONMENTAL MANAGEMENT & POLLUTION PREVENTION PLAN
DOCUMENT NUMBER :
Document Type
Country and Facility And Equipment Sequence
Code Originator Discipline Subtype Location Number
Approve
Rev. Date Description By Checked
d
M10 – PHASE 1
1
PROJECT TITTLE Environmental Management Plan
ENVIRONMENTAL MANAGEMENT PLAN
2
PROJECT TITTLE Environmental Management Plan
4.3.3 Chemical Spill to Water.................................................................................25
4.3.4 Chemical Spill to Land..................................................................................25
3
PROJECT TITTLE Environmental Management Plan
1.1 Objectives
Protection of the environment is of principal concern to VCC, thus making the
environmental aspect of the Health, Safety and Environmental (HSE) Plan an essential
part of the PROJECT. The objective of this document is to:
4
PROJECT TITTLE Environmental Management Plan
Spill Response Plan
This Environmental Management and Regulatory Compliance Program will apply to all
sites under the management of the PROJECT Project Team and to subcontractors that
provide services to PROJECT.
5
PROJECT TITTLE Environmental Management Plan
Risk Management – The PROJECT team will ensure that potential environmental
risks associated with all our designs and activities are assessed as early as is
practicable in order to minimize and manage adverse effects and to identify
opportunities for improvement.
Legislative Compliance – The PROJECT team will operate to standards that will
comply with the requirements of applicable local and appropriate national and
international legislation and codes of practice and will strive beyond compliance and
recognize these principles as a valued way of life.
Training - Health, safety, and environmental managers and staff will be qualified
by reason of education or experience to discharge their responsibilities and will
participate in a program of continuing professional development. In addition, the
project team is committed to provide training and development on environmental
matters that is appropriate to each employee's job duties and responsibilities. The
project team will be proactive in the management of third party contractors to ensure
they are fully aware of the environmental issues and to ensure that their actions are
aligned with project environmental standards.
6
PROJECT TITTLE Environmental Management Plan
The plan will be distributed as a controlled copy to the Client, VICS Construction
Company, Government Agencies, the Project Manager, the HSE Manager and or
Environmental Coordinator, and will be freely available to all PROJECT Team members
and Subcontractors.
7
PROJECT TITTLE Environmental Management Plan
address Environmental Hazards, then the Project should develop a register to assist in
managing this aspect.
The Environmental Plan for PROJECT shall cover how the project intends to manage
those impacts identified in the EIS, and any further potential impacts and risks that arise
or are identified during project activities.
In the absence of an existing EIS then sufficient environmental data must be gathered
and-or be derived and documented, to provide the environmental context in which the
project is to be developed, and to identify and quantify where possible, the project risks
and impacts:
8
PROJECT TITTLE Environmental Management Plan
1.5 Scope
The scope of the EMP will cover the areas, populations and ecosystems which have the
potential to experience environmental impacts due to the VICS Construction Company
work processes.
Integrating social, economic and environmental concerns early on in the planning of the
project will evade impacts, remediation costs, delays and reduce risk associated with the
project.
1.6 Objectives
The purpose of the EMP is to describe the methods, processes and actions used to comply
with the appropriate laws and regulations and also describe the measures taken to
adequately mitigate these impacts. The tasks include:
9
PROJECT TITTLE Environmental Management Plan
Environmental Impact Assessment (EIA): Evaluation of the environmental effects
of the planned work activities;
Socioeconomic Impact Assessment (SIA): Evaluation of the social and economic
impacts of the project directly and indirectly on the immediate community; and
Mitigation measures: Steps taken to reduce or eliminate adverse effects on the
environment (social, economic and ecological).
We will ensure that environmental excellence is vigorously pursued and that measurable
benefits and the highest level of standards are met throughout the project lifecycle
1 .7 .1 General
This section outlines the environmental management protocols to manage, mitigate and
prevent potential impacts associated with the design, fabrication, installation and
commissioning of PROJECT.
