ID Task Task Name Duration Start Finish 2nd Half 1st Half 2nd Half 1st Half

Mode Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1 428 days Tue 4/5/22 Thu 11/23/23
Grian Public Park
2 STRUCTURAL WORKS 428 days Tue 4/5/22 Thu 11/23/23
3 Reception of site 6 days Tue 4/5/22 Tue 4/12/22
4 Letter of commencement of works 19 days Thu 4/7/22 Tue 5/3/22
5 EXCAVATION& BACKFILLING 139 days Fri 4/15/22 Wed 10/26/22
6 12 days
Machine excavation for foundations in normal soil Sat 4/16/22 Mon 5/2/22
7 Excavatinon for pile caps, all according to 18 days Fri 4/15/22 Tue 5/10/22
drawings

8 Back filling in making up levels, compacting 19 days Fri 4/29/22 Wed 5/25/22
9 Back filling around the stucture, compacting 27 days Thu 5/12/22 Fri 6/17/22
10 Removal of surplus excavated materil from site22 days Fri 7/15/22 Mon 8/15/22
11 CONCRETE WORKS 32 days Thu 5/12/22 Fri 6/24/22
12 REINFORCED CONCRETE 54 days Fri 5/20/22 Wed 8/3/22
13 provide and lay reinforced concrete mix C30 22 days Fri 5/20/22 Mon 6/20/22
four foundations

14 Ditto ,but for beams 18 days Tue 5/31/22 Thu 6/23/22


15 Ditto ,but for walls and columns 22 days Thu 6/16/22 Fri 7/15/22
16 Ditto ,but for staircases 16 days Thu 6/30/22 Thu 7/21/22
17 Ditto ,but forparapets and lintels 14 days Tue 7/5/22 Fri 7/22/22
18 Ditto, but for water tank 25 days Thu 6/30/22 Wed 8/3/22
19 PROTECTION 221 days Sun 6/12/22 Fri 4/14/23
20 176 days
provide and lay liquid asphaltic composition, two
21 179 days Wed 7/13/22Mon 3/20/23
ARCHITECTURAL WORKS
22 MASNORY 33 days Sat 7/30/22 Tue 9/13/22
23 WOODEN DOORS, FRAMES 45 days Thu 8/11/22 Wed 10/12/22
24 PVC WINDOWS, FRAMES 45 days Thu 9/8/22 Wed 11/9/22
25 PLASTERING AND RENDERING 89 days Thu 10/6/22 Tue 2/7/23
26 provide and lay external plaster ,for ceilings of 25 days Wed 9/14/22Tue 10/18/22
27 25 days
provide and lay internal plaster ,for internal wall, Mon 10/31/22Fri 12/2/22
28 provide and lay external render for elevation, 35 days Wed 11/9/22Tue 12/27/22
29 PAINTING AND PROTECTIVE 96 days Thu 12/8/22 Thu 4/20/23
COATING
30 FLOOR FINISHES 45 days Thu 12/29/22Wed 3/1/23
31 WALL FINISHES … Ceramic 48 days Fri 1/27/23 Tue 4/4/23
Tiles& Marble
32 74 days Tue 4/4/23 Fri 7/14/23
PLUMBING WORKS
33 152 days Wed 4/12/23Thu 11/9/23
ELECTRICAL WORKS
34 152 days Wed 4/12/23Thu 11/9/23
MECHANICAL WORKS
35 RECEPTION OF WORKS 10 days Sun 11/12/23Thu 11/23/23
36 RECEPTION OF WORKS 1 day Sun 11/12/23Sun 11/12/23
37 AS BUILT DRAWINGS 4 days Tue 11/14/23Fri 11/17/23
38 FOLD OF MATERIAL AND CLEANING OF 5 days
YARD Sat 11/18/23 Thu 11/23/23

Task Project Summary Manual Task Start-only Deadline

Project: grian Split Inactive Task Duration-only Finish-only Progress


Date: Tue 4/5/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone