To eliminate the concept of negligence among contractors, the Safety Department administers safety
orientations for contractors. These orientations are carried out by the safety inspector. In these
orientations the safety inspector explains the basic ideas of safety, how an individual can protect
himself against harm, and the Corporation’s Safety Rules that govern all kinds of activities in plant
including people’s behavior. Therefore, a Contractors Safety Handbook was compiled by Al-Jubail
Plants. The handbook mandates safety obligations for the contractor which he has to fulfill. The
handbook is believed to organize and control all activities conducted by the contractor’s employees.
In other words, it clearly states SWCC’s guidelines which the contractor needs to comply with.
Figure (2-1) shows how the Policy should be carried out.
No
All the above Contractor completes all
Fulfilled? Requirements
Yes
Clearance for ID Issuance
FOREWORD
This Contractor Safety handbook is prepared in conjunction with SWCC approved Systems and
Procedures as attachment to the STANDING INSTRUCTION No. P-037 with special reference
to the following documents and is issued as basic guidelines to be adhered by all contractor
personnel engaged at SWCC facilities.
This Handbook is divided into two sections. Chapter-1 “CONTRACTORS’ SAFETY
ORIENTATION PROGRAM” is intended for familiarization of all the Contractors engaged by
SWCC to work on its facilities with the Safety Principles and Policies of the Plant and to
provide them with the basic and minimum Safety requisites to ensure compliance with the
Safety Rules & Regulation. The Safety Orientation Program will be conducted by Fire &
Safety Department to the Contractor Management and Supervisors prior to commence their
activities.
Chapter-2 “CONTRACTOR SAFETY GUIDELINES” is for procedural description and
detailed instructions on execution of contractor’s activities in a safe and secure manner. This
section deals with the Safety Principles and Safe working practices. All Contractors shall
therefore, ensure that they meet all the Safety requirements and obligations prior to commence
their work at SWCC premises and that all employees are fully aware of the Safety Regulation
and exercise the same to ensure Safety of all men irrespective of their employers and of all
SWCC proprietary.
In the event of conflict in applying the Standard Procedures and Practices, SWCC Fire &
Safety Department with the approval of Plant Manager shall take the necessary action to
resolve the conflict and to ensure the greatest protection of the Safety and Health of all
personnel and Safety of the SWCC proprietary.
COPIES OF THIS HANDBOOK SHALL REMAIN AVAILABLE AT CONTRACTOR’S
JOBSITE THROUGHOUT THE TENURE OF HIS WORK DURATION AT SWCC
PREMISES.
For more precise course of action and guidelines needed in determining safe procedures and
practices, the following standards will be used as the source of origin.
References:
Occupational Safety & Health Administration (OSHA) 1910 & 1926
National Electrical Code (NEC)
National Fire Protection Association (NFPA)
American National Standard Institute (ANSI)
Nuclear Regulatory Authority (IAEA)
Middle East Environmental Protection Agency (MEEPA)
Handbook of Civil Engineering
SWCC Systems and Procedures
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
TABLE OF CONTENTS
CH A P T E R- 1 CO NT R A CT O R S S A F E T Y O RI E NT A T I O N
i
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
C H A P T E R - 2 C O N T R A C T O R S S A F E T Y G U I D E LI N E S
SECTION DESCRIPTION PAGE No.
i. MANAGEMENT …………………………………..…………………….. 13
Figure 1.1-Example of Project Manager’s Pledge ………………….. 13
ii. SAFETY REPRESENTATIVE ………………………………………… 13
iii. SUPERVISOR / FOREMAN …………………………………………… 14
iv. EMPLOYEE ……………………………………………………………… 14
4. CONTRACTOR SAFETY REQUIREMENTS ..………………………….… 14
i. FATALITIES …………………………………………………………….. 18
ii. SERIOUS INJURIES …………………………………………………… 18
iii. EMPLOYEE LOST WORKDAY CASE ………………………………. 18
iv. SPECIAL INVESTIGATION OF ACCIDENTS ………………………. 19
v. ACCIDENT REPORTING ……………………………………………… 19
vi. ACCIDENT INVESTIGATION REPORT FORMS …………………… 19
vii. MEDICAL FACILITIES ………………………………………………… 20
7. RULE OF CONDUCT AND SAFETY REGULATIONS ………………….. 20
ii
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
C H A P T E R - 2 C O N T R A C T O R S S A F E T Y G U I D E LI N E S
SECTION DESCRIPTION PAGE No.
iii. PERMISSION TO WORK ……………………………………………… 20
iv. WORK DRESS STANDARD ………………………………………….. 21
v. PERSONAL PROTECTIVE EQUIPMENT …………………………… 21
vi. WORK SAFETY INSPECTION ……………………………………….. 21
vii. EQUIPMENT INSPECTION, O & M AND REPAIR ……………..….. 21
viii. REPORTING OF UNSAFE CONDITIONS …………………………… 22
ix. REPORTING OF INJURIES AND PROPERTY DAMAGE ………… 22
x. PERSONAL CONDUCT ……………………………………………….. 22
xi. INSUBORDINATION …………………………………………………… 23
xii. DRUG POSSESSION AND USE ……………………………………… 23
8. SPECIFIC TASKS …………………………………………….……………… 23
iii
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
CHAPTER-1
iv
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
1. CONTRACTOR’S PROFILE
CONTRACTOR’S NAME
ADDRESS
TELEPHONE NO.
PAGE 1 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
OUTLINE
10. The Confined Space Entry and Permit to Work System of SWCC will be followed.
These permits can be obtained by contacting the area Shift Charge Engineer.
11. All contract personnel are required to wear the full body harness when working roofs
or elevated structures above 1.8 M (6 ft).
12. All scaffoldings shall be properly erected as per standard. Planking is to be fixed
with hook clamps, pipe lock at both ends or equipped with cleats. Ladder should
protrude at least 36" from top the rail.
13. Horse play is dangerous and will not be tolerated.
14. Contract employees operating moving equipment shall be trained and authorized to
operate such equipment.
15. All power tool cords, equipment, cables and extension cords must be protected with
Ground Fault Circuit Interrupters (GFCI). It should not be hung up off the ground to
prevent tripping hazards. Do not hang cords or attached to hot pipes.
16. Any hazardous waste or regulated waste must be properly disposed by the contractor.
17. SWCC reserves the right to inspect all vehicles, equipment and packages entering or
leaving the plant.
18. Work on any chemical system by a contractor will require the appropriate permits,
personal protective equipment, and procedures.
S E C U R IT Y D E P A R T M E N T
4B 999
F IR E S T A T IO N 998
AM B UL AN CE (P L ANT ) 998
A M B U L A N C E ( C L IN IC ) 997
CE NT R AL CO NT RO L RO O M 996
SA F E T Y D E P A R T M E N T
S A F E T Y A N D F IR E C H I E F
S A F E T Y S P E C IA L I S T
5B
S A F E T Y IN S P E C T O R
PAGE 3 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
All contractor employees are required to be oriented in the safety requirement of the
Plant. Review all applicable items and check them off. Upon completion of the safety
orientation, sign the orientation checklist. The original copy will be filed at the
SWCC Safety Department.
i. MANDATORY ITEMS
16B
SAFETY GLASSES
Must meet ANSI Standard Z87.0.
PAGE 4 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
SAFETY SHOES
RESPIRATORS
All contract employees are trained in the hazards associated with the chemicals
being used.
MSDS will be provided to SWCC Safety Department for all chemicals that are
brought into the plant by contractor.
A Confined Space Entry permit must be obtained before entering any confined
space.
PAGE 5 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
Monitoring of Oxygen level will be performed before entry into confined space.
Full Body Harness and Lifeline must be provided should employees to enter any
tanks.
Contractor employees are not allowed to alter the position of any ISOLATION
boundaries of the Plant, Process or Equipment, neither they Start / Stop or hinder
in any Operation & Maintenance activities.
Contractor will use approved containers for any flammable liquids brought into
the plant.
Contractor will supply fire extinguishers during hot work operations.
Contract employees have been trained in the class of fire and types of fire
extinguishers.
A contract employee will be stand-by as fire watch during hot work operations.
All contract employees have been trained in the use of fire extinguishers.
Contract employees are aware of what to do in case of fire or emergency
evacuation.
PAGE 6 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
Oxygen, Acetylene and Liquefied Petroleum Gas (LPG) Cylinder Hoses should
be fixed with flashback arresters in the regulator side and check valves in torch
side.
Contract employees must wear fall protection (full body harness) when performing
work 1.8 M (6 ft.) or higher.
Contract employees have been trained in the proper use and inspection of fall
protection equipment.
All contract employees have been trained in the emergency signals used for
notifying employees in case of emergency.
