Plastic Gasification - Project Schedule - 20210512 Updated On 27.05.21
Plastic Gasification - Project Schedule - 20210512 Updated On 27.05.21
GPE Korea
Sr. No. Details Scope Scope
Engineering
A General Activities / Work
Drawings list of GPE engineering ○
P and I diagram ○
QC documentation ○
B Client Engineering ○
Layout of Plant ○
C Electrical Engineering
D Instrument Engineering
P & ID ○
F Bought-out items
Technical specification sheet for Bought-out items like; ○
a. Fuel Handling bucket elevator ○
b. All Blowers ○
c. All pumps ○
d. Electric Chiller ○
e. Mechanical Valves ○
f. Water softener ○
g. Air cooler ○
h. Gas analyser ○
i. Compressor + Air receiver + Instrument Air Dryer ○
G Structural Engineering
Structural Wire diagram ○
Structural layout and equipment placement ○
Structural analysis using STAAD software as per applicable code ○
Joint / connection detailing and calculation ○
Drawing and BOM generation ○
Analysis calculation set generation ○
Foundation load data generation ○
GA and manufacturing drawing ○
H Civil Engineering
Civil design and drawing for Gasification system ○
Civil design and drawing for Fuel handling system ○
Civil design and drawing for Auxiliary equipment's ○
Civil design and drawing for MCC. Control room ○
I Insulation Engineering
Insulation thickness calculation sheet ○
Material take off quantity ○
Typical drawings ○
J Refractory Engineering
Refractory engineering ○
Anchor design and drawings from supplier / vendor ○
Drawings from supplier / vendor ○
K Fuel Handling System Engineering
Fuel handling layout and placement of equipment's as per site and client requirements ○
Plan GA and layout ○
Conveyor and elevator calculations including power, flow ○
Hopper and conveyor calculations ○
GA and manufacturing drawings ○
Manuals ○
L Piping Engineering
Piping routing in plan and elevation ○
Pipe stress analysis as required with CAESAR II ○
Pipe layout ○
Pipe Isometric ○
Pipe line line and BOM ○
Pipe support drawings and BOM ○
5.0 Refractory ○
6.0 Gasifier ○
8.0 Cyclone ○
12.0 Paintings ○
Pipes inlcuding Stainless Steel, Carbon Steel, Galvanised Iron with necessary fittings,
40.0 ○
expansion joints
45.0 Structure ○
Railing ○
Grating ○
Stair case ○
Roof ○
Hardware ○
Chain and Pulley block ○
46.0 Insulation ○
Insulation ○
Cladding ○
Any type of Civil work and associated work inclduing foundation bolts or anchor
50.0 bolts ○
Fire fighting at site, plant illumination at site, Lighting protection & earthing /
51.0 ○
grounding
53.0 Statutory approvals (of any kind) along with safety approvals ○
54.0 Waste disposal (if any) ○