The environmental management protocols stipulated in this plan will be consistent with
Client’s and VICS Construction Company’s environmental commitment of “no damage
to the environment”. They will also be set in the context of specific environmental
management system and targets and the industry’s environmental standards and practices.
PROJECT believe that all environmental incidents are preventable. We understand the
ecological significance of the environments and the anthropological and cultural
importance of the region and are committed to achieving positive social impact. We also
understand that design decisions made now will influence emissions, discharges and
wastes for the life of the project. While understanding budget restrictions there are some
pre-investment decisions that are good business and may save future operational costs.
VCC will incorporate these into designs and procedures as appropriate; where a
significant cost of adopting such good practice is identified, the issue will be raised with
the Client and alternatives discussed, relative to base case compliance.
Resources will be made available to ensure environmental integrity is maintained at the
highest standard in design products and at places of work. We are committed to
10
PROJECT TITTLE Environmental Management Plan
undertaking the PROJECT so that at no time will any individual or the environment be
endangered.
1 .7 .2 Risk Management
To meet the requirements of MPN, DPR, other Government agencies and regulatory
authorities; the management of environmental issues will be carried out in such a way
that all stakeholders will be left with no doubt that hazards to the environment have been
identified and appropriately managed. This will be achieved by:
1 .7 .3 Implementation Strategy
VICS Construction Company will implement this Environmental Plan throughout
PROJECT in accordance with the project Environmental Management System. In
following this plan, fit for purpose systems, practices or procedures will be utilised and
documented, or developed (where they don’t currently exist) to ensure best practice and
that environmental risks and effects are as low as reasonably practical (ALARP).
The EMP is an integral part of the Project planning and organisation and will be
championed and controlled by the management team; those with discipline responsibility
for environmental affairs are outlined in the plan, however this does not relieve line
11
PROJECT TITTLE Environmental Management Plan
managers and specific discipline engineering groups or subcontractors, whose designs or
activity may impact the environment, from their responsibilities.
1.9 Organization
Discussion of the endorsement process for deliverables during each stage of the project.
12
PROJECT TITTLE Environmental Management Plan
Evaluate the effectiveness of the environmental and socioeconomic mitigation
measures.
1.11 Training
The PROJECT HSE Training Coordinator will ensure that all personnel working on the
Project have received adequate training to enable them to perform their work
functions/tasks in a safe and efficient manner. All new staff, both PROJECT and
subcontractor personnel, will receive induction training covering relevant Project
environmental requirements at the commencement of their work.
PROJECT HSE will be responsible for the development of a site-specific training matrix.
This training matrix will include, as a minimum, training needed for individual work
functions and tasks. All training courses, together with records of personnel attendance,
will be fully documented with a view to implementing further refresher courses where
appropriate. These records will be maintained at site, and copied to PROJECT office.
Table 1 outlines typical requirements of environmental awareness training.
13
PROJECT TITTLE Environmental Management Plan
TABLE 1: TYPICAL ENVIRONMENTAL AWARENESS TRAINING
14
PROJECT TITTLE Environmental Management Plan
PROJECT HSE will operate a staff competency assurance system which sets a
benchmark for the level of competency required for the environmental management of
the MPN PROJECT.
1.12 Expectations
VICS Construction Company will ensure that all environmental legislations are
adhered to.
15
PROJECT TITTLE Environmental Management Plan
1.13 Procedures
The site-specific baseline data collection process shall be described for work sites where
an EIA or SIA has been carried out.
Mechanism for obtaining endorsement for deviation from specifications or for changing
procedures/designs is necessary.
There shall be provisions for incorporating improvements into the environmental
management system.
Programs to mitigate environmental or socioeconomic impact shall be site-specific.
16
PROJECT TITTLE Environmental Management Plan
2.1 Overview
Waste is an issue of major concern for sustainable resource use. Degradation of areas of
operation has put a strain on agriculture, fishing and economic stability of local
communities. These activities have eroded the livelihoods of many individuals.
Legislation requires that operations be conducted with proper environmental practices.
There are numerous ways the waste issue can be combated, but the waste hierarchy
should be followed for optimum results.
The volume of waste generated should be reduced during the course of the project to
mitigate the cost implication of management, treatment and disposal.
All personnel will be made aware of, and site personnel trained, to implement the
Waste Management Plan;
Wastes will be eliminated, minimised, reused and recycled, where safe to do so.
17
PROJECT TITTLE Environmental Management Plan
2.4 Waste Minimisation
The initial thrust of waste management will focus on waste elimination, followed by
waste minimisation and will include the following measures:
Making wastes available to personnel and others for reuse (where legal and safe to
do so, ensuring no liability).
General wastes will be segregated at the facility and disposed via a licensed
contractor and to a licensed facility;
Designated waste collection and storage areas will be identified and marked;
Wastes will be progressively removed from the facility and not allowed to
stockpile;
Waste collection areas will be inspected daily to confirm that waste is contained
satisfactorily.
18
PROJECT TITTLE Environmental Management Plan
Special attention will be given to hazardous wastes including eg clinical wastes,
putrescible wastes and radioactive wastes
Liquid Wastes
Liquid waste management during design, fabrication, installation and commissioning will
include the following actions:
Produced, cooling, drainage, sewage (black), domestic (grey) waters etc will be
handled via engineering design
All other waste liquids will be stored in bunded areas pending their disposal;
Design will evaluate surplus gas use or re-injection during normal operations
The sources of Greenhouse gases will be identified and reduction evaluated where
practical during design (i.e. Waste Heat Recovery, Energy efficiency, etc, will be
evaluated);
Fuel and flare, purge and pilot, elimination or minimisation strategies will be
evaluated to reduce Greenhouse gas emissions.
19
PROJECT TITTLE Environmental Management Plan
Fugitive emissions will be reduced by selection of appropriate valves and seals
and minimising the number of flanges.
2.6 Tasks
Waste shall be properly collected and segregated at each work site in order to reduce the
management costs and human and environmental impacts. A strategy for collection and
disposal will be established on a site-by-site basis so the waste can be managed
effectively. The following shall be taken into consideration:
- Collection of waste generated
- Classification of waste stream (hazardous waste, construction waste, household
waste)
- Segregation of waste on site
- Measurement of waste volumes
- Calculation of waste aggregates
- Disposal Routes
i) Collection by waste disposal contractor
ii) Collection by local authority
iii) Return to manufacturer
iv) Incineration
v) Transfer to landfill sites
vi) Treatment
- Transportation by waste contractor
2.7 Reporting
Data on all waste streams and calculation methodology related to the project shall be
accurately documented and supplied on a monthly basis by Delta Afrik and all
subcontractors.
Hazardous waste and construction waste will be recorded separately.
20
PROJECT TITTLE Environmental Management Plan
MANAGEMENT OF SPECIFIC WASTES
- Hazardous waste shall be handled with care and properly collected so that
disposal does not cause potential impacts to humans or the environment.
- A human and ecological risk assessment shall be carried out periodically to ensure
minimal or zero impact to the environment.
- Environmental Impact Assessment (EIA) shall be carried out on all sites of the
project to mitigate impact to the environment
- Municipal waste from living quarters should be separated on site and transported
for recycling purposes.
21
PROJECT TITTLE Environmental Management Plan
Subcontractor:
Employees:
- Waste segregation.
22
PROJECT TITTLE Environmental Management Plan
- A sustainable recycling methodology shall be established to reduce the amount of
waste requiring disposal.
- Limit the use of hazardous substances in order to comply with strict environmental
laws.
- Only registered and authorised substances should be used during the project.
- Banned substances should not be used in the execution of the job therefore details
of each substance shall be provided.
2.13 Recordkeeping
A system or database of information shall be developed and periodically updated to
enable tracking the amount of waste type generated and how it is managed and disposed.
23
PROJECT TITTLE Environmental Management Plan
A waste manifest system shall be utilised.
