Rev.

No : 0
FABRICATION SCHEDULE As of Date :10 Aug

Client : PT. VICO


AIR COOLER Doc. No : 034-05-FS

SBS WO.No : 034/05 EG-7040 VLP GAS COMPRESSOR AFTERCOOLER


PO.NO : PO051697

WBS Task Name Duration Start Finish June July August September October November
29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20
1 ENGINEERING PREPARATION 66 days 02 Jun 18 Aug
1.1 Header Design Calculation 17 days 02 Jun 21 Jun
1.2 Header Drawing 17 days 02 Jun 21 Jun
1.3 Steel Structure Drawing 45 days 02 Jun 23 Jul
1.4 Procedure 66 days 02 Jun 18 Aug
1.5 Approval by Client 44 days 22 Jun 11 Aug
2 PROCUREMENT OF MATERIALS 85 days 27 Jun 05 Oct
2.1 Plate Header Box 6 ewks 04 Jul 15 Aug
2.2 Plate & Profile for Structure Work 4 ewks 28 Jul 25 Aug
2.3 Flange & Pipe 7.4 ewks 04 Jul 25 Aug
2.4 Fin Tubes 85 days 27 Jun 05 Oct
2.5 Tube Support Box 69 days 15 Jul 05 Oct
2.6 Hex. Plug, Plug Gasket 74 days 05 Jul 30 Sep
2.7 Electrical Motor, Drive System, Bearing 78 days 05 Jul 05 Oct
2.8 Fans 78 days 05 Jul 05 Oct
2.9 Vibration Switches 78 days 05 Jul 05 Oct
3 FABRICATION 61 days 23 Aug 10 Nov
3.1 EG-7040 - VLP GAS COMPRESSOR AFTER COOLER 61 days 23 Aug 10 Nov
3.1.1 Header Boxes 42 days 23 Aug 11 Oct
3.1.1.1 Marking, Cut, Bevel 3 days 23 Aug 25 Aug
3.1.1.2 Pilot Drilling 4 days 26 Aug 30 Aug
3.1.1.3 Joint Partition Plate to Tube/Plug Sheet 3 days 31 Aug 03 Sep
3.1.1.4 Joint Top/Boot/End Plate to Tube Sheet 7 days 05 Sep 12 Sep
3.1.1.5 NDT 2 days 13 Sep 14 Sep
3.1.1.6 Straightening 2 days 13 Sep 14 Sep
3.1.1.7 Joint Flange to Pipe 5 days 05 Sep 10 Sep
3.1.1.8 Lay Out & Cutting Nozzle holes 2 days 15 Sep 16 Sep
3.1.1.9 Joint Nozzle, Lug, bracket to Box 5 days 17 Sep 22 Sep
3.1.1.10 NDT 1 day 23 Sep 23 Sep
3.1.1.11 PWHT 2 days 24 Sep 26 Sep
3.1.1.12 Final Drill/Grove/Tap 8 days 27 Sep 05 Oct
3.1.1.13 Internal Cleaning 2 days 06 Oct 07 Oct

Task Milestone Project Summary


Prepared by PT.Surya Besindo Sakti
Progress Summary

Page 1 WO.034-05 Air Cooler Rev.0 - VICO


Rev. No : 0
FABRICATION SCHEDULE As of Date :10 Aug

Client : PT. VICO


AIR COOLER Doc. No : 034-05-FS

SBS WO.No : 034/05 EG-7040 VLP GAS COMPRESSOR AFTERCOOLER


PO.NO : PO051697

WBS Task Name Duration Start Finish June July August September October November
29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 02 09 16 23 30 06 13 20
3.1.1.14 Sand Blasting & Painting 3 days 08 Oct 11 Oct
3.1.2 Steel Structure Work 31 days 01 Sep 07 Oct
3.1.2.1 Header Frame 22 days 01 Sep 27 Sep
3.1.2.2 Fan Ring & Structure Details 22 days 07 Sep 01 Oct
3.1.2.3 Plenum 18 days 13 Sep 03 Oct
3.1.2.4 Galvanizing 4 days 04 Oct 07 Oct
3.1.3 Bundle Assembly & Insert Tube 3 days 12 Oct 14 Oct
3.1.4 Tube Expanding 3 days 15 Oct 18 Oct
3.1.5 Hydrostatic Test 2 days 19 Oct 20 Oct
3.1.6 Unit Assembly 4 days 21 Oct 25 Oct
3.1.7 Running Test 2 days 26 Oct 27 Oct
3.1.8 Dis-assembly 3 days 28 Oct 31 Oct
3.1.9 Packing 2 days 09 Nov 10 Nov

4 Delivery To SALIKI DOCK, EAST KALIMANTAN 8 edays 10 Nov 18 Nov

Task Milestone Project Summary


Prepared by PT.Surya Besindo Sakti
Progress Summary

Page 2 WO.034-05 Air Cooler Rev.0 - VICO