Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

How to Use What-If A

and Operations Plan


By Sujit K. Singh and Jane B. Lee

E x ecutive S ummary | In uncertain markets, what-if analysis is a must for demand and supply planning. The
authors show how to use it by discussing a number of case studies, and the way to determine their impact. To make
the most of this analysis, one has to go beyond standard technologies and use the one that is specific to this type of
analysis.

S ujit K . S ingh | Mr. Singh is the Chief Operating Officer of Arkieva that specializes in a software system
for forecasting, S&OP solutions, production planning, inventory management, and what-if analysis. He has done
work for a number of large companies in different industries. He is certified CFPIM and CSCP by APICS.

J ane B . L ee | Ms. Lee is the Executive Director at Arkieva. She has wide experience in forecasting, planning,
and S&OP implementation. Prior to that, she worked for 20 years at DuPont where she created and led the global
S&OP process for the polymer division. In a consulting capacity, she has worked for numerous companies in
paper, mining, chemical, glass, film, food processing, optical fiber, and semiconductor industries.

S upply chain planning is no longer just a once-a-month exercise. In this demand-driven market, it is
critical for both Demand and Supply Planners to stay on their toes at all times, and monitor not only
“actual” versus plan, but also market changes that may require immediate action. This article discusses issues
involved in what-if planning, and how to use it.

4 Copyright © 2013 Journal of Business Forecasting | All Rights Reserved | Fall 2013
f Analysis in Sales
anning

what-if scenarios uncertainty will prevail. It is, therefore,


important to embrace uncertainty
the future. As such, planners build a
plan based on a range around a final
Whether short or long term, all and incorporate it into a plan. A good number. As long as the final number
plans deal with the future, and thus planner (or a planning team) realizes stays within that range, it is a good
have a great deal of uncertainty around that every plan is based on certain plan. If it is outside the range, it will
them. Even if sophisticated techniques assumptions. Plans are more likely require re-planning. At this point, it is
are employed to develop a plan, to be wrong than right in predicting important to identify issues that will

Copyright © 2013 Journal of Business Forecasting | All Rights Reserved | Fall 2013 5
make the plan invalid, and develop a impact both the demand and the supply 5. Is the change so big that it
new one for both demand and supply. side of the equation. For example, if could modify the underlying
What-Ifs During Normal Business a hurricane hits the eastern seaboard assumptions? For example, after
Environment: Most plans assume of the United States, some supply is the 2011 earthquake and tsunami
stable conditions; meaning business interrupted, and so is demand. This is in Japan, companies that had a
conditions of tomorrow will remain different from the scenarios described single source of supply for some of
similar to what we are experiencing earlier because they only deal with their items from that area had to
today. No game-changing event will either demand or supply. It is critical re-think how they would meet the
occur. This is a reasonable assumption, for the planner to understand all the demand in the future.
but often, underlying parameters potential impacts of scenarios such as 6. How can we make the corresponding
change. For example, a big government raw material availability, operational data change in the system? Which
contract could go to a customer on the status, and/or customer impact. tables need to be edited and how
East Coast instead of to one on the can we do it effectively? How can we
West Coast, thereby causing a change SKILL SET make changes so that the master data
in the supply plan. Or, a machine are not affected? For example, when
may breakdown, requiring a long The ability to deal with these planners hear of a change in future
shut down for maintenance. Good scenarios depends not only on the demand and “want” to run a what-if
planners prepare themselves for these skill set of an individual, but also on analysis on it, they need to make an
possible scenarios by running what-if the tools at their command. A good appropriate change in the data in
calculations. planner develops first a list of likely the planning system so that future
Challenges to the Status Quo: what-ifs based on the experience, as requirements can be calculated
The changing market dynamics may well as input received from colleagues based on the changed demand. In
challenge the status quo. A firm might and experts in the area, and then this case, they will need to know the
have always made a product at a certain evaluates them on the basis of the table that stores the demand data
facility. Another facility could be used following criteria: in the database/software, perhaps
but requires certification from the 1. Is this change significant or just a blip make a copy of it, and then change
customer or some changes in the design on the radar screen? If significant, the appropriate rows.
of a part. Just because a given facility has what-if planning may be needed. 7. How can we evaluate the differences
never made this particular product does 2. Would this change impact at and tradeoffs across scenarios once
not mean that it cannot or should not the same level, or manifest itself calculations for the what-ifs have
do it. A good planner evaluates different at couple of levels down the been made?
what-ifs to arrive at the best plan. hierarchy? For example, a given 8. How can we compute and compare
Black Swan Events: A fundamentally change may impact the availability their effect on the bottom line to
different type of scenario planning of raw material as well as the determine the best one?
has the potential of being a game network capacity. 9. How can we establish trigger points
changer. This type of scenario planning 3. Would this change affect the whole when the official plan has to be
evaluates conditions that cannot be supply chain, or only the local area? replaced by another plan?
described as business as usual. The 4. What kind of data/information is 10. How can we bring scenarios and
causes for such a change could be needed to project its impact? A few their impact in a meaningful
environmental, natural, regulatory, or examples are: way into an S&OP meeting or to
geopolitical. While most good planners a.  A customer is going out of management for their review?
run scenarios of the type described business, leading to a decrease 11. How can we translate the results
above, a great planner would also in demand. into action? For example, if a
consider doing what-ifs on such black b.  A competitor is going out of scenario were on future capacity
swan events. Business decision makers business, leading to an increase reduction (say because of an
rely heavily on this type of analysis for in demand. anticipated labor strike), then the
their strategic decisions. c. A labor strike leads to a reduction corresponding action would be to
This big-picture type of scenario can in available capacity. start the inventory buildup at some

