Professional Documents
Culture Documents
Construction Contracts
Construction Contracts
Construction Contracts
Project 1 Project 2
What amount of gross profit (loss) would Bell report in 2016 under the zero profit method and the percentage-of-
completion method?
Solution 1 Answer A
Under the zero profit method. The expected income on project 1 [P420,000 – (P240,000 + P120,000) = P60,000] is
not recognized until the project is completed. However, under this method, an expected loss on a contract must be
recognized in full in the period in which it is discovered. Project 2 has an expected loss of (P20,000) [P800,000 –
(P280,000 + P40,000)] which must be recognized immediately in 2016.
Under the percentage-of-completion method gross profit is recognize using the following formula:
Cost to date
X Estimated profit = Gross profit to date
Total estimated costs
Bell would recognize gross profit of P40,000 on project 1:
P240,000
X [P420,000 – (P240,000 + P120,000)] = P40,000
P240,000 + P120,000
Note that prior years’ gross profit need not be subtracted from P40,000 because the project commenced during 2016.
Under both the percentage-of-completion method and the zero profit method an expected loss must be recognized in
full in the period in which the expected loss is discovered. Project 2 has an expected loss of (P20,000) [P300,000 –
(P280,000 + P40,000)] which must be recognized in full in 2016. The net gross profit recognized on the two projects
is P20,000 (P40,000 profit less (P20,000) loss.
2. Cord Builders, Inc. has consistently used the percentage-of-completion method of accounting for construction-
type contracts. During 2014 Cord started work on a P9,000,000 fixed-price construction contract that was completed
in 2016. Cord’s accounting records disclosed the following:
December 31
2014 2015
Solution 2 Answer A
The total expected income on the contract at 12/31/2015 is P900,000 (P9,000,000 – P8,100,000). The formula for
recognizing profit under the percentage-of-completion method is:
Costs to date
X Expected profit = Profit recognized to date
Total expected costs
P6,300,000
X P900,000 = P700,000
P8,100,000
This result is the total profit on the contract in 2012 and 2013. The 2012 profit recognized must be subtracted from
P700,000 to determine the 2010 profit. At 12/31/2013, the total expected income on the contract was P1,200,000
(P9,000,000 – P7,800,000). The income recognized in 2014 was P600,000, as computed below:
P3,900,000
X P1,200,000 = P600,000
P7,800,000
Therefore, 2015 income id P700,000 less P600,000, or P100,000.
3. State Co. recognizes construction revenue and expenses using the percentage-of-completion method. During
2015 a single long-term project was begun, which continued through 2016. Information on the project follows:
2015 2016
Accounts receivable from construction contract P100,000 P300,000
Construction expenses 105,000 192,000
Construction in progress 122,000 364,000
Partial billings on contract 100,000 420,000
Solution 3 Answer A
Profit to be recognized using the percentage-of-completion method is generally computed as follows:
Costs to date
X Expected profit = Profit recognized in previous periods
Total expected costs
Not enough information is given in this problem to perform this computation, so 2016 profit must be computed
indirectly. Since only construction expenses and profit are debited to the construction-in-progress (CIP account),
2015 profit must have been P17,000 (P122,000 CIP less P105,000 cons. exp.) Cumulative profit recognized by the
end of 2014 must be P67,000 [P364,000 CIP less P297,000 cumulative cons. exp. (P105,000 + P192,000)].
Therefore, 2016 profit was P50,000 (P67,000 – P17,000).
CIP
4. Lake Construction Company has consistently used the percentage-of-completion method of recognizing income.
During 2015 Lake entered into a fixed-price contract to construct an office building for P10,000,000. Information
relating to the contract is as follows:
At December 31
2015 2016
Percentage of completion 20% 60%
Estimated total cost at completion P7,500,000 P8,000,000
Income recognized (cumulative) 500,000 1,200,000
Solution 4 Answer B
Based on the information given it must be assumed that costs incurred are used to measure the extent of progress
toward project completion. At 12/31/2015, the project was 20% complete and total estimated costs were
P7,500,000. Therefore, costs incurred as of 12/31/2015 were 20% of P7,500,000, or P1,500,000. At 12/31/2015, the
project was 60% complete and total estimated costs were P8,000,000, or P4,800,000. The costs incurred during
2016 were P4,800,000 less P1,500,000, or P3,300,000.
5. Hansen Construction, Inc. has consistently used the percentage-of-completion method of recognizing income.
During 2016 Hansen started work on a P3,000,000 fixed-price construction contract, The accounting records
disclosed the following data for the year ended December, 31, 2016:
6. Marr Construction Company has consistently used the percentage-of-completion method. On January 10, 2015,
Marr began work on a P6,000,000 construction contract. At the inception date, the estimated cost of construction
was P4,500,000. The following data relate to the progress of the contract:
How much income should Marr recognize for the year ended December 31, 2016?
a. P300,000
b. P525,000
c. P600,000
d. P900,000
Solution 6 Answer A
Contract Price P6,000,000
Less total estimated costs:
Cost to date P3,600,000
Cost to complete 1,200,000 4,800,000
Estimated gross profit 1,200,000
% of completion (P3,600,000 ÷ P4,800,000) 75%
Income recognized to date 900,000
Income recognized at 2015 600,000
Income recognized in 12/31/2016 P300,000
7. The following data relating to a construction job started by SS Co. during 2016:
8. On April 1, 2016, BB Inc. entered into a cost-plus-fee contract to construct an electric generator for Dalton
Corporation. At the contract date, BB estimated that it would take two years to complete the project at a cost
P2,000,000. The fixed fee stipulated in the contract is P300,000. BB appropriately accounts for this contract under
the percentage-of-completion method. During 2016, BB incurred costs of P700,000 related to the project, and the
estimated cost of December 31, 2016 to complete the contract is P1,400,000. Dalton was billed P500,000 under the
contract.
The gross profit to be recognized by BB Inc. under the contract on December 31, 2016 is.
a. P300,000
b. P100,000
c. P200,000
d. P0
Solution 8 Answer B
BB Inc. will earn P300,000 in total income from this project, regardless of the actual costs incurred, since it is a
cost-plus-fixed-fee contract. The amount to be recognized in 2016 is computed as follows:
Cost incurred to date
X Fixed Fee = Income recognized for 2008
*Total estimated costs
P700,000
X P300,000 = P100,000
*P700,000 + P1,400,000
9. The Robert Construction Corporation uses the percentage-of-completion method of accounting. In 2016, Robert
began work on a contract it had received which provided for a contract price of P8,000,000. Other details follow:
10.In 2016, Long Corporation began construction work under a three-year contract. The contract price is P800,000.
Long uses the percentage-of-completion method for financial- accounting purposes. The income to be
recognized each year is based on the proportion of cost incurred to total estimated costs for completing the
contract. The financial-statement presentations relating to this contract at December 31, 2016 follows:
Solution 10 Answer B
The cash collection in 2016 is computed below:
Contract billings P47,000
Less Accounts Receivable 15,000
Cash collected in 2016 P32,000
The amount to be shown as excess of cost over billings or (billings in excess of cost) in December 31, 2016?
a. (P400,000)
b. P260,000
c. P400,000
d. (P260,000)
Solution 11 Answer C
Constract Costs incurred to date, 2016 P4,250,000
Less: Loss on contract to date:
Contract Price P4,000,000
Total estimated Cost 4,250,000 (250,000)
Net 4,000,000
Billings to date 3,600,000
Costs in excess of billings P400,000
12. X Company uses the percentage-of-completion method of recognizing income. In 2015, work was started on a
P18,000,000 job completed in 2015. Records in 2016 show the following:
Solution 12 Answer D
Contract Price P18,000,000
Estimated cost:
Cost incurred P5,400,000
Cost to complete 10,800,000 16,200,000
Estimated gross profit 1,800,000
% of completion (P5,400,000 ÷ P16,200,000) 33.1/3%
Gross profit recognized in 2016 P600,000
13. In 2016 North Construction Co. was constructed to do the private road network of Subdivision Corp. for P100
million. The project was estimated to be completed in two years.
The construction contract provided among other things the following:
a. Five percent mobilization fee (to be deducted from the last billing) payable within fifteen days after the
signing of the contract;
b. Retention provision of 10% on all billings, payable with the final bill after the acceptance of the completed
project; and
c. Progress billings on construction are payable within seven days from acceptance.
North estimated its gross margin on the project at 25%.It used the percentage of completion method of accounting.
By the end of the year, North presented progress billings corresponding to 50% completion. Subdivision Corp.
accepted all the bills presented except the last one for 10% which was accepted on 10 January. With the exception of
the second to the last billing of 8% accepted in 2016 which was due on 3 January 2017, all accepted billings were
settled.
In 2016 North realized gross profit from the Subdivision project the sum of
a. P10,000,000
b. P12,500,000
c. P25,000,000
d. P 7,500,000
Solution 13 Answer B
Contract Price P100,000,000
Gross profit rate 25%
Estimated gross profit 25,000,000
% of completion 50%
Gross profit realized in 2016 P12,500,000
14. On September 14, 2016, Contractors Inc. won the bid for the construction of a 1,000 room hotel for Victoria,
Inc. on the reclamation are for P1.2 billion. On the terms of payment, parties agreed to the following:
a. One percent mobilization fee (deduction from the final bill) payable within fifteen days after the signing
of the contract;
b. Retention of 10% on all billings, payable with the final bill after the acceptance of entire completed
project; and
c. Progress billings on construction within seven days from date of acceptance.
By the end of 2016, the company had presented only one progress billings for 10% completion which Victoria,
Inc. evaluated and accepted on 28 December for payment in January. The company used the percentage of
completion method of accounting.
Solution 14 Answer C
The fee received by contactor’s fee is P12,000,000 (1% of the bid price of P1.2 Billion).
15. Bona Constructors, Inc. has the following data for a large jobs in its Jobs in Progress account (000’s omitted):
Project no. Actual Cost Estimated Total Cost Contract Price Percent Complete
101 P8,756 P172,800 P192,000 5
102 11,457 14,875 17,500 75
103 53,865 61,250 87,500 80
104 22,800 39,760 49,700 55
105 44,500 122,310 151,000 35
P141,378 P410,995 P497700
The company accounts for its large jobs under the percentage of completion method. Billings are done as follows:
a. 20% down payment upon contract signing.
b. Balance is billed according to percentage of completion less an application of the down payment which is
also according to percentage of completion.
The total billings made for the large job is:
a. P203,286
b. P99,540
c. P104,246
d. P193,786
Solution 15 Answer A
20 % Down payment on contract price:
P192,000 x .20 P38,400
17,500 x .20 3,500
87,500 x .20 17,500
49,700 x .20 9,940
151,000 x .20 30,200
Total P99,540