Quantity Surveying CE 3208

Source: HANDBOOK OF CONSTRUCTION ESTIMATE by SIR RHENO VELASCO


OUTPUT
WORK DESCRIPTION NO. OF WORKFORCE OUTPUT UNIT
A. SITE PREPARATION WORKS
1 Excavation of Loam or Sand 1 0.76 cu.m./hr
2 Excavation of Clay or Heavy Soil 1 0.61 cu.m./hr
3 Backfilling 1 1.22 cu.m./hr
4 Spreading, Tamping and Grading 1 2.09 cu.m./hr
5 Placing Embankment 1 2.00 cu.m./hr
6 Clearing and Grubbing 1 20.00 sqm/hr
7 Demolition of Slab on Grade 2 0.04 cu.m./hr
B. CONCRETING WORKS
1 Concreting of Unreinforced Slab 2 0.15 cu.m./hr
2 Concreting Reinforced Slabs/Footings 2 0.11 cu.m./hr
3 Concreting of Columns/Beams 2 0.06 cu.m./hr
C. REBAR WORKS
1 Reinforcing of On Grade Slabs 2 12.31 kgs/hr
2 Reinforcing of Suspended Slabs 2 8.00 kgs/hr
3 Reinforcing of Columns/Beams 2 5.56 kgs/hr
4 Reinforcing of Stairs 2 6.15 kgs/hr
D. FORMWORKS AND FALSEWORKS
1 Placement of Forms 2 1.86 sqm/hr
2 Removal of Forms 2 1.86 sqm/hr
E. METAL WORKS
1 Placement and Installation 2 177.78 kg/hr
F. MASONRY WORKS
1 Placement of Concrete Cores 2 12.50 blocks/hr
2 Placement/Laying of Joints 2 52.50 blocks/hr
3 Plastering 2 1.00 sqm/hr
G. CEILING WORKS
1 Installation of Cement Board on Metal Frame 2 6.75 sqm/hr
F. TILEWORKS
1 Laying of 100mm x 100mm tiles 2 150.00 pcs/hr
2 Laying of 150mm x 150mm tiles 2 65.00 pcs/hr
3 Laying of 200mm x 200mm tiles 2 37.00 pcs/hr
4 Laying of 200mm x 300mm tiles 2 25.00 pcs/hr
5 Laying of 300mm x 300mm tiles 2 16.00 pcs/hr
6 Laying of 300mm x 600mm tiles 2 8.00 pcs/hr
7 Laying of 400mm x 400mm tiles 2 9.00 pcs/hr
8 Laying of 600mm x 600mm tiles 2 4.00 pcs/hr
G. ROOFING WORKS
1 Installation of Ribbed Type G.I. Sheets and Foam Insulations 2 11.00 sqm/hr
2 Installation of Gutters, Ridgrolls, Cappings and Flashings 2 15.20 lm/hr
H. PAINTING WORKS
1 Plain Paint Finish 1 13.92 sqm/hr

1|P age
Quantity Surveying CE 3208

Source: PHILCON PRICES


OUTPUT
WORK DESCRIPTION OUTPUT UNIT
A. SITE PREPARATION WORKS
EXCAVATION - MANUAL
1.1 Common earth 0.13 cu.m./hr
1.2 Loam of sand 0.76 cu.m./hr
1.3 Clay or heavy soil 0.61 cu.m./hr
1.4 Rock 0.38 cu.m./hr
EXCAVATION - MECHANICAL
1.5 Common earth 0.15 cu.m./hr
1.6 Rock with jack hammer 0.06 cu.m./hr
BACKFILLING
1.7 Common manual 1.22 cu.m./hr
1.8 Gravel fill manual 0.20 cu.m./hr
1.9 By machine 0.50 cu.m./hr
TRENCHING
1.10 By hand 0.17 cu.m./hr
1.11 By machine 2.00 cu.m./hr
TRENCHING & BACFILLING OF UNDERGROUND PIPING USING EXCAVATION MATLS MANUAL
FROM:
1.12 0 - 2m Depth 0.80 cu.m./lm
1.13 2 - 3m Depth 0.60 cu.m./lm
1.14 3 - 4m Depth 0.40 cu.m./lm
1.15 4 - 5m Depth 0.30 cu.m./lm
1.16 Placing binder gravel 9.09 cu.m./hr
1.17 Escombro backfilling 4.76 cu.m./hr
1.18 Spreading,tamping & grading 2.08 sq.m./hr
1.19 Mechanical compaction, plate compaction 16.67 cu.m./hr
MANUAL CLEARING & GRUBBING
1.20 Clearing under growth & trees - 12″ 20.00 sq.m./hr
1.21 Clearing under growth & shrubs 33.33 sq.m./hr
1.22 Disposal of soil 0.59 cu.m./hr
1.23 Hauling of soil 1.00 cu.m./hr
1.24 Gravel fill 0.48 cu.m./hr
B. CONCRETING WORKS
2.1 Grade Members (Tie Beams and Wall Footings) 0.12 cu.m./hr
2.2 Slab On Fill 0.20 cu.m./hr
2.3 Suspended Slabs, Beams, Ledges and Staircases 0.06 cu.m./hr
2.4 Columns and RC Walls 0.70 cu.m./hr
2.5 Mixing manual 0.06 cu.m./hr
2.6 Mixing machine 0.56 cu.m./hr
2.7 Chute from truck 0.14 cu.m./hr
2.8 Crane & bucket 0.07 cu.m./hr
2.9 Wheeling 0.04 cu.m./hr
C. REBARS WORKS
3.1 Grade Members (Tie Beams and Wall Footings) 14.29 kgs/hr
3.2 Suspended Slabs, Beams, Ledges and Staircases 12.50 kgs/hr
D. FORMWORKS
FORM WORKS FABRICATION
4.1 Form works fabrication 1.00 sq.m./hr
FORM WORKS INSTALLATION
4.2 Wall on ground 0.50 sq.m./hr
4.3 Wall above ground 0.43 sq.m./hr
4.4 Beams 0.32 sq.m./hr
4.5 Columns 0.43 sq.m./hr
4.6 Suspended slab
-Suspended slab 0 - 18″ 0.60 sq.m./hr
-Suspended slab 10 - 36″ up 0.30 sq.m./hr
4.7 Elevated & shored slab forming
-Forming only 0.12 sq.m./hr

