September 2016 - BNR
September 2016 - BNR
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -01 Fine Aggregates Quality Test Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/1/2016 P. Barcelona / D. Bacomo 6/2/2016 Contr's. Lab. Recommended for use
15R021 -02 Coarse Aggregates Quality Test Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/1/2016 P. Barcelona / D. Bacomo 6/2/2016 Contr's. Lab. Recommended for use
15R021 -03 Coarse & Fine Agg. Quality Test Malogo River SGA 311 (1)f1 P. Barcelona / D. Bacomo 6/1/2016 P. Barcelona / D. Bacomo 6/3/2016 Contr's. Lab. Satisfactory
15R021 -04 Coarse Aggregates Quality Test Malogo River AL 311 (1)f1 P. Barcelona / D. Bacomo 6/1/2016 P. Barcelona / D. Bacomo 6/3/2016 DPWH Lab. Satisfactory
15R021 -05 Agg. Sub-Base Course Quality Test Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 6/4/2016 P. Barcelona / D. Bacomo 6/6/2016 Contr's. Lab. Satisfactory
15R021 -06 Agg. Sub-Base Course Quality Test Sicaba River LC 200 (1) P. Barcelona / D. Bacomo 6/4/2016 P. Barcelona / D. Bacomo 6/6/2016 Contr's. Lab. Satisfactory
15R021 -07 Agg. Sub-Base Course Quality Test Sicaba River AL 200 (1) P. Barcelona / D. Bacomo 6/4/2016 P. Barcelona / D. Bacomo 6/6/2016 DPWH Lab. Satisfactory
15R021 -08 Subgrade Quality Test Existing G/P 105 (1)b P. Barcelona / D. Bacomo 6/6/2016 P. Barcelona / D. Bacomo 6/7/2016 Contr's. Lab. Satisfactory
15R021 -09 Embankment Quality Test Existing G/P 104 (1)c P. Barcelona / D. Bacomo 6/6/2016 P. Barcelona / D. Bacomo 6/7/2016 Contr's. Lab. Satisfactory
15R021 -10 Subgrade Quality Test Existing LC 105 (1)b P. Barcelona / D. Bacomo 6/6/2016 P. Barcelona / D. Bacomo 6/8/2016 Contr's. Lab. Satisfactory
15R021 -11 Embankment Quality Test Existing LC 104 (1)c P. Barcelona / D. Bacomo 6/6/2016 P. Barcelona / D. Bacomo 6/8/2016 Contr's. Lab. Satisfactory
15R021 -12 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 6/10/2016 Jobsite Satisfactory
15R021 -13 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 6/11/2016 Jobsite Satisfactory
15R021 -14 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 6/11/2016 P. Barcelona / D. Bacomo 6/13/2016 Contr's. Lab. Satisfactory
15R021 -15 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 6/11/2016 P. Barcelona / D. Bacomo 6/13/2016 Contr's. Lab. Satisfactory
15R021 -16 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 6/14/2016 Jobsite Satisfactory
15R021 -17 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 6/15/2016 Jobsite Satisfactory
15R021 -18 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 6/15/2016 P. Barcelona / D. Bacomo 6/16/2016 Contr's. Lab. Satisfactory
15R021 -19 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 6/16/2016 P. Barcelona / D. Bacomo 6/17/2016 Contr's. Lab. Satisfactory
15R021 -20 Concrete Beam Trial Mix FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 6/4/2016 P. Barcelona / D. Bacomo 6/18/2016 DPWH Lab. Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF June - August 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -21 Reinf. Steel Bar 11813.63 kg. Jobsite U.W 311 (1)f1 P. Barcelona / D. Bacomo P. Barcelona / D. Bacomo 6/18/2016 Contr's. Lab. Satisfactory
15R021 -22 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 6/18/2016 Jobsite Satisfactory
15R021 -23 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/18/2016 Contr's. Lab. Satisfactory
15R021 -24 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Satisfactory
15R021 -25 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Recommended for use
15R021 -26 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Recommended for use
15R021 -27 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Recommended for use
15R021 -28 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Recommended for use
15R021 -29 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Recommended for use
15R021 -30 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 6/20/2016 Jobsite Satisfactory
15R021 -31 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Satisfactory
15R021 -32 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Satisfactory
15R021 -33 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Recommended for use
15R021 -34 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Recommended for use
15R021 -35 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Recommended for use
15R021 -36 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Recommended for use
15R021 -37 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Recommended for use
15R021 -38 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 6/24/2016 Jobsite Satisfactory
15R021 -39 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 6/25/2016 P. Barcelona / D. Bacomo 6/27/2016 Contr's. Lab. Satisfactory
15R021 -40 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 6/27/2016 Jobsite Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF June - August 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -41 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 6/28/2016 Jobsite Satisfactory