6 Copyright © 2013 Journal of Business Forecasting | All Rights Reserved | Fall 2013
point. A planner who has done this model to react to a changing event. usually performs these functions well.
particular what-if in advance will be 4. Can store multiple scenarios along
ready to do the inventory buildup if with underlying assumptions. IT USUALLY STARTS
and when the anticipated capacity
reduction is confirmed.
5. Has the ability to compare and
evaluate different scenarios in a
WITH DEMAND
The person who has the requisite meaningful way. What-if scenarios are needed when
knowledge as well as the tools to 6. Can monetize the impact of changes have to be made in demand
work with will do well with the what-if different scenarios. planning. Every planner knows that a
analysis. Figure 1 shows the steps to be 7. Can report the results in a meaning­­ful forecast is not just a number, but also a
followed for this type of analysis. way to management. Management range around it. Implicitly or explicitly,
often needs a graphical view for a planner can establish some degree of
Enabling software quick understanding of different variations around the forecast that can
scenarios and their impact. be considered normal “noise.” (This is,
To evaluate different scenarios 8. The ability to replace the official after all, one of the reasons for keeping
requires enabling software. The scenario with a particular what- safety stock.) Starting with demand,
software should have the following if scenario. This could happen however, does not mean ending there.
capabilities: when a particular what-if scenario Often demand-related questions
1. The ability and the features needed evaluated becomes a reality. For eventually lead to supply-related
to create a model of the business so example, a particular high-demand questions. Let’s examine the impact of
that appropriate calculations can scenario becomes reality when several instances of changes in demand
be carried out. orders come in. In that case, it may on the plan using what-if scenarios
2. The ability to conduct the analysis be desirable to replace the official in cases 1-3. Case 4 and 5 deal with
without disturbing the master data; scenario with it. changes in supply. Case 6 deals with
sometimes referred to as a sandbox Spreadsheet-based tools often fall a natural event and highlights how a
environment. short of these capabilities. A supply planner can add value by preparing the
3. Has a configurable model structure chain planning tool, based in DBMS business for a possible future event by
that allows quick changes in the (Database Management Systems), conducting timely what-if analysis.

Figure 1 | Scenario Decision Process

Copyright © 2013 Journal of Business Forecasting | All Rights Reserved | Fall 2013 9
Table 1 | When Forecast Significantly Exceeds the Actual (Report of a Certain SKU/Location through 1-15-2013)
Total Total Customer Total Orders Total Orders
Original Customer’s Actual as Total SKU/ Forecast as % of MTD + OPEN MTD + OPEN Percent
Customer’s Orders % Over the Location SKU/Location for SKU/ as a % of of Month
Customer SKU Forecast MTD + OPEN Forecast Forecast Forecast Location Forecast Completed
Ajax Co., Product
45 60 33.3% 645 7.0% 340 53% 48%
Fort Fox, Missouri 1
Hartman’s, Product
345 380 10.1% 414 83.3% 410 99% 48%
Clinton, Ohio 2

original forecast for the month and not the demand planner will know, for
CASE NO. 1 the netted version. Finally, such a report example, that “shipments plus open
EXCESS OF DEMAND should clearly indicate how far into the orders” generally are, by mid-month,

