S P SINGLA CONST.PVT.

LTD
JCB/LOADER/POKLANE CHECKLIST SPS/EHS/018
S P SINGLA CONST.PVT LTD.

Construction of Bhanupali-Bilaspur-Beri New BG Line in the State of Punjab & Himachal


Pradesh, India

Name of the Contractor / Operator:…………………………………………………..

Inspected BY: ……………………………….., Location:………………………………..

SlN Check point Yes NO Remark


o
1 Is The machine starting smoothly?

2 Is there any oil /water /diesel leakage?

3 Are the hydraulic lines in good condition?

4 Are the hydraulic control levers /valves


working properly?
5 Are the directions in working condition?

6 Are the brakes / Parking brakes effective?

7 Is the reveres horn in working condition?

8 Is there any leakage in the hydraulic hoses?

9 Is a tire at required air pressure?

10 Are the operating handles fixed properly?

11 Are the steering / acceleration smooth?

Date of Inspection ……………..………… Next inspection is due on ………..………….


Signature of Safety officer Signature of Site Engineer
Sign. of HSE Expert / PM
S.P Singla Construction Pvt ltd S.P Singla Construction Pvt ltd M/s Meinhardt Singapore PTE Ltd