15R021 -42 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 6/29/2016 P. Barcelona / D. Bacomo 6/30/2016 Contr's. Lab. Satisfactory
15R021 -43 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/30/2016 P. Barcelona / D. Bacomo 7/1/2016 Contr's. Lab. Recommended for use
15R021 -44 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/30/2016 P. Barcelona / D. Bacomo 7/1/2016 Contr's. Lab. Recommended for use
15R021 -45 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/30/2016 P. Barcelona / D. Bacomo 7/1/2016 Contr's. Lab. Recommended for use
15R021 -46 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 7/1/2016 Jobsite Satisfactory
15R021 -47 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/1/2016 P. Barcelona / D. Bacomo 7/2/2016 Contr's. Lab. Satisfactory
15R021 -48 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/1/2016 P. Barcelona / D. Bacomo 7/2/2016 Contr's. Lab. Satisfactory
15R021 -49 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 7/2/2016 Jobsite Satisfactory
15R021 -50 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/2/2016 P. Barcelona / D. Bacomo 7/4/2016 Contr's. Lab. Satisfactory
15R021 -51 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 7/4/2016 Jobsite Satisfactory
15R021 -52 Concrete Beam 494.10 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 6/21/2016 P. Barcelona / D. Bacomo 7/5/2016 DPWH Lab. Satisfactory
15R021 -53 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/6/2016 P. Barcelona / D. Bacomo 7/7/2016 Contr's. Lab. Satisfactory
15R021 -54 Concrete Beam 444.69 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 6/24/2016 P. Barcelona / D. Bacomo 7/8/2016 DPWH Lab. Satisfactory
15R021 -55 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/8/2016 P. Barcelona / D. Bacomo 7/9/2016 Contr's. Lab. Recommended for use
15R021 -56 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/8/2016 P. Barcelona / D. Bacomo 7/9/2016 Contr's. Lab. Recommended for use
15R021 -57 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/8/2016 P. Barcelona / D. Bacomo 7/9/2016 Contr's. Lab. Recommended for use
15R021 -58 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/8/2016 P. Barcelona / D. Bacomo 7/9/2016 Contr's. Lab. Satisfactory
15R021 -59 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/11/2016 Contr's. Lab. Satisfactory
15R021 -60 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/11/2016 Contr's. Lab. Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF June - August 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -61 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/11/2016 Contr's. Lab. Recommended for use
15R021 -62 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/11/2016 Contr's. Lab. Recommended for use
15R021 -63 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/11/2016 Contr's. Lab. Recommended for use
15R021 -64 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 7/11/2016 Jobsite Satisfactory
15R021 -65 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/12/2016 P. Barcelona / D. Bacomo 7/10/2016 Contr's. Lab. Satisfactory
15R021 -66 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/14/2016 Contr's. Lab. Satisfactory
15R021 -67 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/14/2016 Contr's. Lab. Satisfactory
15R021 -68 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/14/2016 Contr's. Lab. Recommended for use
15R021 -69 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/14/2016 Contr's. Lab. Recommended for use
15R021 -70 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/14/2016 Contr's. Lab. Recommended for use
15R021 -71 Concrete Beam 378.81 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 7/4/2016 P. Barcelona / D. Bacomo 7/18/2016 DPWH Lab. Recommended for use
15R021 -72 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Recommended for use
15R021 -73 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Recommended for use
15R021 -74 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Recommended for use
15R021 -75 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Recommended for use
15R021 -76 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Recommended for use
15R021 -77 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Satisfactory
15R021 -78 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 7/18/2016 Jobsite Satisfactory
15R021 -79 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/20/2016 P. Barcelona / D. Bacomo 7/21/2016 Contr's. Lab. Satisfactory
15R021 -80 Agg. Sub-Base Course Quality Test Sicaba River LC 200 (1) P. Barcelona / D. Bacomo 7/20/2016 P. Barcelona / D. Bacomo 7/22/2016 Contr's. Lab. Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF June - August 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -81 Agg. Sub-Base Course Quality Test Sicaba River AL 200 (1) P. Barcelona / D. Bacomo 7/20/2016 P. Barcelona / D. Bacomo 7/22/2016 DPWH Lab. Satisfactory
15R021 -82 Concrete Beam 362.34 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/23/2016 DPWH Lab. Satisfactory
