18.03.2022 Well-Wise Daily Geological Report For Drilling Wells (Status at 5:00 AM)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

18.03.

2022
Well-wise Daily Geological Report for Drilling Wells (Status at 5:00 AM)
Rig Loc. Type THD (P/A) Well No. TD (m) Days (P/A) DOS Area/Plinth
S-1 * HZR Dev S 115.3/133 Hapjan-74 2900/2901 90 77 20.12.2021 Hapjan, HJN-16P
Rigging down. (Rig down declared at 1 pm on 07.03.2022).
[Fwd. Loc. HZW (Makum), MKM-8P→ LAF-3 issued on 18.12.2021. Civil work in progress. Recce carried-out on 14.03.2022]
S-2 * NLY Inj J 1094.5 NHK- 660 3560 90 26 19.02.2022 Nahorkatiya, NHK-452/612P
Depth: 2206 m (KOP: 798 m), Prog: 149 m, P/Ops: Circulation (M/Wt.: 69 lbs/cft)
Drilled 2057-2206 m. Observed poor ROP. Circulating prior to P/out for bit change. {THD at 2037.7 m MD (1943.2 m TVD) is 451.6 m (452.1 m) towards
N67.0°W (N67.1°W); D/A: 26.3° (24.9°) (M/s. Baker Hughes)}.
[Fwd. Loc. HZS (Hapjan); Common plinth of HZS-HZT→ Civil work in progress]
S-3 * HZQ Inj J 737.98/ Hapjan-75/MMC 2988/ 2994 90 53 23.01.2022 Hapjan, HJN-19,20,22P
Depth: 2994 m (Final) (KOP: 1000 m), Prog: Nil, P/Ops: Circulation (M/Wt.: 71 lbs/cft)
R/in 5.1/2” oil-string casing from 216 m & landed with shoe at 2987 m (F/C at 2962 m). Circulating prior to cementation. {THD at 2834.0 m MD (2693.4 m TVD)
is 684.1 m (675.7 m) towards S70.4°E (S69.4°E); D/A: 24.4° (24.0°) (M/s. NEWSCO)}.
[Fwd. Loc. DIV (Dholiya); Loc. DBQ Plinth→ Civil work completed. Carried-out final recce on 28.02.2022]
S-4 * DJA Dev S 546.7/ 554.2 S. Tinali-10 3390/ 3399 90 101 06.12.2021 S. Tinali, STL-5/6/7/9P
Depth: 3399 m (Final) (KOP: 1405 m), Prog: Nil, P/Ops: R/in bit (M/Wt.: 70 lbs/cft)
POOH bit from 191 m. R/in bit with stabilizers (at 1, 9 & 18 m) to 2441 m for round trip prior to lowering 5.1/2” casing. {THD at 3179.6 m MD (3071.3 m TVD) is
554.2 m (546.5 m) towards N69.1°W (N68.8°W); D/A: 1.8° (0.0°) (M/s. Baker Hughes)}.
[Fwd. Loc. MGM (Lakwagaon); Common plinth of MGM-MGU→ LAF-3 issued on 12.05.2021. Civil work in progress]
S-5 * DJB Dev J 997.2 S. Tinali-11 3500 90 13 05.03.2022 South Tinali, TNL-9P
Depth: 1329 m (KOP: 1000 m), Prog: 65 m, P/Ops: Drilling (M/Wt.: 67 lbs/cft)
POOH bit. R/in new TCR bit (1-1-7) with new directional BHA to bottom. C&C mud. Drilled 1264-1329 m. {THD at 1310.1 m MD (1300.2 m TVD) is 69.1 m (61.2
m) towards S2.1°W (S3.1°E); D/A: 22.3° (23.6°) (M/s. NEWSCO)}.
[Fwd Loc. TAQ (East Khagorijan); TAQ-TBE-TBD Plinth → Rev LAF-3 issued on 26.10.2021. Under Land acquisition-ROE]
1029.9/
S-6 * NLW Dev J NHK-659/ MMC 3467/3404 90 82 25.12.2021 Nahorkatiya, NHK-169P
1004.4
Rigging down. Well producing clean oil @ 30 klpd (GOR: 312 scum/kl) through 5 mm bean with FTHP: 600 psi.
[Fwd. Loc. MGP (Lakwagaon); MGP-MGO-MGQ-MGR-MGT-MGS Plinth→ Civil work completed. Final recce carried-out on 09.03.2022]
S-7 (E-2000) DYE Exp J 1031/ Dholiya-2/ MMC 4042/ 120 70 06.01.2022 Dholiya, Dholiya-1P
Depth: 3355 m (KOP: 1000 m), Prog: Nil, P/Ops: R/in casing (M/Wt.: 73 lbs/cft)
R/in 9.5/8” casing to 2403 m. {THD at 3355.0 m MD (3168.3 m TVD) is 896.3 m (889.8 m) towards S59.2°W (S59.3°W); D/A: 24.2° (23.9°) (M/s NEWSCO)}.
[Fwd. Loc. MFT (Safrai); IP→ Civil work completed for Sindhu Rig. Modification for S-7 rig in progress]
S-8 (E-3000) DIP Exp S 107/ Balimara-12/ MMC 4440/ 121 59 17.01.2022 Balimara/ IP (combo-pad)
Depth: 2609 m (KOP: 1038 m), Prog: 46 m, P/Ops: P/out bit (M/Wt.: 70 lbs/cft)
Drilled 2563-2609 m. Observed poor ROP. C&C mud. P/out upto 482 m for bit change. {THD at 1463.5 m MD (1455.0 m TVD) is 76.3 m (90.2 m) towards
N44.4°W (N46.8°W); D/A: 12.4° (9.4°) (M/s NEWSCO)}.
[Fwd. Loc. HZU (Singhibil); SGB-1→ Civil work completed]
VFD-1 (E-2000) HZM Exp J 1119.5/ North Balijan-5 4059/ 125 97 10.12.2021 North Balijan/ IP
Depth: 2941 m (B-hole) (A-hole: 2749 m, KOP: 1214 m) (KOP for side-track B-hole: 2591 m), Prog: 9 m, P/Ops: Drilling (M/Wt.: 75 lbs/cft)
POOH bit from 132 m. Obsereved TDS leakage, attended & rectified the same. R/in new TCR bit (1-2-7) with directional BHA to bottom. C&C mud. Drilled 2932-
2941 m. {THD at 2922.9 m MD (2786.5 m TVD) is 646.2 m (646.5 m) towards N82.7°W (N82.7°W); D/A: 23.9° (24.5°) (M/s Baker Hughes) (B-hole)}.
[Fwd. Loc. DJD (Balimara); BMR-11P→ LAF-3 issued on 07.02.2022. Civil work in progress]
VFD-2 (E-2000) DIQ Dev S 507.9/ Balimara- 4377/ 120 Balimara, BMR-6/8P
Waiting for man power. (R/up: 88%).
[Fwd. Loc. BI (Balimara), Balimara-6/8-DIQ-BI-BJ Plinth→ LAF-2 issued]
CH-1 (JB) # TBT Exp J 1651/ Dinjan-2 4190/ 120 86 21.12.2021 Dinjan, Dinjan-1P
Depth: 3490 m (KOP: 600 m), Prog: 124, P/Ops: Drilling {M/Wt.: 76 lbs/cft (HPM)}
R/in new PDC bit with directional BHA (RSS) from 2512 m to bottom. C&C mud. Drilled 3366-3490 m. {THD at 3448.1 m MD (3135.0 m TVD) is 1229.8 m
(1232.6 m) towards N70.8°W (N70.8°W); D/A: 34.3° (34.3°) (M/s Baker Hughes)}.
[Fwd. Loc.HXR (Sesabil); IP→ Civil work completed as per VFD rig, foundation to be modified for CH-1. Land issues resolved]
CH-2 (Quippo-1)
KUBB Dev S 634/655.5 Kumchai-19 3726/3736 149 181 17.09.2021 Kumchai, Kumchai-7P
New#
Rig released at 9 am of 17.03.2022.
[Fwd. Loc. BJN (Baghjan); BGN-25/26/27-BJN-BJO-BJQ→ Civil work completed]
CH-3 (Quippo-2) SDYA
Exp V - Sadiya-1 4500/ 124 42 03.02.2022 Sadiya,IP
New# (Phase-I)
Depth: 2477 m, Prog: 62, P/Ops: Drilling (M/Wt.: 74 lbs/cft)
Circulated & observed no mud loss. R/in bit from 1776 m to bottom. C&C mud. Drilled 2415-2477 m.
[Fwd. Loc. KUBF (Kumchai); Common plinth of KMC-11-KUBF-KUBG→ LAF-3 issued on 16.06.2021. Civil work in progress]
CH-4 (SINDHU)# BJC Exp J 943.8/ South Baghjan-5 4155(R)/ 120 139 29.10.2021 BJC-BJB Plinth
Depth: 3510 m (B-hole) (A-hole: 2425 m, KOP: 1000 m) (KOP for side-track B-hole: 2212 m), Prog: 75, P/Ops: Drilling (M/Wt.: 72 lbs/cft)
R/in new TCR bit (1-3-7) with directional BHA from 3220 m to 3420 m & washed down to bottom. C&C mud. Drilled 3435-3510. {THD at 3490.9 m MD (3354.7 m
TVD) is 776.0 m (775.2 m) towards N75.4°W (N75.5°W); D/A: 15.4° (14.7°) (M/s. Halliburton) (B-Hole)}.