Contract employees have been trained in procedures for evacuation of the plant.
Contract employees should be familiar with the locations of assembly points should
any emergency that require the plant to be evacuated.
Contractor will ensure that all mobile equipment (forklift, cranes, vehicles, etc.)
will be in good condition and working properly. Fire extinguisher should be
provided in each unit.
Contractor will provide valid driver’s license for contract employees who will be
driving vehicles within SWCC.
Traffic Rules and Regulations should be observed inside the premises.
PAGE 7 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
xii. EXCAVATION
27B
Contractor will evaluate excavation conditions (soil type / work area) and
familiarize employees with working conditions and any potential hazards that
may occur.
Contractor will barricade and provide adequate lightings in the excavation area
and identify the hazards present with safety sign.
Contractor will provide a ladder or steps for employees to enter and exit
excavation area when excavation area is deeper than 1.2 M (4 ft.).
xiii. DEMOLITION
28B
Contractor will meet with SWCC project coordinator prior to working to review
operating procedures and demolition requirements.
In applying demolition permit the area should be detailed.
Contractor will ensure that all utilities (gas, water and electricity) have been shut
off and placed in a ZERO POTENTIAL ENERGY STATE before starting to
work.
Contractor will place barricade tape around the demolition work area and hang
safety signs identifying “DANGER – DO NOT ENTER”.
Contractor will ensure that surrounding areas, adjacent structures and equipment
are protected from demolition operations or debris.
Contractor will install bracing to stabilize walls, vessels or other structures
should be demolition work require.
Contractor will ensure that his employees are wearing proper personal protective
equipment for demolition operations (hard hat, safety shoes, goggles, ear plugs,
respirators heavy gloves and full body harness).
PAGE 8 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
6. CONTRACTOR ACKNOWLEDGEMENT
29B
Standing Instruction No. P-037”, was also given to me along with its attachment namely
“CONTRACTORS SAFETY GUIDELINES”.
I agree to review the above information with my subordinates of all Safety Policies and
Procedures requirements covered in these Guidelines and understand that any violators of
Safety Rules will not be admitted within the SWCC plant.
CONTRACTOR REPRESENTATIVE:
6B
Name: ______________________________
7B
Position:_____________________________
8B
Signature: ___________________________
9B
Date: _______________________________
Name: ______________________________
1B
Position:_____________________________
12B
Signature: ___________________________
13B
Date: _______________________________
PAGE 9 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
passed the Safety Orientation conducted by Fire and Safety Department concerning the
items contained within the SWCC “Contractor Safety Orientation Program” and fully
understands of all the contents and instructions given to me.
As a contract employee, I promised to abide all SWCC Safety Polices and Procedures and
15B
agree to receive any disciplinary action(s) including expulsion of SWCC plant, if the Safety
Policies and Procedures will be violated.
NAME SIGNATURE
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__
PAGE 10 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
CHAPTER-2
PAGE 11 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
PAGE 12 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
a. MANAGEMENT
a. The contractor’s Project Manager is directly responsible for compliance with provisions
of this Safety Manual and for execution of all items contained in the contractor’s Safety
Plan.
b. The contractor Project Manager shall monitor the work plan and issue directives and
delegate authority required for its safe and efficient execution.
c. The Project Manager shall sign a pledge that he will inform and instruct his
subordinates under his supervision of all existing SWCC Safety Rules, Guidelines and
Regulations. An example of the pledge is illustrated in Figure 1.1.
d. Coordination and cooperation shall be established and maintained with other contractors
sharing the same work location(s) or adjacent area(s) to assure a project-wide safe
environment.
CONTRACTOR’S PLEDGE
of ____________________________ as a ___________________________
Do hereby pledge to inform and instruct my employees on all existing Safety Rules and
Regulations in Saline Water Conversion Corporation (SWCC).
I understand that violators of Safety Rules shall not be admitted within the SWCC Premises.
