Annual Insp SPJ 150322
Annual Insp SPJ 150322
SN Action by
1.0 NARKATIAGANJ:
1.5 FOB: Extension of FOB has been completed towards North PCOM
CAO/C/N
direction in Mar’22. Goods wharf and yard layout was seen.
At present, only half rake wharf and corresponding goods
wharf is available in North side of NKE station, which is being
used for Sugar loading. Feasibility of converting it into full
rake length goods wharf to be explored keeping in view its
recurring earning capacity. ESP of NKE yard-remodelling may
be reviewed accordingly in consultation with Construction
Organization.
1.6 Health Unit: PCMD
PCPO
Inspected the health unit. Overall cleanliness was found DRM/SPJ
satisfactory.
Presently the flooring is mosaic. Tiles to be provided for
better cleaning & hygiene.
HMIS was inaugurated. It will facilitate registration,
prescription, medicine issues etc. through digital means.
Furniture needs to be replaced with new one. Old doors to
be replaced and modernized look to be given by using tiles
on walls.
1.7 Colony inspection: PCE
PCMD
General upkeep of colony was found satisfactory. DRM/SPJ
Children Park needs to be improved by providing some
more swings, etc.
Occupant of quarter No.L/163 was asked for any
difficulties. She replied that water logging, roof leakage,
drainage problem and insects etc. are major problem
during rainy season - to be attended on priority.
Abandoned structures need to be dismantled and
disposed off.
Page 2 of 28
1.8 Meeting with Shri Sunil Kumar, Hon’ble MP/Valmikinagar
(LS): Following points were raised by Hon’ble MP during the CAO/C/N
meeting:- PCME
(i) An underpass was requested at Bugaha station to PCOM
PCE
facilitate women, children, divyang and old people at PCCM
the entrance/exit point. DRM/SPJ
(ii) Washing Pit at Narkatiaganj should be restored.
(iii) Narkatiganj-Bhikhnatodi line to be commissioned early.
(iv) Booking counter to be provided at North side of
Narkatiaganj station as there are 17 wards.
(v) RXL-HYB is being stabled 11 hours at RXL - to be
extended to NKE.
(vi) Doubling works to be expedited.
(vii) NKE-ROB at LC No.21 & 22: Divider needs to be
extended and a round traffic control point may be
provided.
(viii) NKE-DBG direct train to be provided. All passenger
trains to be made normal.
1.10 Just outstation of the station limits telephone wire poles were PCSTE
DRM/SPJ
seen. If obsolete, these poles to be removed.
2.0 Bridge No.96: Inspected the bridge. Fasteners were found PCE
intact. Bearing was attended as per schedule. Tools for bridge
measurement/maintenance were displayed. At random,
working of rebound hammer (for checking the strength of
concrete) was checked but the same was not properly
calibrated and instructions on it were not readable being in
Chinese Language. All concerned were advised to use latest
internet-based technology for deciphering the foreign script.
There was no handrail on the ladder, meant to give
accessibility to bearing/piers. Proper design of ladder to be
followed to provide safety to maintenance staff. Also, the old
piers are to be dismantled.
Page 3 of 28
Road surface on LC was found satisfactory. Height of
Boom and Check rails gap were found within limits.
Private number book was not issued under the signature
of Controlling Officer, which should be invariably ensured.
Newly built height gauge by Construction department was
not having standard mark at 4m from the top to have
control over the overall height.
4.0 Bridge No.83: Minor bridge. HFL= 1986. It was painted with PCE
cement slurry, which is totally unacceptable. There is no
provision for painting of bridges by white cement in
Engineering Code or Manual. DNR division also did the same
work. PCE to issue guidelines in this regard.
Page 4 of 28
9.0 Speed restriction was imposed on MBG bridge No.62.
Speed restrictions are imposed on MBG bridges - the
reason of which is not clear. In case, these bridges are not
suitable for higher speed, sanctioned new bridges to be
built quickly.
