On-site measurements of Partial Discharges through tap of the bushings —


Brazilian experience in power transformers

Conference Paper · June 2013


DOI: 10.1109/ICSD.2013.6619767

CITATIONS READS

5 162

5 authors, including:

Hélio de Paiva Amorim Junior André T. Carvalho


Eletrobras Cepel Eletrobras Cepel
6 PUBLICATIONS   7 CITATIONS    10 PUBLICATIONS   70 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Fault identification in power equipment and networks View project

Análise de Qualidade do Isolamento de Geradores View project

All content following this page was uploaded by Caio F. F. C. Cunha on 10 September 2015.

The user has requested enhancement of the downloaded file.


2013 IEEE International Conference on Solid Dielectrics, Bologna, Italy, June 30 – July 4, 2013

On-Site Measurements of Partial Discharges Through Tap of the


Bushings – Brazilian Experience in Power Transformers
H. P. Amorim Jr. A. T. D. Carvalho T. B. Rodrigues J. B. S. Borges C. F. F. de C. Cunha
Department of Lines and Stations, DLE
Electric Energy Research Center - CEPEL
Rio de Janeiro, Brazil
amorim@cepel.br tomaz@cepel.br thiagobr@cepel.br borges@cepel.br caiocunha@cepel.br

Abstract—This paper describes the recent Brazilian experience specialists: the partial discharge measurement is still a
at on-site Partial Discharges (PD) measurement and analysis in fundamental tool to establish consistent evaluation of electrical
Power Transformers, including the development of IMA-DP performance of the insulation system.
(Instrumentation for Monitoring and Analysis of Partial
Discharges), designed by Eletrobras to monitor High Voltage II. PARTIAL DISCHARGES
Equipment. The proposed system includes high speed digitizer
The occurrence of partial discharges in the insulation
cards on an industrial computer and is designed to operate off-
system of the high voltage (HV) equipment is a symptom of
line or on-line, remotely logging statistical maps of PD over time.
The goal of this project was to evaluate the performance of the the fragility of the dielectric. Its evolution can have serious
operative state of power transformers of 138kV up to 500kV consequences for these equipments and for the whole electric
installed in the Brazilian electric power system. system. The measurement of partial discharges is made in
order to verify if there are discharge activities inside the
Keywords — Partial discharge, power transformers dielectric and, if possible, to quantify it.
Physically, Partial Discharges are the result of an
I. INTRODUCTION ionization process in gaseous environment in the interior of
The PD on-site evaluation on high voltage equipment is a dielectric materials, caused by an intense and located electric
predictive diagnosis tool that can assist in the accomplishment field [1]. From this process, several physical quantities are
generated in the local, like electromagnetic pulses, brightness,
of the maintenance of the equipment. The result of this
acoustic noise, temperature increasing and local chemical
evaluation can lead to the intervention in the equipment before
reactions.
it can suffer more serious damage. A catastrophic failure can
even affect the whole electrical system. Traditionally, PD have been evaluated by the measurement
of the high frequency electric pulses conducted on a specific
The measurement of partial discharges in power measurement circuit, according to the procedures described in
transformers has always caused intensive discussions and IEC 60270 [2], see Fig.1.
differing opinions on specialized technical groups. The state of
the art, which has evolved very little in recent years in terms of On an electromagnetic noisy environment such as electric
effective diagnosis of the machines, fails to produce the substations, signal pre-conditioning is required in order to
desired universal procedures and recommendations. discriminate noises from useful PD signals. The quality of an
on-site PD measurement is directly related with an efficient
The oil-paper insulation of a power transformer can pre-processing of the acquired signals. In order to provide
tolerate partial discharge for a while. Partial discharge activity, effective signal pre-conditioning for IMA-DP (Instrumentation
on the other hand is an indicator for degradation of the for Monitoring and Analysis of Partial Discharges) in such
insulation system. Thus, partial discharge monitoring is an electromagnetic noisy environment, customized analog filters
effective tool to evaluate its insulation system. have been successfully used.
Among reasons for the absence of universal measurement
procedures, we can cite the difficulty to quantify the severity
of the internal problem, since the registered amplitudes are
also functions of the location of the discharges. In this paper,
we presented three cases that can help on the discussion of the
importance of the partial discharge measurement.
The technologic stagnation results on a diversity of
solutions about monitoring and diagnosis according to the
culture and the technical knowledge of each company.
However, there is a common sense of the most part of Fig. 1. PD measurement circuit in laboratory.

