Professional Documents
Culture Documents
3 Steamship Mutual Underwriting Association Bermuda Limited V Sulpicio Lines Inc GR Nos 196072 Amp 208603 September 20 2017
3 Steamship Mutual Underwriting Association Bermuda Limited V Sulpicio Lines Inc GR Nos 196072 Amp 208603 September 20 2017
The Contract provides that: (1) the target Transfield filed a complaint for
completion date of the Project shall be on 1 Injunction(with prayer for TRO and writ of
June 2000, or such later date as may be preliminary injunction) against LHC in the
agreed upon by the parties or otherwise RTC Makati. It sought to restrain LHC from
determined in accordance with the Turnkey calling on the Securities and respondent
Contract; and (2) petitioner is entitled to banks from transferring, paying on, or in
claim extensions of time (EOT) for reasons any manner disposing of the Securities.
enumerated in the Turnkey Contract, among RTC issued a (72)-hour TRO, which was
which are variations, force majeure, and extended for another (17) days
delays caused by LHC itself.(3) Further, in
case of dispute, the parties are bound to RTC denied petitioner's application for a writ
settle their differences through mediation, of preliminary injunction. It ruled that
conciliation and such other means petitioner had no legal right and suffered no
enumerated under Clause 20.3 of the irreparable injury to justify the issuance of
Turnkey Contract. the writ.
Employing the principle of "independent
To secure performance of petitioner's contract" in letters of credit, the trial court
obligation, Transfield opened in favor of LHC ruled that LHC should be allowed to draw on
two (2) standby letters of credit the Securities for liquidated damages
The trial court further ruled that the banks
Transfield sought various EOT to complete were mere custodians of the funds and as
the Project. However, LHC denied these such they were obligated to transfer the
requests - this gave rise to a series of legal same to the beneficiary for as long as the
actions: latter could submit the required
1st of the actions was a Request for certification of its claims.
Arbitration (which LHC filed before the
CIAC-Construction Industry Arbitration CA (petitioner,Petition for Certiorari under
Commission) followed by another Request Rule 65)
for Arbitration filed by Transfield in ICC Contention: LHC's call on the Securities was
(International Chamber of Commerce) premature considering that the issue of its
default had not yet been resolved with
In both arbitration proceedings, the finality by the CIAC and/or the ICC.
-CA issued a TRO, BUT upon expiration of
the TRO , representatives of LHC went to
ANZ Bank and withdrew the total amount of
US$4,950,000.00, reducing the balance in
ANZ Bank to US$1,852,814.00.
-CA dismissed the petition of certiorari and
expressed conformity with the trial court's
decision
SC
Petitioner contends that the courts below
improperly relied on the "independence
principle" on letters of credit when this case
falls squarely within the "fraud exception
rule." (Transfield contents: LHC knowingly
misrepresented that petitioner had incurred
delays— notwithstanding its knowledge and
admission that delays were excused under
the Turnkey Contract.
Issue:
Ruling: