S P SINGLA CONST.PVT.

LTD SPS/EHS/
GAS CUTTING SET CHECKLIST 017
S P SINGLA CONST.PVT LTD.

Construction of Bhanupali-Bilaspur-Beri New BG Line in the State of Punjab &


Himachal Pradesh, India

Name of the cutting set User/Contractor: ___________________________________________


Date of the Inspection: ______________________ Cutting Set Sl. No:____________________

S.No. Items Checked Yes No Remarks


1. Cylinders used are in upright and secured position

2. Cylinders in used are kept away from sunlight,


sparks and excessive heat.
3. Soap solution available for testing for leakages in
cylinder
4. All Connections are “ Soap solution” tested to be
leak free
5. Cylinders are kept away from live electrical cables
or ground
wires
6. Regulators and torches are in sound and working
condition
7. Hoses are free from tape or wrapping materials
used for
plugging leaks
8. Proper connections are used for fastening

9. Any kinked or tangled hoses

10. Hoses protected from Burning / mechanical


damage
11. Flash back arrestor provided for cylinder / Non
return valve
provided for the torch

Foreman Sign:

Checked By Reviewed By Project Manager


Name and Signature Name and Signature Signature