OVER SUPPLY month we are as a percentage (Percent


of Month Completed). In the example
ahead of the “Percent of Month
Completed” for this business. Provided
Demand for a given SKU/location/ below, this comes to 48% (=15/31). The that the inventory position for Product
customer is higher than expected. report would look something like Table 1. 1 at Fort Fox is okay, the demand
Hitting the forecast at a SKU/location/ Table 1 shows that even though planner would treat this variation as
customer level month by month is the Ajax’s actual is 33.3% above its “noise” within the expected range, and
practically impossible, so the planner forecast, its forecast represents only 7% thus no action is necessary.
may decide that anything more than, of the total forecast of the SKU at Fort Hartman, on the other hand,
say, 10% above the forecast at a SKU/ Fox, Missouri. Currently, based on the provides over 83.3% of the demand
location/customer level should be last two columns, orders are running for Product 2 at Clinton, Ohio. Demand
considered an exception. But a 10% a bit ahead of “Percent of Month for this SKU halfway through the
increase in demand of a customer who Completed.” In many businesses, this month is already 99% of the forecast.
takes only 1% of the monthly demand might be perfectly fine as orders are This situation requires investigation to
for a SKU/location is not as significant usually placed with some lead time, determine whether or not re-planning
as a similar increase for one who takes say by about five days. In such a case, is needed. To investigate this further,
more than half of the demand. For
this reason, the percentage of the Table 2 | Detailed Report of Forecasts and Actuals
total SKU/location volume should
Previous Open Open
be taken into account. Let’s look at a Product 2 4 Month Current Orders: Orders:
Clinton, Ohio Month –2 Month –1 Average Month Month +1 Month +2
sample report that provides enough
Total Forecast 410 392 399 414 396 420
information to make a decision.
Total Actual 414 388 398 410 250 20
Suppose we flag every SKU/ Actual Minus Forecast 4 -4 -1 -4 -146 -400
location/customer order that is 110% Hartman’s
or more of its forecast. A report Forecast 345 345 345 345 345 345
should give the following information: Actual/Month to date/Open 350 340 343 380 250
Remaining -5 5 -2 -35 95
customer’s forecast for a SKU/
Customer 2
Location, actual as a percent over the Forecast 35 35 35 35 35 35
forecast as of today, total forecast for a Actual/Month to date/Open 35 35 35
SKU/location, customer’s forecast as a Remaining 0 0 0 35 35 35
percentage of total forecast for a SKU/ Customer 3
location, and total shipped orders in Forecast 10 12 9 14 16 20
Actual/Month to date/Open 9 13 10 10
current month as of today (also known
Remaining 1 -1 -1 4 16 20
as current month to date or MTD) as a Customer 4
percentage of total forecast for a SKU/ Forecast 20 0 10 20 0 20
location as well as any open orders (or Actual/Month to date/Open 20 0 10 20 20
OPEN). A forecast is included as the Remaining 0 0 0 0 0 0

10 Copyright © 2013 Journal of Business Forecasting | All Rights Reserved | Fall 2013
the Demand Planner should be able to from another location, or to buy should then be passed on to the
call up a report like Table 2 at any time. more from an outside vendor. These Supply Planner for supply planning
The columns in this report represent alternatives need to be evaluated. runs. Here the Demand Planner must
two months before the current month, Even if there is adequate inventory be careful not to assume that a one-for-
one month before the current month, to cover the additional 35 units this one replacement is a given. It is quite
the average demand for the last four month, more investigation is required. possible that the new product may
months prior to the current month, The Demand Planner may ask the sales run at a very different rate (perhaps
the current month, next month, and rep to call Hartman to find out if this takes more or less time to produce)
the month after that. is a permanent increase in demand or or require some special equipment
For the current month, the rows merely a onetime advance in timing of or raw materials not needed by the
labeled Actual/Month to Date/Open an order, which normally would have product it will replace. If overall
include both month to date shipments come in the next month. The answer capacity is fairly tight, an accelerated
and open orders (all demand for the will influence both forecasts and safety new product sales rate is more likely to
current month); for the future months, stock calculations. require what-if planning than a slight
this row represents open orders (as If it is a permanent increase in increase in sale of an existing product.
there is no month to date shipments demand, then a supply-side what-if
in future months at this time). Note analysis may be necessary to determine
that Forecast in all cases is the total— the best way to meet this increase in CASE NO. 3
not net—forecast for the month.
“Remaining” rows are Forecast minus
demand. Do we have capacity to make
the additional quantity? Do we have
TAKING MORE NEW
Actual; a negative “remaining” amount to move production to a different BUSINESS FOR A
means demand has exceeded forecast,
while a positive remaining amount
location? If we are tight on capacity,
do we have an option of increasing
CERTAIN PRODUCT
means the amount of orders are production of either this or another Very often a question is brought
still expected for current and future product competing for the capacity? to the attention of a Demand Planner
months. What is the most cost-effective way of by a product line manager or sales
As can be seen, a wealth of handling this? A properly conducted manager, which is this: what to do
information has been conveyed by what-if analysis will provide the with spare capacity? In that case,
this report. For example, Customer answer. taking on new business for a given
4 is expected to place an order of 20 product would not present any
units every other month. Customer2, problem. Before answering this
Case no. 2 question however, a Demand Planner
on the other hand, places an order of
35 units every month, but it has not A new product must consider all the ramifications. It
yet placed an order for the current and
the following months. The increase
IS selling much may be possible the product being
considered for production expansion
in Hartman’s order by 35 units in the faster than may be produced at a specific plant
current month means that Hartman
may wind up using the inventory
expected that is already at or near capacity. For
the sake of discussion, let’s assume that
intended to meet Customer 2’s Forecasts for new product the business as a whole is operating at
forecast. This may require the Demand introductions are educated guesses at or near capacity. This raises a series of
Planner to consult with the Supply best. When orders exceed the forecast questions:
Planner. Depending on what sort of significantly, the demand planner 1. If we take more new business of
production cycle the product is in must evaluate different assumptions Product Y, which products do we
and how much safety stock is kept, about continued growth rates. At the need to cut back?
it may be necessary to increase this same time, the demand planner must 2. What is the bottom-line tradeoff in
month’s production in order to meet consider whether the new product terms of profitability?
the expected order for an additional will partially or fully cannibalize the 3. If we cut back the production of
35 units, or to transship the product existing product. The new forecast(s) a certain product, would we lose