[Fwd. Loc. BJB (South Baghjan); Common plinth of Loc. SBJ-5-BJB→ Civil work completed]
CH-5 (FORESIGHT)
TBP Exp J 930.7 South Baghjan-6 4324/ 120 73 03.01.2022 S. Baghjan, SBJ-3/4P
#
Depth: 3670 m (KOP: 2152 m), Prog: 54 m, P/Ops: Drilling (M/Wt.: 76 lbs/cft)
Drilled 3616-3670 m. {THD at 3647.9 m MD (3503.3 m TVD) is 613.9 m (613.9 m) towards N69.3°W (N70.9°W); D/A: 28.5° (27.9°) (M/s Baker Hughes)}.
[Fwd. Loc. TBL (S. Baghjan); SBJ-3/4/6-TBL-TBO common plinth→ Civil work completed]
CH-6(Quippo)
BJK Dev J 1017/ Baghjan-28 4200/ 114 82 25.12.2021 Baghjan, BGN-3/20P
New #
Depth: 3888 m (KOP: 1500 m), Prog: 44, P/Ops: Drilling (M/Wt.: 76 lbs/cft)
P/out bit upto 2264 m & observed mud cut. Attended & rectified the same. R/in bit with directional BHA to bottom. C&C mud. Drilled 3844-3888 m. {THD at
3866.8 m MD (3686.5 m TVD) is 884.2 m (883.8 m) towards N28.4°W (N28.5°W); D/A: 21.9° (23.6°) (M/s Baker Hughes)}.
[Fwd. Loc. KUBC (Kumchai); Kumchai-6/16 plinth→ Civil work completed, foundation modification required]
DM-5** WDW-202 S 150/ /MMC 1435/ 25 12 06.03.2022 Nahorkotiya, NHK-175P
Depth: 1190 m (KOP: 560 m), Prog: 159 m, P/Ops: Drilling (M/Wt.: 66 lbs/cft)
Drilled 1031-1190 m. {THD at 1162.4 m MD (1146.1 m TVD) is 132.4 m (131.9 m) towards N44.7°E (N45.0°W); D/A: 9.8° (9.7 °) (M/s NEWSCO)}.
[Fwd. Loc. WDW-210 (NDM-1P)→ Civil work completed]

Exp: Exploratory, Dev: Development, Apr: Appraisal, (R): Revised, R/up: Rig-up, EDS: Expected Date of Spudding, EDC: Expected Date of Completion; CHH: Casing Head Housing, IRD: Independent Rotary
Drive, TBR:Tie-Back Receptacle. VDS: Vertical Drilling System, RAL: Radial Analysis Bond Log, STAR: Simultaneous Acoustic Resistivity Image, SWPA: Swivel Wash Pipe Assembly,**E-750 HP rig.*E-1400 HP
rig. #E-2000 HP rig, SDMM: Steerable Downhole Mud Motor, PLC :Programmable Logic Controller, PCL: Pipe Conveyed Logging. LTSA: Locator Tubing Seal Assembly, CI: Corrosion Inhibitor, PHPA: Partially
Hydrolyzed Polyacrylamide; PCR: Power Control Room. ZREAC: Zonal Research & Extension Advisory Committee, HMI: Human Machine Interface, TAG: Throw Away Gun. SCR: Silicon Controlled Rectifier, HPU:
Hydraulic Power Unit. Ŵ: Window cutting wells, FB: Flat Bottom, RCJB: Reverse Circulation Junk Basket. LCP: Live Condition Perforation. CIT: Casing Integrity Test, RRV: Reset Relief Valve. NDDF- Non
Damaging Drilling Fluid; I-BOP: Internal Blow-out Preventor; CIT: Casing Integrity Test; MP-1: Mud Pump-1; DP: Drill Pipe; O/up: Open up; EC: Eddy Current; (R): revised; HLS: Halliburton Services; HWDP:
Heavy Weight Drill Pipe; RLA: Rotating Link Adapter; DCST: Dril Collar Severing Tool, SRV: Safety Relief Valve; FPI: Free Point Indicator, PTU: Pressure testing Unit, THP: Tubing Head Pressure, HSD: High
Speed Diesel, Inj: Injector; LCM: Loss Circulation Materials; MCC: Magnesia Cross-linked Cement; CP: casing pressure; RCI: Reservoir Characterization Instrument; IFX: Insitu Fluid Explorer, FDZ: Freshly
Drilled Zone; PCL: Pipe Conveyed Logging, ERPG: Electronic Reservoir Pressure Monitoring Gauge; F/C: Float Collar; S/C: Stage Collar; FOSV: Full Opening Safety Valve, NIFA: Non Invasive Fluid Additive.