NO. Description Commulative Current Month Up To Last Month: From Project Start To Date
NO. Description Commulative Current Month Up To Last Month: From Project Start To Date
HEAD COUNT
2 Total Working Days (TWD) 34 26 34
3 Total Man Days Worked (TMD) 0 0 0
4 Total Manhours Worked (TMH) 0 0 0
5
Total Man hours from the Last LTI 0 0 0
6 Safety Manpower (Including Sub-Contractor) 2 2 2
Site security Manpower 1 1 1
7 1 0 1
LAGGING INDICATORS/ACCIDENT &
20 Tamimi Safety Observation Report (SOR & SI) received from K&A 355 25 330
21 Tamimi Safety Violation letter (SVL) received from K&A 28 7 21
22 Tamimi Safety MEMO received from K&A 0 0 0
TR
People Inducted
25 Tamimi Toolbox talk 134 22 112
26
0 0