2|P age
Quantity Surveying CE 3208

-Forming & Shoring 0.09 sq.m./hr


4.8 Wood wall & Partition 2.00 sq.m./hr
STRIPPING OF FORMS
4.9 Wall on ground 4.00 sq.m./hr
4.10 Wall above 10″ 0.78 sq.m./hr
4.11 Beams 0.97 sq.m./hr
4.12 Columns 1.18 sq.m./hr
4.13 Suspended slab
-Suspended slab 0 - 18″ 1.20 sq.m./hr
-Suspended slab 10 - 36″ up 0.93 sq.m./hr
4.14 Elevated & shored slab forming - strip of forms 0.29 sq.m./hr
4.15 Floor slab at grade - strip of forms 0.36 sq.m./hr
E. CARPENTRY
5.1 Plywood partition 1.00 pcs/hr
5.2 T & G Flooring and Siding 7.14 bdft/hr
5.3 Ceiling & frame work 2.78 bdft/hr
5.4 Siding frame work 3.70 bdft/hr
5.5 Flooring framing 1.03 bdft/hr
5.6 Wooden post errection 2.33 bdft/hr
5.7 Truss Fabrication 2.86 bdft/hr
5.8 Truss Installation 1.25 bdft/hr
5.9 Girt Installation 4.76 bdft/hr
5.10 Plates Installation 7.69 bdft/hr
5.11 Purlins Installation 3.70 bdft/hr
5.12 Fascia board Installation 2.17 bdft/hr
5.13 Cutting by manual 1.00 pcs/hr
5.14 Assembly 2.38 sq.m./hr
F. MASONRY
6.1 4” CHB
Laying 8.0 - 10 m2/day
Tooling 11 - 14 m2/day
Plastering 8.0 - 10 m2/day
6.2 6” CHB
Laying 7.0 - 9.0 m2/day
Tooling 11 - 14 m2/day
Plastering 8 - 10 m2/day
6.3 8” CHB
Laying 6-8 m2/day
Tooling 11 - 14 m2/day
Plastering 8 - 10 m2/day
G. STRUCTURAL STEEL
FABRICATION - MILD STEEL
7.1 Light 7.70 - 9.09 kgs/hr
7.2 Heavy 11.11 - 16.67 kgs/hr
ERECTION - MILD STEEL
7.3 Light 10.00 - 14.29 kgs/hr
7.4 Heavy 16.67 - 25.00 kgs/hr
FABRICATION - G.I. STEEL
7.5 Heavy weight 11.11 - 20.00 kgs/hr
7.6 Light weight 8.00 - 10.00 kgs/hr
7.7 Grating 1 1/4″ x 3/16″ 0.30 - 0.33 sq.ft./hr
7.8 Star threat grating 0.20 - 0.25 sq.ft./hr
7.9 Errection
7.10 Heavy Structural teel 16.67 - 33.33 kgs/hr
7.11 Light Structural steel 11.11 - 16.67 kgs/hr
7.12 Stacks ( Inc. full welding ) 3.33 - 4.00 kgs/hr
7.13 Tanks ( Inc. full welding ) 3.64 - 5.00 kgs/hr
WELDING
7.14 1- Welder and 1- Helper ( 16 total mh ) 40-50 lf/day
H. ROOFING WORKS
Roofing Sheets

3|P age
Quantity Surveying CE 3208

8.1 Metallic 1.03 sq.m./hr


8.2 Non-Metallic 0.66 sq.m./hr
Sidings (Gutters, Ridgerolls, Capping and Flashing)
8.3 Metallic 0.78 sq.m./hr
8.4 Non-Metallic 0.66 sq.m./hr
I. ARCHITECTURAL SPECIALTIES
DOORS
9.1 Wooden 0.42 sq.m./hr
9.2 Steel 0.13 sq.m./hr
9.3 Aluminum 0.12 sq.m./hr
9.4 Cyclone wire 0.13 sq.m./hr
WINDOWS
9.5 Glass 0.31 sq.m./hr
9.6 Louver 0.22 sq.m./hr
9.7 Steel 0.03 sq.m./hr
PARTITIONS
9.8 Single wall 0.40 sq.m./hr
9.9 Wooden wall 0.29 sq.m./hr
9.10 Wooden Louver 0.29 sq.m./hr
9.11 Cyclone Louver 0.19 sq.m./hr
PAINTING ( 3 coats )
9.12 Equipment 4.17 sq.ft./hr
9.13 Pipes 3.33 sq.ft./hr
9.14 Miscellaneous 4.17 sq.ft./hr

4|P age