SUBJECT : BILL OF MATERIALS

PROJECT : GASOLINE STATION WITH ONE STOREY MIXED USE COMMERCIAL BUILDING
OWNER :
ARCHITECT :

QTY UNITS MATERIALS UNIT COST TOTAL COST


EXCAVATION
360 CU.M. EXCAVATION 500.00 180,000.00

MASONRY
5200 BAGS PORTLAND CEMENT 200.00 1,040,000.00
260 CU.M. FINE SAND 600.00 156,000.00
250 CU.M. COARSE AGGREGATE 960.00 240,000.00
400 CU.M. BACKFILLING MATERIALS 350.00 140,000.00
1600 PCS 16MM DIA. RSB 380.00 608,000.00
3000 PCS 10MM DIA. RSB 148.00 444,000.00
300 KG #16 G.I. WIRE 75.00 22,500.00
10000 PCS 5''CHB 11.00 110,000.00
2,760,500.00

FORMS & SCAFFOLDING


30 PCS 3/4X 4 X 8 PENOLIC PLYWOOD 1,250.00 37,500.00
2500 BDFT 2X3X12 COCO LUMBER 26.00 65,000.00
2 BOXES ASSORTD CWN 1,200.00 2,400.00
104,900.00

STEEL WORKS
4 PCS 16X16 X25mm BASE PLATE 2,600.00 10,400.00
1 LOT PRE-FABRICATED STEEL COL & BEAM 150,000.00 150,000.00
24 PCS 18"X20mm ANCHOR BOLT 490.00 11,760.00
280 PCS 2X4 G.1 C-PURLINS (1.2MM) 480.00 134,400.00
340 PCS 1/4X2X2 ANGLE BAR 980.00 333,200.00
120 KLS WELDING ROD 65.00 7,800.00
15 GALS EPOXY PRIMER 650.00 9,750.00
485,150.00

ROOFING
900 SQ.M. RIB SPAN COLOR ROOF .50mm 280.00 252,000.00
18 PCS STAINLESS GUTTER 24'' .50mm 900.00 16,200.00
40 PCS WALL FLASHING .50mm 420.00 16,800.00
1 LOT HARDWARE 25,000.00 25,000.00
310,000.00

ELECTRICAL WIRES AND FITTINGS


LUMPSU 1 LOT STRANDED WIRES 620,000.00

ELECTRICAL FIXTURES
88 PCS LED LIGHT 400.00 35,200.00
6 PCS WALL LIGHT 1,750.00 10,500.00
45,700.00

PLUMBING PIPES AND FITTINGS


LUMP SU 1 LOT PPR PIPES AND STANDARD ORANGE PIPES 250,000.00

PLUMBING FIXTURES
13 SETS WATER CLOSET PACKAGE 6,500.00 84,500.00
10 SET LAVATORY 3,000.00 30,000.00
2 SET KITCHEN SINK DOUBLE BOWL 9,000.00 18,000.00
2 SET KITCHEN SINK FAUCET 1,200.00 2,400.00
134,900.00

MECHANICAL
3 SETS 10000 KL UNDER GROUND TANK 185,000.00 555,000.00
4 SETS 6 HOSES FUEL DISPENSER 385,000.00 1,540,000.00
2,095,000.00

EXTERIOR ARHITECTURAL FINISHES & TOILET


1 LOT ACP WALL AND PARAPET CLADDING 350,000.00 350,000.00
240 PCS 60X60RUSTIC TILES (HALLWAY) 165.00 39,600.00
180 PCS 60X60 FLOOR TILES ( TOILET FLOOR) 165.00 29,700.00
630 PCS 60X60 GLAZE WALL TILES ( TOILET WALL) 145.00 91,350.00
120 BAGS ABC HEAVY DUTY TILE ADHESIVE 250.00 30,000.00
40 BAGS ABC GROUTE 120.00 4,800.00
545,450.00

PAINTINGS
LUMPSU 1 LOT BOYSEN OR DAVIES PAINTING MATERIALS 400,000.00

DIRECT MATERIAL COST 7,751,600.00

DIRECT LABOR COST 3,100,640.00

10% CONTIGENCY ALLOWANCE 775,160.00

TOTAL PROJECT COST 11,627,400.00