Professional Documents
Culture Documents
Weekly Progress MOM 133 - 25 March 2021 - Draft
Weekly Progress MOM 133 - 25 March 2021 - Draft
Weekly Progress MOM 133 - 25 March 2021 - Draft
Attendees
Name Designation Organization Email Phone #
Mr. Omar Alnuaimi Project Manager Musanada Omar.alnuaimi@Musanada.com 0502334477
Mr. Yasir AlKubaisi Sr. Resident Engineer DCI/Parsons Yasir.AlKubaisi@parsons.com 0505933911
Mr. Alaa Ali Abudaqqa ARE- Electrical DCI/Parsons alaa.abudaqqa@parsons.com 0553400181
Mr. Shaji Divakaran ARE- Civil DCI/Parsons shaji.divakaran@parsons.com 0505353526
Mr. Said Ebrik HSE Engineer DCI/Parsons said.ebrik@parsons.com 0506614234
Mr. Reynaldo Rabuco Planning Engineer DCI/Parsons reynaldo.rabuco@parsons.com 0503384052
Mr. Aiad Hamdan Project Manager Ghantoot Group Eyad.hamdan@ghantootgroup.ae 0506618165
Mr. Mobashir Anwar HSE Coordinator Ghantoot Group Mobashir.anwar@ghantootgroup.ae 0547911238
Mr. Karan Sahai Project Engineer Electrical Ghantoot Group Karan.sahai@ghantootgroup.ae 056-5488524
Mr. Andrew Shaw Business Unit Manager Menard ashaw@menard-vibro.ae
Mr. Mustansar Javed Project Engineer Menard mjaved@menard-vibro.ae 0565076553
Mr. Wesam Abu El Maaty General Manager Al Makarem Global wesamabuelmaaty@gmail.com 0569629496
Mr. Mohamed Talaat Project Manager Al Makarem Global pm1@mkrmco.com 0527814828
Mr. Ahmed Omran Project Manager GCC First_omran@yahoo.com 0503195984
Mr. Moataz Loutfy CM - Landscape GCC Moataz.loutfy@outlook.com 0565040341
Page 1 of 6
Form Ref. TMT140, Rev- 1, Date: 9-Feb-17
MINUTES:
Status
Revised Target Completion
S. N Item/ Discussions Action By Target Date (NS/
Date Date
IP/CP)
1 Safety Moment:
Excavations and trenches: definitions, associated hazards and
control measures.
GTGC stated that three (3) near misses were reported during the IP
GTGC
week. However, related reports were not issued for review and 29th March 2021
follow-up by the Consultant.
Musanada PM asked GTGC regarding the PTW issuance. PM
instructed DCI HSE to review and investigate the PTW procedures of
GTGC and subcontractors and their implementations.
Workshop conducted and discussed all the future services at Road No. 25 GTGC/ 30th March 2021 IP
Since 04th March
and Roads at Sector MSH-06. Musanada requested to GTGC to submit the DCI 2021
shop drawings for sewer network at Road 13 in order to submit to KN for final
approval.
M/s Menard to submit IFC Drawings for Road No. 12 and Road No. 13 by Menard/ IP
next week. Menard has started the Inclined Grouting at the Services Corridor MAKAREM 09th March 2021
Page 3 of 6
Form Ref. TMT140, Rev- 1, Date: 9-Feb-17
Status
Revised Target Completion
S. N Item/ Discussions Action By Target Date (NS/
Date Date
IP/CP)
(RHS). Musanada PM reminded all attendees that full cooperation from all
Parties is essential and needs to work as a Team.
M/s Makarem planned to start precast elements in-situ. Makarem requested
for storage area at site for the cast precast elements. Makarem to submit Menard/
MAKAREM Since 11th March IP
related shop drawings and method statement.
2021
Workshop conducted on 28-Mar-2021 for the Alternative Design for Road
No.25/MSH-06 Roads (Road No. 14, 13 & 12) and the related new sequence
of works that will be implemented. Accordingly, M/s GTGC/Menard to submit
a revised Programme of Works.
GCC was reminded to secure the required Authorities approval for NDRC GCC
Works and Connection of RTU which was pending since 08-Jul-2020 and no
action from the Contractor.
GCC stated that TRANSCO had stopped the works from RA-02 to RA-04.
Page 4 of 6
Form Ref. TMT140, Rev- 1, Date: 9-Feb-17
Status
Revised Target Completion
S. N Item/ Discussions Action By Target Date (NS/
Date Date
IP/CP)
DCI asserted that GCC shall apply for a Work Permit from TRANSCO and
comply with their requirements. Musanad PM stressed that this had GCC
happened due to miscommunication on the part of GCC.
GCC to expedite the material approval for “Green Acrylic Coat” for Cycle
Track which was already delayed by about three (3) months noting that the
GCC
materil sis a long lead item.
Notes:
(1) Refer to attached “Record of Attendance”.
(2) Any addition, alteration or omission must be brought to the attention of the under signed within one working day from the date of issuance of these draft minutes otherwise these minutes
will be considered final.
(3) Use the following abbreviations: NS: Not started, IP: In Progress, CP: Completed.
Minutes Initiator Eng. Yasir Al Kubaisi Designation Sr. Resident Engineer
Organization/ Division/Dept. M/s. DeLeuw Cather International Date of Issuance 24th March 2021
Page 6 of 6
Form Ref. TMT140, Rev- 1, Date: 9-Feb-17