Rough riding was noticed at Curve No.26. Versine of curve
to be checked and intimated. Immediate corrective action
to be ensured.
Bridge No.59 was having skewed parapet. Reason to be
checked for corrective action.
Loop No.1 of Marjadwa has kink in the X-over portion. To
be attended.
Too many curves were observed during the run, especially
in bridge approach, in spite of there being a feasibility of
easing them out. Due care to be taken in new sections.
At some stretches in NKE-RXL, stone dust was used
without ballast on shoulders. Responsibility to be fixed.
Ballast deficiency was found between RXL-ADX and other
places of RXL-SMI section - to be recouped and made
good.
Line taking off from RXL to SGL does not seem in good
condition - to be inspected by CTE within 15 days.
30 Kmph speed board for loop to be put at right location.
‘For Loop’ to be mentioned on board for clarity and as per
norms.
Degree of curves needs to be re-established considering
large variation from standard versine.
At few station valencing on Platform shelter was not
available - to be ensured for public convenience.
10.1 Accident diagram provided in panel room Bhelva was non- PCOM
PCSO
standard and on a chart paper. It shows sub-standard
working of the sectional TI and SM of the station. They
should be taken up under D&AR.
Page 5 of 28
10.3 Complaint: Two persons from the public complained of low SDGM
PCE
standard work done by the contractor in platform
construction. It needs to be investigated in detail.
12.0 RAXAUL:
13.0 Ghorasahan:
Engineering maintenance tools and charts were displayed
at the station.
TRD maintenance spares and tools were also shown at the
station.
AEE/TRD/BMKI gave an informatics presentation on the
TRD working.
14.0 Bairgania:
PCCM
People demanded for stoppage of all the Mail/Exp trains. PCOM
80% people are residing at South side so connectivity of PCE
ROB was requested at both sides of station. PCSC
15.0 Sitamarhi:
15.3 People also raised the issue for restoration of normal DEMU PCCM
in place DEMU Spl and also asked for restoration of normal
fare for all DEMUs.
15.4 Local people raised the issue for parking of vehicle. It should DRM/SPJ
be properly earmarked for chargeable and for drop purpose.
16.0 Speed trial was conducted from SMI to MFP. The running was PCE
found quite satisfactory. As such planning for raising the
sectional speed from existing 100 Kmph to 110 Kmph to be
done.
Page 9 of 28
4
SUMIT KUMAR, Group 5000
SSE/EnHM/RXL & TEAM
SHANTI RAKSHIT & SSE(C&W)/ DEPOT Group
5 5000
TEAM RXL
6 SANJAY RAUT & TEAM GANG NO.-35/NKE Group 10000
MAHIMA SHUKLA, Group
7 SSE(WORKS)/NKE & 5000
TEAM
8 ACCOUNTS TEAM Group 5000
ASHOK KUMAR K, Group
9 CLI/CCC/RXL AND HIS 20000
TEAM
OFFICERS CLUB & Group
10 50000
CULTURAL TEAM
DIVISIONAL RAILWAY Group
11 50000
HOSPITAL
Sub Total = 1,80,000
Grand Total= ₹2,48,000/-
.
Points noted by PCSO:
1. Station diary: Plain register is being used though printed diary is DRM/SPJ
available in Traffic Stores. This should be looked into.
3. Signal Failure Register : Month wise signal failures were as under:- DRM/SPJ
Month Nos. of Failures Summary
Nov’21 03 Block Instrument -1, Pt. -1, Track
-1
Dec’21 02 Engg (Cons.) -1, O/Stn. - 1
Jan’22 02 Block Instrument -1, Pt. -1
Feb’22 04
SSE /Sig/NKE had given last remarks on 11.03.2022.
5. Joint TRD Register: Last two joint inspections done on 12.08.2021 DRM/SPJ
& 08.01.2022 respectively. Some deficiencies noted in the register
are yet to be complied.