____________________________ ___________________________
Signature Date
PAGE 13 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
b. SAFETY REPRESENTATIVE
a. The Contractor Foreman / Supervisor shall also act as “Safety Representative” who
shall be responsible for routine implementation of the SWCC Safety requirements. He
shall carryout daily safety inspection at the worksite.
b. All routine Safety matters shall be coordinated through the contractor Safety
representative.
c. SUPERVISORS / FOREMEN
a. The contractor’s Supervisor / Foreman shall be responsible for Safety Conduct and
work practices of the workers.
b. The contractor Supervisor / Foreman will be required to undergo test process for the
appointment of “AUTHORIZED PERSON” prior to commence the work, if the work
duration is more than a month. This is required to qualify him to Receive, Clear and
Suspend Permit to Work in the concerned area.
c. The Supervisor / Foreman shall execute provisions of the Safety Plan as detailed in
section III.a.1 above.
d. The Plan shall provide such Safety Training as required to perform the work in a safe
and efficient manner. Safety training may also be given by the Safety Representative or
Training Officer. This shall not relieve contractor’s Site Officials responsibility for
assuring that workers conduct themselves in a safe manner and employ safe work
practices.
d. EMPLOYEE
i. Each contractor employee shall be given safety instructions by his employer on, or prior
to, his first day at work site.
ii. The employee shall abide by all the safety training, instructions rules and all follow-up
supervision from his Supervisor / Foreman.
iii. He shall not engage in any activities which may endanger a fellow worker or SWCC
proprietary or is contrary to SWCC Safety and General Rules & Regulations.
iv. Orientation & Training requirements are mandatory for all tasks, including those in
Confined Spaces, Handling Toxic Materials, Ionizing Radiation, Explosives, Flammable
Liquids & Gases and other similar hazardous materials handling.
b. The Plan shall conform to Contractors Safety Plan Outline as indicated in Figure 1.2.
The Plan will form the basis for the Contractor’s Safety Program including employees
Safety training.
PAGE 15 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
PAGE 16 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
c. The contractor shall take the opportunity to consider alternative solutions without any
shortcut or bypassing of Safe working practices to resolve job safety hazards revealed
by the work task analysis such as:
d. When all factors of task as outlined in (2) and (3) above have been considered, general
and specific safety training programs shall be formulated and presented.
e. Follow-up training shall be accomplished through continuous monitoring by the
Supervisor of employee work practices to enforce and emphasize the safety training
they received.
f. Supervisor / Foreman shall correct immediately any unsafe work practices or job
conditions note during follow-up training which could cause accidents.
g. Orientation & Training requirements are mandatory for all tasks, including those in
Confined Spaces, Handling Toxic Materials, Ionizing Radiation, Explosives, Flammable
Liquids & Gases and other similar hazardous materials in handling and operations.
h. The Saudi Arabian Government requirements for vehicle and other machinery operation
to have valid Driver's License / Operator’s Permit will be mandatory respectively.
PAGE 17 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
i. FATALITIES
a. For on duty fatalities, the contractor shall investigate injuries received as a consequence
of occupational related hazards and exposures regardless of the length of time between
the occurrence and death.
b. The contractor shall investigate all fatalities of persons other than his employees whose
deaths are apparently related to contractor activities.
PAGE 18 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
v. ACCIDENT REPORTING
a. Any accident related to contractor’s activities, resulting in personnel Injury, Damage to
SWCC Property or Production Loss (irrespective of its magnitude) must be reported
promptly to SWCC Fire & Safety Department.
b. Accidents / Injuries resulting in fatal or serious injuries shall immediately reported by
the contractor to SWCC Fire & Safety Department by telephone. Immediate notification
of the incident by telephone shall also be made by the contractor to SWCC Security.
c. The verbal information of the incident shall be followed by written notification of the
accident / injury on the prescribed form.
d. Within 5 days of the closing of each Gregorian month, the contractor will provide the
SWCC Fire & Safety Department a summary of job related accidents and injuries of the
preceding month. Injuries shall be reported on the form provided and all sections of the
form shall be completed
Note:
The Report Form does not replace but is in addition to “NOTICE OF EVENT,
OCCURRENCE OR LOSS” or other similar forms required by the Insurance Brochure
& Claim Procedure Manual which is issued by the Insurance Agency.
PAGE 19 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
PAGE 20 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
PAGE 21 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
x. PERSONAL CONDUCT
a. Indulgence in practical jokes, horseplay, scuffling, wrestling or fighting is forbidden
within SWCC premises.
b. Destroying or tempering with Safety Devices, Signs and Signals or willfully and
unnecessarily discharging Fire Extinguishing Units are prohibited.
c. Sleeping on the site is strictly prohibited.
d. Wandering around in areas other than jobsite is not allowed.
e. Smoking or use of open flame in areas of ‘NO SMOKING’ is prohibited.
f. Carrying of matches, cigarette lighters and other source of ignition in all fuel or gas
areas where such items are a hazard shall cause for disciplinary action.
g. Observance of Road Traffic Rule and Regulations within SWCC premises is mandatory.