978-1-4673-4461-6/13/$31.00 ©2013 IEEE

1020
2013 IEEE International Conference on Solid Dielectrics, Bologna, Italy, June 30 – July 4, 2013

III. PARTIAL DISCHARGES MEASUREMENT IV. FIELD RESULTS AND CASE STUDIES
Bushing sensors are employed at online electrical PD A. Case 1 - Transformer rating: 145 kV/69 kV – Three Single
measurements. They are installed in the capacitance tap of the Phase Tanks
bushings. Fig. 2 shows a typical bushing sensor that is
installed in the capacitance tap of a high-voltage bushing. These transformers are installed in the substation of the
Brazilian Electric Energy Research Center, CEPEL, in Rio de
Janeiro. It is used by the laboratory for special tests that
require high power. Therefore, it is an important equipment
and must be monitoring continuously. See Fig. 3.

Fig. 2- Typical bushing sensor and yours installation

Typically, bushing coupler units suited for permanent


installation are mounted to the test tap of the bushings. The
connector output of the bushing adapter is then connected to
the bushing coupler unit, which provides the high-frequency
signals superimposed with the AC signal derived from a
capacitor voltage divider, and also provides a second output
connector for bushing monitoring, such as: tan delta and Fig. 3. Power Transformer evaluated.
voltage measurements.
The phase resolved partial discharge measurement offers
The sensors must have the capability to catch the high- excellent possibilities to characterize the properties of defects
frequency signals of PD. One of the key issues in making on isolation materials. An example can be seen on a surface
electrical measurements is the noise, especially on high- graph shown in Fig. 4. From this representation, we can get
voltage substations. Typical noise found in high-voltage many other information, like total number of PD registered,
substations are corona and floating potentials. In this work and the graphics of pulse count versus phase or amplitude.
high-pass analog filters have been used to reduce noise of
Sequential results, each three months, indicated an
lower frequencies.
evolution in the intensity of Partial Discharges, see Fig. 5. In
Fig. 3 shows an arrangement of the on-site measurement this case, the recommendation is a more intense investigation
circuit. All the components – power transformers, bushing, and monitoring.
bushing sensors, measurement impedance (quadripoles), Currently, based on the analysis of PD data, this equipment
oscilloscope and IMA-DP – have been presented in this is under maintenance and will be recovered. After its recovery
Figure. a new sequence of PD tests will be programmed to evaluate
the effectiveness of the repair.

Fig. 5. Power Transformer evaluated Fig. 4. Phased Resolved Partial Discharge of Case A

978-1-4673-4461-6/13/$31.00 ©2013 IEEE

1021
2013 IEEE International Conference on Solid Dielectrics, Bologna, Italy, June 30 – July 4, 2013

Fig. 4. Power Transformer evaluated – Case 1 Fig. 6. PRPD of the High Voltage A-Phase – Case 3

B. Case 2 – Power Transformer rating: 230 kV/138 kV – The results confirmed PD existence and enabled us to
Three Single Phase Tanks evaluate its severity degree, see Fig. 6.

