Computation of Productivity of Drill Machines (AutoRecovered)

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 8

COMPUTATION OF

PRODUCTIVITY OF DRILL
MACHINES
National institute of Technology Raipur

MADE BY:
RAVI KUMAR
MINING ENGINEERING 19121906
CONTENT
Topic page
1.Introduction 1
2.determinatiojn of parameters for drilling machine 2
3.entery into the mine and site calculation 3
4.calculation and graph for productivity of drill machine 4
5. conclusion 6
6. reference 6
INTRODUCTION:
Drilling is a material-removing or common machining process, one
cutting process in which the tool estimate is that 75% of metal
uses a drill bit to cut a hole of cutting material removed comes
circular cross-section in solid
materials. This is the most from the drilling operation.

Drilling machines with high • Possess an electronic indicator of


productivity has the punch hammer drilling system - observation.
1238 and its characteristic of drilling
• Drilling equipment Drilling lafeten
and construction in function of
diverse.
hammer puncher who can reach
various results and are obtained • Drilling in rotation with water.
other time intervals for other • Possesses water under pressure
drillings. It is therefore imperative and spraying water.
that any drilling machine should
obtain other results by the method • Automatic lubrication.
of recording in which the additional • Catalyst.
results will be obtained. Drilling
• Automatic shutdown system
machines for our case when the car
ANSUL.
has worked in hammer drilling
puncher nr. 1238 has a 210 HL • The electrical system in 1000 v,
platform. with start-up directly.
• It is designed for movement in
The characteristics of this machine mines, - with diagonal roads – cross
are: section.

• It has the possibility of • There is a direct system of drilling


manipulation up-down and a new control system of anti-blocking,
version of llafetes manipulation of works RPCF (pressure controlled
drilling. rotation feed).
• Rotation, printing and mechanism
should be kept suppressed under
pressure).

Below is the example of a mine of pyrite and mixture

The determination of parameters for mining drilling in ore


body
During the recording phase of are displayed in the Gantt schedule
drilling works in mining have for drilling-mining jobs with high
reached a range of values, the productivity machine puncher.
results of which were recorded for
• Driven by four wheels, operated
each hole drilled separately and we
by steering wheel, brake position
met up in the results as follows:
and the whole chassis lubricated
Forehead of drilling has been with
with lubricant plant.
great width and necessary for
drilling two rows, so as not to wide • In the centre it is equipped with a
line to endangering the workshop. It telescopic lever FOPS, owns a
is based on the time taken for protective roof, lighting mechanism,
operator which will examine all the the winch cable wrapped, shot
other chapters following. All these water pump etc.
• The centre is equipped with a • Drilling done by Bürgi length 3 m
telescopic lever FOPS, owns a head Drilling F = 45 mm, but there is
protective roof, lighting mechanism, a possibility that in other cases
the winch cable wrapped, water Bürgi to be used with other
pump etc. dimensions.

Entry into the mine and the site (The entry In mine and work the
forehead)
The time required for access to the with 20 minutes are calculated time
site: • Time of entry to the site is what the machine take from the
analysed in the time of 1 hour and garage to the working place. • Time
10 minutes. • The time required to control and security of the site is
check the oil level and visual defined the time of 20 minutes
preview of the vehicle 20 minutes

refe
r:https://springer.com
The drilling in productive machine
The drilling cycle is made in two positions so as it is mentioned above. The
reason why we are doing two positions is for security reasons. This is best
shown in Figure 2. By figure 2 are presented two positions, we would make
presentation of each position separately.
For positon 1.
Drillin Time Description of drilling Manipulation Length of
g (minute) drilling
1 3:38 Pyrite + quartz+ limestone 0:30 3
2 3:30 Pyrite + quartz + galena 0:50 3
3 3:50 Quartz + gap + pyrite 1:00 3
4 5:15 Quartz + pyrite 0:30 3
5 3:39 Pyrite + gap + quartz 0:25 3
6 2:54 Pyrite with more space 1:40 3
7 4:10 Pyrite + quartz 3:00 3
8 4:00 Pyrite + quartz + galena 1:05 3
9 4:20 Pyrite + micros 1:30 3

Refer:https://springer.com/
After getting this data we can draw the graph of the data and we can predict
that the relation is linear.

refer:
https://springer.com/
Similarly we can draw the graph for the second position we have
refer.:h
ttps//springer.com
Once we get the values from the factual situation from drilling machine Drilling
we have presented these graphically to win a graph function which was
overwhelmed with points that are related chart and earned value. In the graph
we render as follows: In the axis Y we presented drilling in the meters length.
Figure. 3 chart of the drilling position 1. Figure 4 chart of the drilling position 2.
In axis X in minute is presented a time of the drilling. The order of drilling with
intervals and operator have given different values, but close to drawn straight
line we have drawn and that has met the most points or approximated most
values and straight line drawn is the graph of the function (Y = 3 / 5 X +1/4).
This graph is obtained by analysis of drilling position of the drilling 1, after that
is created coordinate axis with the same graphic of the function as random
drilling 1, Have gave the results with which we can consider that it is more
realistic (figure 4 drilling position Chart 2). Since other parameters are
calculated, and then in a cycle of changing the whole activity of the graphics
we presented in Table 4
refer.:https://springer.com

Conclusion
The machinery which has done the drilling came with resulted of a graph of
the function which in Y axis shows the interval while drilling, whereby in axis X
the borehole in meters. From this we can conclude that if we want to have
drilling then we substitute the desired number of drilling and replace the (Y)
and (X) draw in the time interval for how long shall we do for that number of
desired drilling. Optimal solution should be done to decrease the operating
time of positioning and better planning of the machine with high drilling
productivity. The lack of good positioning could bring to the situation without
operational ability, because it loses more time of at least 1 hour drilling
explosive filling respectively. You have a better analysis and planning of the
exploitation phase of the operator to save time NOTES.

Reference
1. Spathis A.,gupta R.(2012)tunneling in rock by drilling
and blasting .
2. Designing of new underground mining facilities with
dual function in the Pb-Zn mine .by Dr.izet Zequiri.
3. Springer.com/mining/drilling
4. Productivity of drill machine by shawn hatric (1988)