PAGE 22 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
h. Contractor employee shall promptly report all observed unsafe and potentially
hazardous condition to their Foreman / Supervisor so that timely corrective action can
be taken to prevent injuries or damage.
xi. INSUBORDINATION
a. Noncompliance toward any Supervisor in respect to carrying out properly issued
instruction or orders for Safety purposes shall be sufficient cause for initiating
disciplinary action against offender(s) in accordance with established disciplinary
procedures.
b. A copy of any disciplinary action initiated by contractor against violation of safety rules
and regulations of his employee(s) shall be sent to SWCC Fire & Safety Department for
record and follow-up.
8. SPECIFIC TASKS
c. SWCC Fire & Safety Department shall be informed in advance by the contractor about
such activities with the location and estimated duration of tasks.
PAGE 24 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
i. DEMOLITION COORDINATOR
a. Before demolition work starts, an experienced and skilled person having demolition
knowledge shall be appointed as “DEMOLITION COORDINATOR” by SWCC in
writing as the person in charge of that particular job.
b. The Coordinator shall directly supervise the work force, ensuring that PERMIT TO
WORK requirements are met, and liaise with other contractor(s) and SWCC employees
in the general area to the site to minimize disturbances.
v. SITE PROTECTION
a. Adjacent structures shall be protected from debris and where necessary, bracing shall be
installed to ensure their stability.
b. Barricades shall be erected around the work area.
c. Signs bearing words in bold 6 inches red or black on yellow background shall be
erected at frequent intervals at the approach points to the barricade. The wording on the
signs is detailed below:
Sign-1 shall read Sign-2 shall read
DANGER! DANGER!
DEMOLITION
IN DO NOT
PROGRESS ENTER
PAGE 25 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
PAGE 26 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
ii. It is relatively easy to eliminate explosive concentration of vapors within the large
tanks, vessel or pipe-work by forced ventilation using large blowers or ejector
system. This method will rapidly reduce the vapor concentration. With material less
volatile, the main dander lies in the hot cutting causing fire to any residues in the
tank. It is therefore essential that the residues are removed before work starts.
iii. The risk of explosion or fire during hot cutting work can be practically eliminated
by using cold cutting techniques. Although, often more costly and laborious, it may
prove to be the only safe method.
PAGE 27 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
PAGE 28 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
FORM CS -01
Description Of Accident:
Witness Statement(s)
PAGE 29 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
FORM CS – 02
CONTRACT No.
CONTRACTOR
PROJECT LOCATION
1. Work Injuries:
2. Fires:
SAFETY MEETING:
1.
2.
3.
4.
5.
(B) Attendance:
(C) Instructor(s):
PAGE 30 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
References:
Occupational Safety & Health Administration (OSHA)1910 & 1926
National Electrical Code (NEC)
National Fire Protection Association (NFPA)
American National Standard Institute (ANSI)
Nuclear Regulatory Authority (IAEA)
Middle East Environmental Protection Agency (MEEPA)
Handbook of Civil Engineering
SWCC Systems and Procedures
PAGE 31 of 32
ﻛﺘﻴﺐ ﺍﻟﺴﻼﻣـﺔ ﻟﻠﻤﻘﺎﻭﻟﻴﻦ
ﺍﻟﻤﺆﺳﺴﺔ ﺍﻟﻌﺎﻣﺔ ﻟﺘﺤﻠﻴﺔ ﺍﻟﻤﻴﺎﻩ ﺍﻟﻤﺎﻟﺤﺔ
S.W.C.C.
ﺇﺩﺍﺭﺓ ﺍﻷﻣﻥ ﺍﻟﺻﻧﺎﻋﻲ
CONTRACTOR SAFETY HANDBOOK ISD
FORM CODE CS - 03 03 - ﻡ ﺱ ﺭﻗـﻢ ﺍﻟﻨﻤﻮﺫﺝ
CONTRACTOR’S PLEDGE
of ____________________________ as a ___________________________
Do hereby pledge to inform and instruct my employees on all existing Safety Rules and
Regulations in Saline Water Conversion Corporation (SWCC).
I understand that violators of Safety Rules shall not be admitted within the SWCC Premises.
____________________________ ___________________________
Signature Date
PAGE 32 of 32