Mezzanine Office Extension Interior Fit-out

and Warehouse
Extension Project
Weekly Construction Summary Report No. 2

P.O. NO.: 7119 For the Period ending : 15-Nov-2019

KEY DATES CONTRACTUAL FORECAST REMARKS


NTP Received: 25 Oct 2019
COMPLETION DATE 2-Jan-20 2-Jan-20
P.O. Received: Yet to receive

PROGRESS (%) Last Week This Week Next Week


OVER-ALL PROGRESS ACCOMPLISHMENT Plan Actual Delta Plan Actual Delta Plan Actual Delta
Cumulative Forecast Schedule 0.65% 0.54% 0.11% 2.86% 1.59% 1.27% 6.26%

KEY ACTIVITIES DONE DURING THE WEEK KEY ACTIVITIES PLANNED FOR NEXT WEEK
1. Mobilization 1. Layout
2. General Documentation for design and permits 2. Vinyl Tile
3. Actual Layout 3. Rock Wool Installation
4. CHB Laying

COMPLETED MILESTONES RECOVERY PLAN STATUS, IF ANY


1. Plan to work 24/7 upon receipt of CARI and approval of all materials
2. Increase group of teams

LIGHTNING
WEATHER MONITORING Morning Afternoon
ALERT

02/11/2019 (SAT) FAIR FAIR


03/11/2016 (SUN) FAIR FAIR
REASONS CONTRIBUTING TO PROGRESS BACK LOG, IF ANY 04/11/2019 (MON) FAIR FAIR
1. Waiting for PO. 05/11/2019 (MON) FAIR FAIR
2. Waiting CARI and other bonds and insurances 06/11/2019 (MON) FAIR FAIR
07/11/2019 (MON) FAIR FAIR
08/11/2019 (MON) FAIR FAIR
: Mezzanine Office Extension Interior Fit-out
Project Name and Warehouse Extension Project

Project Location : LRMC Compound

Subject : Weekly Report 2

Project Accomplishment Report As of: 15-Nov

DESCRIPTION BOQ Previous This Period To Date

S/N % Wt PREVIOUS THIS PERIOD TO DATE


Qty Unit % Progress % Wt % Progress % Wt % Progress % Wt

1 CIVIL AND ARCHITECTURAL WORKS


General Requirements lot 1 0.767% 10.000% 0.077% 20.000% 0.153% 30.000% 0.230% 0.1 0.2 0.3
Mobilization/Demobilization lot 1 0.958% 30.000% 0.287% 20.000% 0.192% 50.000% 0.479% 0.3 0.2 0.5
Temporary Facilities

(Temporary Power, water, communication facilities, barracks,


temp office, warehouse lot 1 0.575% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

Health and Safety Facilities


Hoarding, PPE, Clinicetc..
Bond and Insurance lot 1 0.575% 10.000% 0.057% 50.000% 0.287% 60.000% 0.345% 0.1 0.5 0.6
Advance Payment Bond (30% of Contract Price) callable on demand
Performance Bond (20% of Contract Price) callable on demand
Retention Bond (10% of Contract Price)
Warranty Bond (10% of Contract Price)
Designs and PI Insurances (as applicable) lot 1 0.575% 10.000% 0.057% 50.000% 0.287% 60.000% 0.345% 0.1 0.5 0.6
Mechanical Design / ACU's / FDAS Interface
Electrical Design
Permits lot 1 0.144% 40.000% 0.057% 30.000% 0.043% 70.000% 0.101% 0.4 0.3 0.7
Building Permit
Occupancy Permit
Contractors Tax
Vetting Fee
(LRMC Permits)
AS Built Plans
Overhead/Supervision
Hauling/Scaffoldings/delivery of materials
Security
Others (as applicable)
Staff House and Barracks Rentals lot 1 0.431% 0.000% 0.000% 20.000% 0.086% 20.000% 0.086% - 0.2 0.2

Demolition Works
Demolition / removal of existing chb wall and cabinet at CEO/ set 1 0.096% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Restoration of existing exhaust fan opening sets 2 0.057% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Removal of existing fire exit door and restoration of opening lot 1 0.048% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