This is an important equipment of an electric substation in Unfortunately, the appropriate decision has been taken in
Brasil. A failure in this equipment may cause a blackout on time to prevent failure. The consideration of the PD
thousands of consumers in the central region of the country. In measurement as an essential tool to establish a robust
this case, IMA-DP was installed as a standalone system. assessment of electrical performance of the Power
Partial Discharge measurements were made during two days Transformer was not accepted by the company. After a few
continuously. The maximum detected PD was around 450 pC months, the electrical equipment failed, causing great damage
from the high-voltage B-Phase sensor, see Table I. and inconvenience technicians. The most important fact is the
confirmation of what was indicated by the PD measurement.
TABLE I.RESULTS OF PD MEASUREMENT ON POWER TRANSFORMER CASE 2.

Phase A - HV A - LV B - HV B - LV C - HV C - LV
Charge (pC) 300 350 450 350 150 200

A PRPD measurement of the High Voltage B-Phase is


shown on Figure 5. It is possible identify characteristic signals
of partial discharges in this PRDP through its relationship with
the reference signal of 60Hz.

Fig. 5. PRPD of the High Voltage B-Phase – Case 2

C. Case 3- Power Transformer rating: 550 kV/ 230 kV – Three


Single Phase Tanks
This is another very important equipment of an electric
substation in Brazil, see Fig. 7. An equipment failure can
cause prejudice thousands of consumers and various industries
with high electrical loads. The cost of such a failure is
incalculable.
In this case, a permanently PD monitoring system was Fig. 7. Power Transformers Failed
installed. Partial Discharge measurements were made during
four years continuously.

978-1-4673-4461-6/13/$31.00 ©2013 IEEE

1022
2013 IEEE International Conference on Solid Dielectrics, Bologna, Italy, June 30 – July 4, 2013

Digital PD measurement instrumentation for monitoring


V. RESULTS, DISCUSSIONS AND CONCLUSION purpose requires hardware with high sample rate and large
Analyzing and locating internal partial discharge activity memory, besides heavy signal process performed in parallel
on large power transformers is a demanding task. Power with the signal acquisition and storing processes. Another
transformers have a complex internal life that is mostly hidden important goal was the use of commercial, available modular
by the tank. Traditional methods along with modern measurement equipment, what has reduced the system’s final
measurement techniques offer results and information needed cost, making easier and cheaper the system’s maintenance,
to support maintenance. Signal processing techniques have repairs and future upgrades.
greatly improved traditional testing methods for accessing the
health of power transformers. One important result was to reduce the costs of the PD
monitoring system so that turn possible its installation on a
In this paper the practice of performing in-service electrical large number of measurement points at a large number of
PD monitoring on large power transformers has been Power Transformers of the Brazilian power system. This will
successfully demonstrated for three cases. One of them has improve our diagnostic capability of electrical equipment,
failed. This failure could have been avoided if measures had improving thus the reliability and availability of the electricity
been taken into account. This case demonstrates that the supply.
measurement of partial discharges may be very useful in
preventing future failures. REFERENCES
Moreover, since 2004 IMA-DP has been used in two [1] “IEC 60270 - High Voltage Test Techniques: Partial Discharge
hydro-generators at a Brazilian hydroelectric power plant Measurements, third edition (2000)”. 2000.
located in Tucuruí, the biggest genuinely Brazilian [2] J. R. Perkins, “Some general remarks on corona discharges”,
Engineering Dielectrics Volume I: Corona Measurement and
hydroelectric plant. Besides that, it will be soon installed in Interpretation, ASTM Special Publication 699, Philadelphia, 1979, pp
others hydroelectric plants, in thermal plants and in nuclear 03-21.
plants in Brazil. [3] IEEE C57.113-1991 "IEEE Recommended Practice for Partial Discharge
Measurement in Liquid- Filled Power Transformers and Shunt
Reactors".
[4] D. Gross, M.. Soeller, "Partial Discharge Diagnosis on large Power
Transformers," ISEI 2004 Conference, Indianapolis, IN, September 19-
222004, 04CH37561C, pp. 186-191.

978-1-4673-4461-6/13/$31.00 ©2013 IEEE

1023
View publication stats

You might also like