Copyright © 2013 Journal of Business Forecasting | All Rights Reserved | Fall 2013 11
business only of that product room for materials normally made the raw material that is in short supply.
or also of whatever else those in the plant being shut down, and Alternatively, if the raw material will not
customers buy from us? for external sources, it is important be available from the usual supplier,
Question number three can only to determine whether or not then alternate suppliers, quantities, and
be answered on the basis of market the outside source can meet the prices have to be incorporated in to the
knowledge and business intelligence. demand in a timely fashion. model. Once again, an optimization or
A true optimization model with Like Case No. 3, the ability to rule-based model structured for this
appropriate prioritization of products model the move of a shutdown will purpose can easily do this job, as well
and profitability is needed to answer be significantly limited unless there as indicate the additional cost of using
the first two questions. Simple tools is a sophisticated optimization model alternate suppliers.
that are rule based (such as a home that can identify product that can While the cases above have dealt
grown tool in Excel) might not be able be moved from one unit to another primarily with issues internal to one’s
to evaluate the tradeoffs properly. or dropped altogether without a own business and production facilities,
significant penalty. Similarly, it is an experienced planner may also look
critical to recognize that there is not into other potential problems that are
CASE NO. 4 necessarily a one-to-one tradeoff beyond anyone’s control. If they occur,

MANAGING A PLANT between facilities, because Product


1 may take twice as long to run on
they could prove disastrous.

SHUTDOWN FOR alternate facility B as it does on primary


Case NO. 6
MAINTENANCE facility A, thereby causing an increase

Issues impacting supply can also


in the overall cost.
A Shipping
necessitate what-if planning. Let’s look
Case No. 5
lane becomes
at some examples.
In Case No. 4, planned shutdowns A key raw material unavailable
generally require a buildup of inventory
ahead of time to cover demand
IS IN short supply Let us now look at a business that
ships grain by barge from various ports
during the shutdown, particularly if In some standard capacity models, along the upper Mississippi to New
the shutdown is expected to be for a availability of raw materials may be Orleans for export. Suppose that in late
longer period. Two types of inventory assumed rather than be modeled. In 2011, a planner had enough foresight
must be considered: reality, this is not the case. Therefore, a to recognize that a drought might close
1. Products that can be made only at substantial restructuring of the model down most or all barge traffic along
the facility that is to be shut down. is required to account for the limitation the Mississippi in mid-2012 because
In that case, there is no alternative of a specific raw material. A properly of record low water. This is the sort of
source of supply, and then an formulated model (optimization or “out of the box” thinking that can prove
inventory buildup is imperative. heuristics based), which explicitly states invaluable if planning is done early
How far in advance that buildup raw material quantities available, can enough to allow the business to develop
must start will depend upon reflect a shortage by merely changing a plan that takes into account this worst-
not only the demand for these the appropriate table that holds these case scenario. The transportation section
products but also on the available data. (Most modern software will hold of an optimization model is generally
“spare capacity.” such data in tables that are kept in a set up in tables containing information
2. Products under consideration database.) It may show how much of a such as:
may have an alternative source certain amount of raw material will be 1. Mode(s) of transportation available
of supply, which may be internal available in a given month. It could also from A to B.
(an alternate facility) or external; show whether alternative bills of material 2. Capacity of each mode of trans­
each source may have its own (or alternative recipes) could provide portation available in each model­
limitations. Alternate facilities a way around the shortage by using a ing period.
must have “spare capacity” to make different recipe that does not require 3. Transit time from A to B for each

