2022 Bid Tabulations For ADA Improvements

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

BID TABULATION

2022 CITY PROJECT NO. 2


ADA IMPROVEMENTS
EAST GRAND FORKS, MN
Proposal 1
3/1/2022 Engineers Estimate Opp Construction H & S Construction Tony Anderson Construction
ITEM UNIT UNIT UNIT UNIT
ITEM NO. DESCRIPTION UNIT QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
01 5526 MOBILIZATION LUMP SUM 1 $ 3,500.00 $ 3,500.00 $ 2,500.00 $ 2,500.00 $ 5,000.00 $ 5,000.00 $ 1,000.00 $ 1,000.00

01 5526 TRAFFIC CONTROL LUMP SUM 1 $ 2,500.00 $ 2,500.00 $ 3,200.00 $ 3,200.00 $ 3,500.00 $ 3,500.00 $ 2,300.00 $ 2,300.00

01 5713 STORM DRAIN INLET PROTECTION EACH 3 $ 200.00 $ 600.00 $ 300.00 $ 900.00 $ 300.00 $ 900.00 $ 175.00 $ 525.00

02 4100 REMOVE CONCRETE CURB & GUTTER LIN FT 256 $ 10.00 $ 2,560.00 $ 6.50 $ 1,664.00 $ 15.00 $ 3,840.00 $ 16.00 $ 4,096.00

02 4100 REMOVE PAVEMENT SQ YD 42 $ 25.00 $ 1,050.00 $ 57.00 $ 2,394.00 $ 15.00 $ 630.00 $ 25.00 $ 1,050.00

02 4100 REMOVE CONCRETE PAVEMENT SQ YD 162 $ 20.00 $ 3,240.00 $ 20.00 $ 3,240.00 $ 25.00 $ 4,050.00 $ 25.00 $ 4,050.00

02 4100 REMOVE 4" CONCRETE SIDEWALK SQ FT 1,767 $ 3.00 $ 5,301.00 $ 1.10 $ 1,943.70 $ 2.50 $ 4,417.50 $ 2.40 $ 4,240.80

02 4100 REMOVE CONCRETE DRIVEWAY SQ YD 8 $ 80.00 $ 640.00 $ 45.00 $ 360.00 $ 50.00 $ 400.00 $ 25.00 $ 200.00

02 4100 SALVAGE / INSTALL SIGN EACH 1 $ 250.00 $ 250.00 $ 200.00 $ 200.00 $ 500.00 $ 500.00 $ 200.00 $ 200.00

02 4100 CLEAR AND GRUB TREE EACH 1 $ 2,000.00 $ 2,000.00 $ 1,000.00 $ 1,000.00 $ 600.00 $ 600.00 $ 500.00 $ 500.00

32 1216 CONSTRUCT PAVEMENT SQ YD 42 $ 175.00 $ 7,350.00 $ 210.00 $ 8,820.00 $ 150.00 $ 6,300.00 $ 235.00 $ 9,870.00

32 1600 7" CONCRETE PAVEMENT SQ YD 162 $ 90.00 $ 14,580.00 $ 93.00 $ 15,066.00 $ 100.00 $ 16,200.00 $ 130.00 $ 21,060.00

32 1600 CONCRETE CURB & GUTTER, DESIGN B624 LIN FT 256 $ 50.00 $ 12,800.00 $ 47.00 $ 12,032.00 $ 50.00 $ 12,800.00 $ 75.00 $ 19,200.00

32 1600 4" CONCRETE SIDEWALK SQ FT 924 $ 12.00 $ 11,088.00 $ 16.00 $ 14,784.00 $ 10.00 $ 9,240.00 $ 9.50 $ 8,778.00

32 1600 6" CONCRETE SIDEWALK SQ FT 1096 $ 14.00 $ 15,344.00 $ 20.00 $ 21,920.00 $ 11.00 $ 12,056.00 $ 10.80 $ 11,836.80

32 1600 6" CONCRETE DRIVEWAY SQ YD 8 $ 150.00 $ 1,200.00 $ 160.00 $ 1,280.00 $ 110.00 $ 880.00 $ 130.00 $ 1,040.00

32 1600 DETECTABLE WARNING PANELS SQ FT 110 $ 65.00 $ 7,150.00 $ 66.00 $ 7,260.00 $ 70.00 $ 7,700.00 $ 80.00 $ 8,800.00

32 1723.13 CROSSWALK MARKINGS SQ FT 378 $ 6.00 $ 2,268.00 $ 4.50 $ 1,701.00 $ 26.00 $ 9,828.00 $ 30.00 $ 11,340.00

32 1723.13 24" STOP BAR LIN FT 36 $ 10.00 $ 360.00 $ 9.00 $ 324.00 $ 53.00 $ 1,908.00 $ 30.00 $ 1,080.00

32 9219 TOPSOIL BORROW (LV) CU YD 20 $ 50.00 $ 1,000.00 $ 45.00 $ 900.00 $ 50.00 $ 1,000.00 $ 62.00 $ 1,240.00

32 9219 TURF ESTABLISHMENT SQ YD 241 $ 12.00 $ 2,892.00 $ 16.00 $ 3,856.00 $ 6.00 $ 1,446.00 $ 15.00 $ 3,615.00

TOTAL BID PROPOSAL 1 $ 97,673.00 $ 105,344.70 $ 103,195.50 $ 116,021.60

25
BID TABULATION

2022 CITY PROJECT NO. 2


ADA IMPROVEMENTS
EAST GRAND FORKS, MN
Proposal 2
3/1/2022 Engineers Estimate Opp Construction H & S Construction Tony Anderson Construction
ITEM UNIT UNIT UNIT UNIT
ITEM NO. DESCRIPTION UNIT QUANTITY PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT PRICE AMOUNT
01 5526 MOBILIZATION LUMP SUM 1 $ 2,000.00 $ 2,000.00 $ 2,500.00 $ 2,500.00 $ 12,000.00 $ 12,000.00 $ 1,000.00 $ 1,000.00

01 5526 TRAFFIC CONTROL LUMP SUM 1 $ 2,500.00 $ 2,500.00 $ 2,800.00 $ 2,800.00 $ 2,750.00 $ 2,750.00 $ 1,000.00 $ 1,000.00

01 5713 STORM DRAIN INLET PROTECTION EACH 9 $ 200.00 $ 1,800.00 $ 300.00 $ 2,700.00 $ 300.00 $ 2,700.00 $ 175.00 $ 1,575.00

02 4100 REMOVE CONCRETE CURB & GUTTER LIN FT 201 $ 14.00 $ 2,814.00 $ 15.00 $ 3,015.00 $ 15.00 $ 3,015.00 $ 16.00 $ 3,216.00

02 4100 REMOVE 4" CONCRETE SIDEWALK SQ FT 1413 $ 3.00 $ 4,239.00 $ 1.40 $ 1,978.20 $ 5.00 $ 7,065.00 $ 2.40 $ 3,391.20

02 4100 REMOVE 6" CONCRETE SIDEWALK SQ FT 150 $ 6.00 $ 900.00 $ 2.40 $ 360.00 $ 5.00 $ 750.00 $ 2.40 $ 360.00

02 4100 SALVAGE / INSTALL SIGN EACH 2 $ 250.00 $ 500.00 $ 200.00 $ 400.00 $ 300.00 $ 600.00 $ 200.00 $ 400.00

31 2200 COMMON EXCAVATION (P) CU YD 2 $ 100.00 $ 200.00 $ 60.00 $ 120.00 $ 125.00 $ 250.00 $ 75.00 $ 150.00

32 1600 CATCH BASIN CASTING ASSEMBLY EACH 1 $ 2,500.00 $ 2,500.00 $ 1,400.00 $ 1,400.00 $ 1,600.00 $ 1,600.00 $ 750.00 $ 750.00

32 1600 CONCRETE CURB & GUTTER, DESIGN B624 LIN FT 201 $ 50.00 $ 10,050.00 $ 49.00 $ 9,849.00 $ 50.00 $ 10,050.00 $ 75.00 $ 15,075.00

32 1600 4" CONCRETE SIDEWALK SQ FT 740 $ 12.00 $ 8,880.00 $ 16.00 $ 11,840.00 $ 10.00 $ 7,400.00 $ 9.50 $ 7,030.00

32 1600 6" CONCRETE SIDEWALK SQ FT 830 $ 14.00 $ 11,620.00 $ 20.00 $ 16,600.00 $ 11.00 $ 9,130.00 $ 10.80 $ 8,964.00

32 1600 DETECTABLE WARNING PANELS SQ FT 90 $ 65.00 $ 5,850.00 $ 60.00 $ 5,400.00 $ 70.00 $ 6,300.00 $ 80.00 $ 7,200.00

32 1723.13 REMOVE CROSSWALK STRIPING SQ FT 135 $ 8.00 $ 1,080.00 $ 10.00 $ 1,350.00 $ 15.00 $ 2,025.00 $ 15.00 $ 2,025.00

32 1723.13 CROSSWALK MARKINGS SQ FT 636 $ 6.00 $ 3,816.00 $ 4.50 $ 2,862.00 $ 26.00 $ 16,536.00 $ 30.00 $ 19,080.00

32 1723.13 24" STOP BAR LIN FT 90 $ 10.00 $ 900.00 $ 9.00 $ 810.00 $ 53.00 $ 4,770.00 $ 30.00 $ 2,700.00

32 1723.13 YELLOW CURB PAVEMENT MARKING LIN FT 217 $ 8.00 $ 1,736.00 $ 11.00 $ 2,387.00 $ 12.00 $ 2,604.00 $ 10.00 $ 2,170.00

32 9219 TOPSOIL BORROW (LV) CU YD 20 $ 50.00 $ 1,000.00 $ 45.00 $ 900.00 $ 45.00 $ 900.00 $ 62.00 $ 1,240.00

32 9219 TURF ESTABLISHMENT SQ YD 181 $ 12.00 $ 2,172.00 $ 16.00 $ 2,896.00 $ 6.00 $ 1,086.00 $ 15.00 $ 2,715.00

TOTAL BID PROPOSAL 2 $ 64,557.00 $ 70,167.20 $ 91,531.00 $ 80,041.20


TOTAL BID PROPOSAL 1 + PROPOSAL 2 $ 162,230.00 $ 175,511.90 $ 194,726.50 $ 196,062.80

26