MEZZANINE FIT OUT


Wall Works
100mm thick wall, 12 mm thick FCB, on 0.6mm x 76mm metal frame sq.m. 385.399 7.571% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

12 mm thick Tempered Glass on 22mm x 22mm alum. U-Channel including Doors, Handle and Hardwares to complete the works

> Board Room (W12.05m x H 2.40m) sets 1 4.018% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> Spare Room (W5.975 x 2.40m) sets 1 1.993% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> TELCO / EE Room (W1.55 x 2.40m) sets 1 0.517% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> Meeting Room (W3.24 x 2.40 m) sets 4 4.322% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> AFCS Room (W2.285 x 2.40m) sets 1 0.762% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Frosted and Graphic Sticker lot 1 0.623% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
12 mm thick FCB only on Top of Existing Wall sq.m. 25.25 0.254% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
12 mm thick double FCB for New Perimeter Wall including fram sq.m. 30.71 0.515% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
100 mm x 12mm thick PVC Baseboard Duco Paint Finish lm 79.12 0.682% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

Painting Works
Roller paint finish in semi gloss to FCB walls. sq.m. 341.08 2.059% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Roller paint finish in semi gloss to CHB walls. sq.m. 110.63 0.668% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

Supply and installation of 150mm CHB Wall sq.m. 52.65 0.822% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Lintel Beams & Stiffiner Columns
Concrete m³ 2.1 0.177% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Reinforce Steel kg 660.51 0.494% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Formworks sq.m. 33.41 0.295% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Plastering works for Perimeter Walls sq.m. 110.3 0.793% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

Ceiling Works
3.2.1 12mm thk gypsum board on metal frames ga#22 sq.m. 181.07 3.557% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Furring, ga#20 on carrying, 6mm dia. Full threaded
hangers, with 30mm x 30mm shadow line
3.2.2 12mm thk Fire Resistant gypsum board, on metal frames
with 30mm x 30mm shadow line lm 109.68 0.420% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Rockwool Insulation, 125mm thk, 50kg/m3 with Wiremesh Rein sq.m. 368.25 4.129% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
3.2.4 roller painting to new gypsum board ceiling sq.m. 181.07 1.093% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

Floor Works
3.3.1 Floor Preparation,Lean concrete mortar to receive sq.m. 350.72 0.907% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
the new finishes;
3.3.1.1 Vinyl Floor Tiles sq.m. 224.48 1.764% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
3.3.1.2 Carpet floor tiles sq.m. 126.24 3.569% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

Other Fit-Out
AFCS room
4.1.2 6mm thick marine plywood backing sq.m. 2.88 0.029% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
: Mezzanine Office Extension Interior Fit-out
Project Name and Warehouse Extension Project

Project Location : LRMC Compound

Subject : Weekly Report 2

Project Accomplishment Report As of: 15-Nov

DESCRIPTION BOQ Previous This Period To Date

S/N % Wt PREVIOUS THIS PERIOD TO DATE


Qty Unit % Progress % Wt % Progress % Wt % Progress % Wt

Meeting Rooms
4.2.2 20mm thk plywood backing for white board sq.m. 8.64 0.145% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

Boardroom
4.5.3 20mm thk. Plywood Backing sq.m. 8.64 0.145% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
4.5.5 Ledge in HP Laminate Finish l.m. 2.4 0.333% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

Doors
Supply and installation of 90mm x 210mm Wood Flush Door inclu sets 1 0.144% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

Electrical
Lighting Fixtures
> Surface mounted 1x18watts LED Tube Light w/ acrylic d sets 40 1.587% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> 200mm dia. Pinlight, warm white, 12 watts with acrylic d sets 42 0.610% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> Spectrum Emergency Lighting Unit with 2-25W incandes sets 13 1.008% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
sealed maintenance free batteries with charger and mounting brackets (GA-1003)
> LED Exit Sign, Green, 3W (Single Face) sets 2 0.054% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Wall Switches, Panasonic, Wide Series
> One- Gang Switch sets 2 0.011% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> Two- Gang Switch sets 4 0.028% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> Two- Gang (3 Way) Switch sets 4 0.031% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Panasonic Convenience Outlet
> Duplex, grounding type 16A sets 13 0.100% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> Duplex floor mounted outlet, pop-up type 16A set 1 0.076% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Conduits
> 1/2" IMC Pipes and Connectors lghts 250 1.749% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