12 Copyright © 2013 Journal of Business Forecasting | All Rights Reserved | Fall 2013
transportation mode. model all those changes together. determine when the inventory buildup
In order to model a closure on the Further, if you now know that a must start in that event, while a second
Mississippi, the planner may make the shutdown will be moved from June to scenario run will determine when the
following changes: July, it should be made a part of the inventory buildup must start if the
1. Ensure that railcars can be used for same modeling run. business does not get the extra demand.
transportation for each location Suppose further, within a month, All sorts of permutations, however, may
where shipping is currently done there have been several disruptive require additional scenarios, including
by barge. changes in capacity. The management when the new demand is expected to
2. Set barge capacity to zero for each wants to know how much sales it would begin, with what if any other demand
such location for each anticipated lose as a result. Also, it wants to know it will replace, and whether we will lose
river closure period (month). how early we should start building up the rest of those customers’ business
3. Set the available railcar capacity for inventory for a seasonal demand that (see Case No. 3, question 3) beyond the
each current barge location/period is anticipated to be heavier than usual. orders we cannot fill.
to a number large enough to How many scenarios must a planner
handle the normal barge volume. run to answer these questions? Bringing the
Then the model will tell you the This sort of conundrum is faced by
exact railcar capacity you will need. planners every day. There is no pat and Change to the
4. Set the appropriate transit time for easy answer. But the planner needs to S&OP
each ship-from starting location to explain to those asking the question
New Orleans for the rail car transit. and/or to the S&OP team the reasons The role of the S&OP meeting is
Note that many versions of this for the output the planner produces. to summarize alternatives, and then
problem/solution can be run by While any optimization program makes seek the management’s approval.
varying the length of time of the low hundreds of thousands of decisions, the This requires a concise report backed
water, and even the section of the planner still needs to be able to make by detail as needed and then quickly
river that might be closed. In addition, sense of the results to “laymen.” taken to an offline meeting if too
tanker trucks could be added as an In the situation outlined here, much detail is required. For example,
additional transportation mode from the minimum scenario runs will be the anticipation of low water in the
some or all locations. Having run two, though more may be required. Mississippi months in the future might
these scenarios and making resulting First, consider that the anticipated be presented briefly in the S&OP, with
logistical arrangements in advance disruption to the capacity is now a separate meeting set up for those
could avoid a great deal of scrambling confirmed. The new (reduced) capacity who need more detail in order to make
and delay versus dealing with the should, therefore, be incorporated decisions, and to set trigger points
issue when it arises. If and when the in all new scenarios. Further, let us (e.g., water levels at specific points) for
crisis strikes, a company that is well assume that the reduced capacity will contingencies.
prepared can take away market share necessitate an inventory buildup if The only thing for sure in business is
from the competition. the demand is as expected. Since the change and uncertainty. If there were
business is anticipating the possibility no change, there would be no need
Which straw WILL of a higher-than-usual demand, the for planning beyond the back of an
next set of questions will then be envelope. Wherever what-if planning
brEAk the camel’s twofold: when should the inventory is done, the results should be brought
back? buildup begin if the heavier than into the S&OP process. How quickly
anticipated demand they should be brought to the attention
One of the most vexing questions a) Will not happen? of S&OP depends on the immediacy of
about what-if planning is how many b) Will happen? the need for a change. Indeed, part of
changes can or should be modeled at The answers to these two questions the training of an S&OP coordinator/
one time. Certain things are obvious. will be provided via two scenario runs. planner is to know what is critical and
When you have a whole new monthly One scenario run will assume that the what can wait for the usual up-coming
demand forecast, it is necessary to business gets the extra demand and monthly meeting. (info@ibf.org)

14 Copyright © 2013 Journal of Business Forecasting | All Rights Reserved | Fall 2013
Reproduced with permission of the copyright owner. Further reproduction prohibited without
permission.

You might also like