EV/QS-01/REV-01/NOV-18

GBEMICH SEVICES
APPLICATION FOR PAYMENT- NO:
AS AT:02/08/2022

Date of Application : 2/8/2022

CONTRACT CIVIL CONSTRUCTION WORK


CLIENT LADOL
CONSULTANT FO-AB
CONTRACT PRICE: 78,765,193 (ORIG) (REV) : 0
COMMENCEMENT DATE 7/12/2021 COMPLETION DATE

SUMMARY OF VALUATION

BILL DESCRIPTION AMOUNT (N)

1a Milestone (25% of contract price)

1 Mobilization / Advance Payment - 1. All formwork material 2. All


civil work materials 3. Advance payment for the production of
alluminium sheet coverings
1b Milestone (20% of contract price)
2
1. All aluminium materials
2. All balance materials
2 Milestone
1. Footings, Stub (20%
columns, and tieof contract
beams price)
(100% completed)
2. Store room and changing room
substructure (100% completed) 3. Store room
3 and changing room superstructure (50% completed)
4. Purlin materials

AMOUNT DUE THIS VALUATION (20% of contract price) 15,750,038.60