> 1 1/2" IMC Pipes and Connectors lghts 100 1.495% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

> 1/2" Flexible Metal Conduit and Connectors l.m. 150 0.230% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> # 16 Utility Box w/ Cover, Deep Type sets 30 0.043% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> Junction Box, Metal sets 50 0.072% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> Fittings & Hangers lot 1 1.009% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Wires
> 3.5 mm2 THHN Wire, Phelp Dodge l.m. 1000 0.642% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> 5.5 mm2 THHN Wire, Phelp Dodge l.m. 650 0.610% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> 14 mm2 THHN Wire, Phelp Dodge l.m. 25 0.041% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> 38 mm2 THHN Wire, Phelp Dodge l.m. 90 0.293% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> Consumables lot 1 0.505% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

Provision of Panel Boards and ECB's

> LPP Panel, 125AT, 3Pole, 400V assy 1 1.437% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> 50AT, 3pole, 230V, Nema-3R ECB set 6 4.649% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> 20AT, 2pole, 230V, Nema-3R ECB set 14 4.072% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Transformer
> 75kVA dri-type transformer 460/230V, 3Ph, 60Hz (Alumi assy 1 3.728% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> Testing & Commissioning lot 1 0.479% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Fire Alarm & Detection System
> Smoke Detector pcs 13 1.862% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> 15mm dia. IMC Pipe lgths 35 0.245% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> Junction Box pcs 20 0.029% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
>15mm dia. Flexible Conduit w/ fittings lm 30 0.046% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> Hanger and Supports lot 1 0.383% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
> #18 TF wire twisted Pair lm 300 0.193% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

Mechanical Works
Supply and Installation of 5TR Ceiling Cassete Type ACCU-FCU, Inverter Type ( Carrier Brand)
Boardroom - 2 units sets 2 2.300% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Open area - 4 units sets 4 4.600% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Supply and Installation of 1hp Split Type ACCU-FCU, Inverter Typ sets 6 3.737% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Supply and Installation of 2hp Split Type ACCU-FCU, Inverter Typ set 1 0.882% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
FCU Drainwith Insulation lot 1 0.287% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Testing and Commisioning lot 1 0.652% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

WAREHOUSE EXTENSION
PROVISION OF CLADDINGS WITH METAL FRAMING
Wall Finishes:
0.6 mm thck metal cladding, rib type with fixing hardwares sq.m. 148.45 1.849% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
3"x4"x3mm thck. Tubular Frames l.m. 18 0.147% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
2"x4"x3mm thck. Tubular Frames l.m. 18 0.129% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
I- Beam Supports for Roll Up Doors kgs. 420.48 0.411% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
W6x12# with Consumables
Installation of Owner Supplied Steel Doors and Jamb set 1 0.335% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Supply and installation of door lockset set 1 0.144% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

Re-installation of Owner Supplied Rool Up Doors sets 2 0.671% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Misc. Works/Overheads lot 1 0.163% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
: Mezzanine Office Extension Interior Fit-out
Project Name and Warehouse Extension Project

Project Location : LRMC Compound

Subject : Weekly Report 2

Project Accomplishment Report As of: 15-Nov

DESCRIPTION BOQ Previous This Period To Date

S/N % Wt PREVIOUS THIS PERIOD TO DATE


Qty Unit % Progress % Wt % Progress % Wt % Progress % Wt

Masonry and Concreting Works


Supply and installation of 150 mm thck CHB (700 psi) with reinf sq.m. 55.29 0.864% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Plastering Works sq.m. 110.58 0.795% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Concreting Works for stiffener columns and lintel beams cu.m 1 0.084% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

Concrete Slab on Grade


150mm concrete slab on existing flooring (3000PSI) cu.m 27 2.274% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Non-Metallic Concrete Floor Hardener sq.m. 180 2.363% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Reinforcing Steel, Grade 60 kgs. 878.95 0.640% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Formworks sq.m. 5.775 0.051% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

Painting Works :
Repainting of existing roof framing lot 1 0.011% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Painting of I- Beams and Steel Frames sq.m. 15 0.167% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Painting of Plaster Finish sq.m. 110.58 0.668% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Supply and Installation of Onion Turbine Vents including all sup sets 2 1.212% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Removal of existing gutter l.m. 22.5 0.075% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -
Supply and installation of stainless steel gutter l.m. 22.5 0.149% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% - - -

Total 100.000% 0.5366% 1.049% 1.5860%

Prepared by: Verified by:

Kyel Corpuz Harold Viernes


Project Engineer Project Manager
PR - 9125
Mezzanine Office Extension Interior Fit-out Project

Mezzanine Office Extension Interior Fit-out Project


PROJECT S-Curve

120

100

80

60

40

20

0
19 19 9 9 9 9 19 19 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 19 19 9 9 9 9 19 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 20 20 0
v- v- -1 -1 -1 -1 v- v- -1 -1 -1 v-1 -1 -1 v-1 -1 v-1 -1 -1 -1 -1 -1 v-1 v-1 -1 -1 -1 v-1 -1 -1 c- c- -1 c-1 c-1 c -1 c- -1 c-1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 -1 n- n- n-
2
No No ov ov ov ov No No ov ov ov No ov ov o ov No ov ov ov ov ov No o ov ov ov No ov ov De De ec De De De De ec De ec ec ec ec ec ec ec ec ec ec ec ec ec ec ec ec ec ec ec ec ec ec Ja Ja Ja
1- 2- 3-N 4-
N
5-
N
6-
N
7- 8- 9-
N -N -N - -N -N -N -N - -N -N -N -N -N - -N -N -N -N - -N -N 1- Commulative
2- -D
3Cost 4- Actual 5- Cost 6- 7- 8-DCost 9- -D -D -D -D -D -D -D -D -D -D -D -D -D -D -D -D -D -D -D -D -D -D 1- 2- 3-
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
Commulative 30Cost Commulative 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

4-Nov-19 8-Nov-19 15-Nov-19 22-Nov-19 29-Nov-19 6-Dec-19 13-Dec-19 20-Dec-19 27-Dec-19 3-Jan-20
Month
0 1 2 3 4 5 6 7 8 9

Budgeted Cost 0.00 0.65 2.21 3.40 14.33 18.63 16.48 19.71 14.98 9.61

Commulative
0.00 0.65 2.86 6.26 20.59 39.22 55.70 75.41 90.39 100.00
Cost

Actual Cost 0 0.537 1.049

Commulative
0 0.537 1.586
Cost

Planning and Control [5/8]


Project Name : Mezzanine Office Extension Interior Fit-out and Warehouse Extension Project
Project Location : LRMC Compound
Subject : Safety Statistics

SAFETY Cumulative Previous Cumulative


Cumulative  This Week
PERFORMANCE Week To Date

Personal Accidents - - -
a.      Fatality - - -
b.      Lost Time Incident - - -
c.      Restricted Work Case - - -
d.      Medical Treatment
- - -
Care
e.      First Aid Case - - -
f.       Number of
- - -
Occupational Illness
g.      Lost Time Incident
- - -
Frequency Rate
h.      Severity Rate - - -
i.        Exposure Manhours - - -
j.        Safe Manhours Since
112 112 224
Last LTI
Other Incidents - - -
k.      Property Damage - - -
l.        Environmental - - -
m.     Others (fire, explosion,
- - -
etc.)
n.      Near Miss - - -
o.      Safety Observations - - -
p.      Good Observation - - -
Project Name : Mezzanine Office Extension Interior Fit-out and Warehouse Extension Project
Project Location : LRMC Compound
Subject : Progress Photos

Material Mobiization

Tools and Equipment Mobilization


CHB Laying Materials

Status of Warehouse Extension


(We are requesting for Clearance)