Operating waste disposal sites will maintain a database of information on the amount of
waste received and the final destination within the facility.
A Plan to include information on its software packages and sample waste tracking form
upon request
24
PROJECT TITTLE Environmental Management Plan
25
PROJECT TITTLE Environmental Management Plan
All oils and fuels will be stored in bunded areas;
The integrity of the fabrication facility and associated equipment will be regularly
inspected, audited and maintained on an ongoing basis to avoid oil leakages or
spills;
Subsea equipment (e.g. flowlines) will be designed to be resilient and have external
coating in accordance with industry standards to protect against damage from
snagging or dropped objects;
The design will include level indicators, overflow detectors, bunds or coamings and
drainage systems to prevent and contain fuel spills;
Breakaway couplings will be used on offloading hoses and export hoses will be
flushed back to tanks following offloading activities;
Unique couplings will be installed on fuel hoses to ensure correct use of lines;
Marine refuelling procedures will state specific thresholds of sea conditions where
fuelling can and can not take place;
Adverse weather (e.g. Cyclone) response strategies will be developed to protect the
environment against accidental discharges;
The location of the facility will be notified to the DPR (so it can be marked on
maps/official marine charts) to minimise the potential for collision. Facilities will
have appropriate navigation and or aircraft warning lights. Offshore facilities will
have collision radar equipment to detect nearby vessel movement;
Bunding and spill response equipment will be readily available to contain small
leaks and spills, and personnel made familiar with its use and associated waste
disposal;
Ensure Stocks of spill response equipment are available from the subcontractors.
The availability of Real-time oil spill trajectory models from the operating
company should be established;
26
PROJECT TITTLE Environmental Management Plan
All spills greater than one barrel (160 litres) will be recorded and reported
internally, to the MPN.
Chemicals will be selected based on the least potential for environmental impact.
Material Safety Data Sheets (MSDS) will be readily available for all chemicals at
the facility and at the worksite;
All hazardous chemicals will be stored within bunded areas (onshore this typically
will have a volume of at least 110% of the volume of the largest vessel Offshore
this may not be practical or safe.);
Any materials within the bunded areas (including spillage and direct rainfall) will
drain to a sump from where it can be inspected and disposed of or treated in an
appropriate manner;
Any actions required to repair damaged storage containers and remove spillage
from the bunded area will be undertaken as soon as practical;
Spill trays will be provided to capture any spillage from chemicals, fuels and oils
usage areas. All materials in the spill trays will be decanted into an appropriate
waste storage container for later disposal at an approved waste disposal facility.
Drainage systems and storage bunding will be designed to retain spilled material
and reduce the likelihood of escape.
27
PROJECT TITTLE Environmental Management Plan
2.17 Reporting
VICS Construction Company shall report spills at work sites to DPR in compliance with
the regulations while all documentation of the spills will be provided by the
subcontractor.
The following criteria shall be used to determine a reportable spill on worksite:
Includes petroleum derived liquids (crude oil, condensate, gasoline, diesel fuel) and
petroleum derived solvent (toluene, xylene etc.).
i. Volume of each spill: Any spill volume greater than one (>1) barrel of oil
(160 litres) requires immediate report to DA
ii. Spill directly to water or reaching surface water (streams, creeks, rivers,
lakes, ponds, ocean)
iii. Excludes off premise, non-marine transportation spills where the product
is in custody of third party carrier.
ii. Spill must have contact with soil. Excludes spills inside containment or
collection areas.
iii. Include spills from tank bottoms and underground storage tanks.
iv. Report the total volume in barrels or litres of oil spilled to land regardless of
amount recovered.
28
PROJECT TITTLE Environmental Management Plan
iv. Excludes spills of insoluble solids to water that have no environmental
impacts (e.g. plastic pellets).
iv. Include spills or leaks from tank bottoms and underground storage tanks
29
PROJECT TITTLE Environmental Management Plan
30
PROJECT EPCM-1 Regulatory Compliance & Environmental Management Plan