Irregularities Point no.
Insulated bond crossing Missing
Page 10 of 28
below positive rail 1 no. Not isolated - 012/017 T,
012T, 013T, 017T, 016/04T, 06T,
506AT, 503BT, 04T
2 Nos. - 06T
03 nos. - 08T
Deficiencies noted should be complied early.
6. Joint Points & Crossings Register: Last two joint inspections done DRM/SPJ
on 22.09.2021 & 11.12.2021 respectively. It was due since
10.03.2022. Some deficiencies noted in the register are yet to be
complied like :
Irregularities Point no.
Clearance between the rod and Only clear was written instead
foot of the rail of actual measurement for most
of the points.
Housing of the switch 3 SL - 501/B, 508/A, 503/B,
511/B,
3/4 SL - 511/A
3/2 SL - 516/A
-/2 SL - 507
4/3 SL - 505/A
-/3 SL - 506/B, 506/B
Condition of Tongue rail LH - 140 × 3 mm broken from
310 mm toe - 503/A
LH - 1365 × 2 mm knife edge -
504/B
LH 400 × 2 mm knife edge -
510/A
RH -790 × 3 mm broken after
230 mm from toe - 518/A
RH 160 X 4 mm broken after
793 mm from toe - 520/A
Page 11 of 28
9. Private Nos. exchanged by Station Master with LC gate No. 20/C DRM/SPJ
were randomly cross-checked and found correct.
10. Chains and Clamps available and were found hanged but padlocks DRM/SPJ
were without Numbered keys. This should be done.
11. One R/L platform is shown between line nos. 6 & 7 in station DRM/SPJ
diagram which is not there. This should be corrected in SWR and
all diagrams.
13. There is a large vacancy of station staff in safety category. Detail DRM/SPJ
position is as under:
Category BOS MOR Vacancy
SM 19 15 04
Porter 33 21 12
Gateman 06 02 04
Shuntman 04 02 02
Goods Guard 31 16 15
Pass Guard 26 14 12
TNC 04 01 03
Vacancy of safety category staff should be filled up on priority.
14. There is no separate toilet for ladies staff in SM’s EI room. This DRM/SPJ
should be provided as lady staff are working.
15. Staff Gradation Register: Last done on 14.03.2022. 97 staff had DRM/SPJ
been graded ‘A’ and remaining 16 staff were graded ‘B’. Regular
counseling should be done to improve their knowledge.
16. Caution Order Register : Detail Section wise caution order position DRM/SPJ
was as under:
SN Section No. of Cautions
1 NKE - RXL via GKA 14
2 NKE - RXL via SGL 17
3 NKE - GKP 15
4 NKE - MFP 26
Caution Order is generated through ICMS for only 02 sections i.e.
SN 1 & 2, but for remaining 02 sections i.e. SN 3 & 4 being done
manually as cautions are not getting updated timely by SEE and
BSB divisions. Needful should be done in co-ordination with
adjacent divisions.
17. Quality of paper and printing of Caution Orders through ICMS was DRM/SPJ
not proper. It should be printed on A-4 size paper. Staff available
reported regarding non supply of A-4 size papers from divisional
Traffic store.
18. On-duty SM reported that track circuit no. 021 T, surrounding DRM/SPJ
area of bridge no. 303 remain intermittent failed. This should be
looked into and rectified.
Page 12 of 28
19. As per SWR, 04 SMs i.e. Outdoor SM, Indoor SM, EI in-charge SM DRM/SPJ
and Panel Operator have to perform 8 hrs duties in each shift. But
presently, only 03 SMs perform duty in each shift, to be looked
into.
20. There is no point Indicator for point no. 515/B connected with DRM/SPJ
running Line no. 6 and non-running Line no. 7. This should be
planned.
