Data Sheet

DATA 2021-22
Laying of CC Road from Srinivas Naik (H) to malyanaik (H) of Utakunta thanda (V) of Narayanpet (M)

1 Engaging Unskilled Labour for earth work excavation in Ordinary Soils AT SITE
with initial lead & initial lift and breaking clods and sectioning for formation of
embankment - for roads (CSSR)

Unit-1cum
taking output = 1cum
Ordinary soil
Mechanical Means
Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
Mazdoor (Unskilled) day 3.64 490.00 1783.60
Add 75% for foundations Cum 0.00 1783.60 0.00
District head Quator limits 0.00 0.00
Cost for 10 cum = a+b+c 1783.60
Rate per cum = /10 178.36
Rate as per Current RSSR for
formation of road 178.36
Engaging Unskilled Labour for Labour charges for Spreading of Sand / Gravel in
2 the field as per RSSR 2019-20

1.04x490/
33.97
15
District head Quator limits 0.00 0.00
Rate as per 1 Cum 33.97 /Cum
Cement Concrete Pavement
3 Construction of un-reinforced plain cement concrete pavement, thickness as per design, over a
prepared sub base,with Nominal Mix of VCC (1:2:4) equivalent to M20 grade as per IS 456-2000
with 330 kgs of cement per cubic meter of concrete for internal roads with 43 grade cement or any
other type, coarse and fine aggregates conforming to IS : 383, maximum in a concrete mixer of not
less than 0.2 cum capacity and appropriate weigh batcher using approved mix, laid in approved
fixed side formwork (steel channel, laying and fixing of 125 mictron thick polythene film, wedges,
steel plates including levelling the formwork as per drawing), spreading the concrete with sholvels,
rakes, compacted using needle and plate vibrators and finished in continuous operation including
provision of contraction and expansion, construction joints with High performance expansion joint
filler board / using concrete cutting machine with diamond studded saw, applying debonding strips,
primer, sealant, admixtures as approved, curing of concrete pavement for 14- days/curing
compound (where specified) finishing to lines and grade as per drawing but excluding cost of High
performance expansion joint filler board/ concrete groove cutting charges with daimond studded
saw including all applicable taxes.
Unit = cum

Page 1 of 3
Data Sheet

Taking output = 75cum (172.50 t)


(100x3.75 x 0.200)
a) Labour
Mason (1st class) day 5.00 545.00 2725.00
Mason (2nd class) day 5.00 515.00 2575.00
Mazdoor (unskilled) day 150.00 490.00 73500.00
Mazdoor(skilled) day 6.00 490.00 2940.00
Mazdoor(semi-skilled) day 6.00 490.00 2940.00
84680.00
b) Machinery
Concrete mixer 0.28/0.40 cum capacity ( Hour 36.00 627.60 22593.60
6 mixers) with weight batcher and
suitable capacity calibrated water tank
Needle Vibrator Hour 9.00 251.10 2259.90
Plate vibrator Hour 9.00 54.00 486.00
Water tanker 6 Kl. Capacity Hour 5.00 699.00 3495.00
8000 ltr Rs 898.20.
28834.50
c) Material
(I) Crushed stone coarse aggregates, grading will be as
per clause 1501.2.4.1 (Table 1500.1) of specifications
@ 0.90 Cum/cum of concrete

20mm (66%)
20 Cum
C 44.55
44 55 1594.59
1594 59 71038.98
71038 98
10mm (34%) Cum 22.95 1328.34 30485.40
(ii) Sand as per IS:383 and conforming to cum 16.88 908.76 15335.33
clause 1500.2.4.2. @ 0.45 cum of
Rock Sand cum 16.88 1027.09 17332.14
(iii)Cement @ 330Kg/cum of concrete t 24.750 5700.00 141075.00
(iv)Polythene sheet 125 micron sqm 412.50 21.00 8662.50
Water for curing kl 18.00 73.00 1314.00
Plasticizer 0.5% by weight of Cement Liter 122.00 61.00 7442.00

Bitumen Sealent for 800ml Per Joint Liter 19.00 110.40 2097.60
for 23 Joints
294783.28
(a+b+c) 408297.78
(d) Form work @ 3% on (a+b+c) 12248.93
Cost for 75 cum = a+b+c+d 420546.71
Rate per Cum = (a+b+c+d+e)/75 5607.29

5607.29
Rate per cum 5607.29
4 TBS Cutting transverse contraction joints 3 to 4 mm wide and 1/3 rd depth of
C- concrete slab using concrete groove cutting machine with diamond studded saw
Q.VII within 24 - 48 hours of casting of CC Pavement. complete including subsequent
I-01 widening of the groove 8 to 10 mm. wide at top having depth of 15 mm. as
directed by Engineer incharge.

Unit = Rm
RM 1 55.00 55.00

Page 2 of 3
Data Sheet

55.00 / RM
5 Collection of Sand and stacking at site to departmental gauge and Spreading
including cost and conveyance of all material and labour charges etc complete

Unit = cum
Taking output = 15 cum
c) Material
Cost of Sand Cum 1.00 908.76 908.76

908.76
Total cost per cum 908.76 /Cum

// Data approved //

Asst.Exe.Engineer Dy.Executive Engineer


MP Narayanpet PR SD Narayanpet