Schedule
50
5,000,000 Volume Urugan
208,333 Volume per bulan Solusi :
6,944 Volume per hari Semua Armada harus masuk terutama Index 22
868 Ritase/Hari (Index 8) Jalan menuju Quarry harus masuk angkutan kelas 2
289 Jumlah Truck / hari Jalan menuju lokasi proyek harus membuat jalur proyek (Kelas 2)
72 Armada Truck/Quarry 1
72 Armada Truck/Quarry 2
72 Armada Truck/Quarry 3
72 Armada Truck/Quarry 4
58 Excavator Galian
14 Excavator Louding
9 Bulk Dozer
4 Vibrator Roller
4 Mobil Tangki
PROJECT MANAGER
Ir. SARONI HAMID, MT. MM.
Purchasing Purchasing
Site Manager Quarry 1 Site Manager Quarry 2 Site Manager Quarry 3 Site Manager Quarry 4 Site Manager Zone 1 Site Manager Zone 2 Site Manager Zone 3 Site Manager Zone 4
Kepala Labour Kepala Labour Kepala Labour Kepala Labour Kepala Labour Kepala Labour Kepala Labour Kepala Labour