21. Mobile No. of Dr. Jahur Ekram mentioned in DMP board was DRM/SPJ
randomly checked and found not responded. Contact No. should be
updated time to time for quick communication during emergency.
22. In Crew Lobby, digital PSR & TSR display was seen. Some cautions DRM/SPJ
like 80 KMPH SR in SRA-BMKI was not reflected. It was also very
inconvenient to read the SRs in colour codes.
SRs should be displayed in numerical and not in colour codes for
easy understanding by Crew and Guards.
23. Chief Crew Controller was not aware of pre-departure detention DRM/SPJ
(PDD) of goods trains which is an important parameter to monitor
utilization of Crew and mobility of freight operation. This should be
maintained for all directions separately and monitored by field
supervisors/officers and officers in divisions.
24. Compliance on COR items are delayed in many cases and proper DRM/SPJ
remarks are not getting timely written /recorded in the CMS
system. Immediate action on safety items and proper remarks
should be ensured.
2. Bio-data of Gatemen was checked and found not due for PME & DRM/SPJ
Refresher course.
3. Both Hindi & English version GWR were available but without DRM/SPJ
issuing and enforcement date.
4. Danger Board on height gauge was fixed by wire. It should be fixed DRM/SPJ
properly.
6. TVU - 1380 of January, 2018 was written in GWR. Latest TVU DRM/SPJ
1586/June, 2021 was written at gate lodge. GWR to be corrected
Page 13 of 28
as per latest TVU.
2. In the Private No. Sheet Register formatting found not done. DRM/SPJ
Column to whom Private No. sheet supplied was not available.
5. Joint Points & Crossings Register: Last two joint inspections done DRM/SPJ
on 20.09.2021 & 20.12.2021 respectively. Some deficiencies noted
in the register are yet to be complied like :
Irregularities Point no.
Gauge at the toe - 4 mm - 52/B
6. POINT NO. 55 in BLV yard : Housing was 4 only sleepers in LHS DRM/SPJ
and 3 sleepers in RHS of point no. 55/B but the same was merely 1
sleeper in LHS & 2 sleepers in RHS of point no. 55/A.
10. Fire Alarm and Detection System was not available in SM’s EI DRM/SPJ
room.
Page 14 of 28
11. Rules regarding emergency operation of Panel should be displayed DRM/SPJ
for reference of SMs.
2. Gateman was not the regular staff of Bhelwa station. He was DRM/SPJ
posted at CAO. There is shortage of staff. Vacancy should be filled
up.
3. Private no. sheet being used was without signature & seal of DRM/SPJ
issuing official.
2. Safety Alert No. 2 and Red Bulletin issue- February, 2022 were not DRM/SPJ
available.
4. Track circuit of running line nos. 6, 7 & 8 were showing red since PCSTE
commissioning of EI on 12.08.2018. Trains are received on Calling DRM/SPJ
‘ON’ Signal. This is not correct from safety perspective. This failure
should be rectified at the earliest.
5. Shunt Signal no. 210 on line no. 9 towards SMI end and Shunt PCSTE
Signal no. 118 on line no. 118 towards SMI end are failed since DRM/SPJ
long.
6. Time Variation Register: Opened and maintained from recent past DRM/SPJ
by the name of 16 hrs. Register. This should be maintained as
“Time Variation Register”. SM on duty should put his signature in
the register for time noted/matched with Control at 16 hrs every
day.
7. Safety Slogan found not written in the TSR. Available staff were DRM/SPJ
Page 15 of 28
counseled for writing safety slogan to inculcate safety awareness
amongst staff.
8. Mobile No. of Deep Nursing Home mentioned in DMP board was DRM/SPJ
randomly checked and found not in use. Contact no. should be
updated time to time for quick communication during emergency.
10. Joint Points & Crossings Register: Last two joint inspections done DRM/SPJ
on 18/19.09.2021 & 18/19.12.2021 respectively. Some deficiencies
noted in the register are yet to be complied like :
Irregularities Point no.
Gauge at the toe - 5 mm - 73/B, 76/A
+ 16 mm - 77,
+ 11 mm - 79
Condition of packing required 74/A
Housing of the switch 3/3 SL - 73/B, 74/B, 75, 76/B,
80, 82/B.
Clearance between leading 5/2 mm - 76/B.
stretcher bar & rail bottom
Deficiencies noted should be complied on regular basis.
11. Length of stabling line was increased but in SWR was not DRM/SPJ
corrected. This should be done.
12. Magneto telephone of LC Gate no. 15 & 16, situated between RXL - DRM/SPJ
RGH stations was found out of order from 09.30 of 15.03.2022.
13. Staff Gradation Register: Last done on 03.01.2022. 33 staff had DRM/SPJ
been graded ‘A’ and remaining 27 staff graded ‘B’. Regular
counseling is required to improve their knowledge.
14. Joint Track Circuit Register: Last joint inspection done on DRM/SPJ
18.12.2021. Some deficiencies noted in the register are yet to be
complied like:
16. SM/RXL pointed out that Veedor counter of Crank Handle does not DRM/SPJ
increase whenever used. This should be rectified.
Page 16 of 28
17. There are 03 vacancies of Shunting Master and 16 vacancies of DRM/SPJ
Group 'D' Staff. Vacancy of safety category staff should be filled up
on priority.
2. Joint Track Circuit Register: Last two joint inspection done on DRM/SPJ
20.09.2021 & 07.03.2022 respectively. Some deficiencies noted in
the register are yet to be complied.
Irregularities Point no.
Weather sufficient GFN Liners 95% - 02T, 4T, 8T, 04T, 06T,
Rubber Pad provided or 08T, 03/04T, 07/06T, 03T, 05T,
not (not less than 97%) 07T, 5T, 011T, 11T, 0C-12T
93% - 6T.
Deficiencies noted should be complied on regular basis.
3. Joint Points & Crossings Register: Last two joint inspections done DRM/SPJ
on 23.12.2021 & 07.03.2022 respectively. Some deficiencies noted
in the register are yet to be complied.
Irregularities Point no.
Housing of the switch 3/3 SL - 51/A, 52/A,
52/B
3/4 SL - 56/B, 55/A
4/3 SL - 56/A
Clearance between leading 5/4:mm - 51/A
stretcher bar & rail bottom 2/5 mm - 52/A.
Deficiencies recorded should be complied on regular basis.
1. Signal Failure Register : Month wise signal failure was as under: DRM/SPJ
Month Nos. of Failures Summary
Oct.’21 07 Signal – 3,TLBI-3,BPAC-1
Nov.’21 07 Signal – 2,TLBI-5
Dec.’21 06 Signal – 2,TLBI-4
Jan.’22 02 Track – 1,TLBI-1
Feb.’22 02 Summary not prepared.
March’22 04 (till date) -
TLBI failures are quite high after electrification of this section
recently. It should be checked and corrective action should be
taken.
Page 17 of 28
2. Relay Room register: Month wise position of opening of Relay Room DRM/SPJ
was as under:
Nov.’21 – 12, Dec.’21 -10, Jan.’22-04 and Feb.’22- 02.
Opening has been quite high in the months of Nov.’21 and Dec.’21
against the prescribed norms.
3. Station diary: Plain register is being used though printed diary is DRM/SPJ
available in Traffic Stores. This should be looked into.
5. There is no attached toilet causing hardship to ‘ON’ duty staff for DRM/SPJ
natural calls. This should be provided.
6. Joint Points & Crossings Register: Last two joint inspections done DRM/SPJ
on 10.12.2021 & 05.03.2022 respectively. Some deficiencies noted
in the register are yet to be complied.
Irregularities Point no.
Housing of the switch 3/3 SL - 51/A, 51/B, 52/A,
54/A, 57/B, 58/A, 60/A,
62/A, 62/B
4/3 SL - 52/B, 53/A, 59/B,
61/B
3/4 SL - 53/B, 55/B
-/3 SL - 56 X.
Housing of switch has been found at many locations. Corrective
action required.
Page 18 of 28
Points noted by PCME:
Twin Dustbins with the third dustbin for Bio hazardous waste were DRM/SPJ
1. available.
ARMV/NKE
10. Medical staff should practice on the various adjustment of the OT DRM/SPJ
table, as staff present during inspection was not aware about the
adjustment of OT table.
Page 19 of 28
2. Root analysis of Rail madad complaints required. It must be train DRM/SPJ
wise & type of complaint wise. Corrective action taken must be
shown for every complaint. Report summary required for
complaints.
01 Earth resistance of FOB earth pit was found to be 8.32 ohm. DRM/SPJ
Combined value was found to be 1.19 ohm. Both values are under
limit.
03 There is an ATD mast near line no. 1 (away from PF side) at loc. DRM/SPJ
NKE/246/11 with implantation 3.80 m. Passenger may sit under
counter weight. So, a fabricated cage should be provided to avoid
any unforeseen event due to falling of counter weight.
04 All types of caution boards and notices were provided on FOB. DRM/SPJ
05 SWRD and appendix-G were found as per latest physical condition DRM/SPJ
of site.
07 The engineering works of TRD Depot, Staff quarters, tower wagon CPD/DNR
shed (along with pit facilities) and linking to track is very slow.
Depot working is being hampered at NKE KVC & RXL due to
unavailability of quarters TRD Depot & TRD shed need to be
expedited, at the earliest.
08 Required spare OHE materials and Tools and Plant need to be CAO/C/N
provided to KVC,SGL , RXL and NKE depot in view of electrification
work of NKE-RXL section and doubling of MFP-VKNR section.
09 Number plates are not provided on OHE masts. Bridge earthing is CAO/C/N
not done as yet. Bridge mast needs to be provided in view of bigger
span length.
Continuity bonds as well as shunt bond and at bridge ends needs
to be provided. Earth pit at both ends connecting to girders to be
made.
Page 20 of 28
11 25000V danger board is fixed with loose winding wires. It should CAO/C/N
be fixed properly by getting hole drilled in boom of height gauge DRM/SPJ
and fixing with rail & volt. Public Caution Board is also to be
provided height gauge boom.
12 Earthing of boom (lifting barrier) should be done with rail and/ or CAO/C/N
by using additional earth pits. Fencing needs to be connected with DRM/SPJ
rails.
13 GWR should include TRD aspect also. TRD safety Do’s and Don’ts DRM/SPJ
should be mentioned in that.
14 Contact wire height was found to be 5.83 m above rail level. Height DRM/SPJ
of height gauge was found 4.78 m from road level.
21 25000V danger board is fixed with loose winding wires. It should CAO/C/N
be fixed properly by getting hole drilled in boom of height gauge DRM/SPJ
and fixing with rail & volt.
22 Earthing of boom (lifting barrier) should be done with rail and/ or CAO/C/N
by using additional earth pits. Fencing needs to be connected with DRM/SPJ
rails.
23 GWR should include TRD aspect also. TRD safety Do’s and Don’ts CAO/C/N
should be mentioned in that. DRM/SPJ
Page 21 of 28
24 Electric shock treatment chart needs to be provided. DRM/SPJ
25 Implantation of legs of FOB between line no. 2 and 3 at RXL in loc. DRM/SPJ
187/20A-187/22 is 2.17m and 2.18 m respectively w.r.t. line no.2
track as from SMI to NKE direction. Arrangements should be done
to improve implantation to avoid any unwarranted situation due to
less implantation.
Bairganiya Station:BGU
29 Chief crew controller Sri Umesh Kumar, CC- Sri Tuntun Kumar, DRM/SPJ
CMS Operator- Sri Rohit kumar(Outsourced) were present in the
crew lobby at the time of inspection.
31 COR Register checked and found that one abnormality was DRM/SPJ
reported by LP on 14.03.2022 regarding all Right Signal not
exchanged from opposite side of the Kumarbag station, on which
no action was taken by the concerned department. COR should be
monitored and prompt action should be taken immediately.
35 Clean and hygienic linen should be provided to the crew. Washing DRM/SPJ
quality to be improved.
37 Right hand signal location flex was available, Safety related more DRM/SPJ
posters and flex to be provided in Running room.
NKE:
1 Block Instrument: Diado has been installed towards SAHI and DRM/SPJ
CAMU on 15.03.2019 & 26.03.2019 and Push Button tokenless
block instrument has been installed towards GKA on 25.08.2018.
All the Block Instruments are working properly on single media
(Quad) only.
Note: Towards SAHI & CAMU, the DIADO Block Instruments
should be replaced by Double Line UFSBI with Media Diversity
Facility at the earliest.
Page 23 of 28
working properly. During random check of voltage on CTR for 1HR
and C3TPR, voltage was found as 52.90 Volt and 25.91 Volt
respectively. ELD should be integrated with Datalogger and health
of cable shall be monitored.
7 As per Points & Crossing Register, the last date of inspection is CAO/C/N
09/11.12.2021. Deficiencies noted has been complied timely except DRM/SPJ
for point no.54’B’. Effort shall be made to comply deficiencies on
the same day.
8 Failure: DRM/SPJ
Dec’21: 02(Engg. Con-01 & Miscr-01).
Jan’22: 02 (Engg. Con-01 & Miscr-01).
Feb’22: 04 (S&T-01, Engg. Con-01&Incidental.-02).
BLV:
1 Push Button tokenless block instrument has been installed in both DRM/SPJ
ends on 12.08.2018 and it is running smoothly.
6 As per Points & Crossing Register the last date of inspection is DRM/SPJ
20.12.2021. Deficiencies has been complied but housing of the
points is not satisfactory.
7 Failure: DRM/SPJ
Dec’21: 00.
Jan’22 : 00
Feb’22: 02.
Page 25 of 28
Raxaul (RXL):
8 As per Points & Crossing Register, the last date of inspection is CAO/C/N
18/19.12.2021. Deficiencies shortlisted have been complied DRM/SPJ
timely. Housing of the points should be 4 to 6 sleepers.
10 CCTV has been provided in relay room. This practice should be All DRMs
adopted for all relay room of every station.
11 Fire alarm system is not available in relay room at this station. It DRM/SPJ
should be installed immediately. Fire ball must be provided at
least 06 no. in place of 02 nos.
Page 26 of 28
BGU:
3 IPS: DRM/SPJ
Amaraja make, Integrated Power Supply System installed on
27.12.2012 at this Station is working smoothly.
Last gravity of secondary cell has been checked on 13.03.2022 and
found that Specific Gravity of Secondary Cell is not less than 1220.
SMI:
1220
DRM/SPJ
4 Data Logger Details:
Efftronics make Data Logger installed in the year 2010 of 1024/32
and
capacity at this Station is working properly. Networking
validation has been completed at this station.
DRM/SPJ
5 As per Points & Crossing Register the last date of inspection is
06.03.2022.
05.03.2022. Deficiencies has been complied on
be at least 4 to 6 sleeper.
Remarks: Housing of all points should
DRM/SPJ
6 Veeder Counter:
COGGN:001526
RRBUN: 000385
EUYN: 005651
EWN: 000822
EOVN:001355
CH 001299
DRM/SPJ
Failure Details:
Dec 2021 03 (S&%T-02, Optg.-01)
Jan 2022 03 (S&T-02, Engg.-01)
Feb 22 till date : 02 (S&T-01, Miscrants-01)
A (Aman Raj)
To6o12
Secretary to GM