15R021 -83 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 7/24/2016 Jobsite Satisfactory
15R021 -84 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Satisfactory
15R021 -85 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Recommended for use
15R021 -86 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Recommended for use
15R021 -87 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Recommended for use
15R021 -88 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Recommended for use
15R021 -89 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Recommended for use
15R021 -90 Agg. Sub-Base Course Quality Test Sicaba River AL 200 (1) P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 DPWH Lab. Satisfactory
15R021 -91 Coarse Aggregate Quality Test Malogo River AL 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 DPWH Lab. Satisfactory
15R021 -92 Concrete Beam 345.87 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/27/2016 DPWH Lab. Satisfactory
15R021 -93 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/26/2016 P. Barcelona / D. Bacomo 7/27/2016 Contr's. Lab. Satisfactory
15R021 -94 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/27/2016 P. Barcelona / D. Bacomo 7/28/2016 Contr's. Lab. Recommended for use
15R021 -95 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/27/2016 P. Barcelona / D. Bacomo 7/28/2016 Contr's. Lab. Recommended for use
15R021 -96 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/27/2016 P. Barcelona / D. Bacomo 7/28/2016 Contr's. Lab. Recommended for use
15R021 -97 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/28/2016 P. Barcelona / D. Bacomo 7/29/2016 Contr's. Lab. Satisfactory
15R021 -98 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/28/2016 P. Barcelona / D. Bacomo 7/29/2016 Contr's. Lab. Satisfactory
15R021 -99 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/28/2016 P. Barcelona / D. Bacomo 7/29/2016 Contr's. Lab. Satisfactory
15R021 -100 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/28/2016 P. Barcelona / D. Bacomo 7/29/2016 Contr's. Lab. Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF June - August 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -101 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/28/2016 P. Barcelona / D. Bacomo 7/29/2016 Contr's. Lab. Satisfactory
15R021 -102 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/29/2016 P. Barcelona / D. Bacomo 7/30/2016 Contr's. Lab. Satisfactory
15R021 -103 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/29/2016 P. Barcelona / D. Bacomo 7/30/2016 Contr's. Lab. Satisfactory
15R021 -104 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 7/30/2016 Jobsite Satisfactory
15R021 -105 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Satisfactory
15R021 -106 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Satisfactory
15R021 -107 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Satisfactory
15R021 -108 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Recommended for use
15R021 -109 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Recommended for use
15R021 -110 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Recommended for use
15R021 -111 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 8/2/2016 Jobsite Satisfactory
15R021 -112 Concrete Beam 428.22 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 7/20/2016 P. Barcelona / D. Bacomo 8/3/2016 DPWH Lab. Satisfactory
15R021 -113 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/3/2016 Contr's. Lab. Satisfactory
15R021 -114 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/3/2016 Contr's. Lab. Satisfactory
15R021 -115 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Satisfactory
15R021 -116 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Satisfactory
15R021 -117 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Satisfactory
15R021 -118 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Recommended for use
15R021 -119 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Recommended for use
15R021 -120 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Recommended for use
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF June - August 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -121 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 8/5/2016 Jobsite Satisfactory
15R021 -122 Agg. Sub-Base Course Quality Test Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Satisfactory
15R021 -123 Agg. Sub-Base Course Quality Test Sicaba River AL 200 (1) P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 DPWH Lab. Satisfactory
15R021 -124 Portland Cement 1,000 bags Jobsite FT 200 (1) P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Satisfactory
15R021 -125 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Satisfactory
15R021 -126 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Recommended for use
15R021 -127 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Recommended for use
15R021 -128 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Recommended for use
15R021 -129 Concrete Beam 444.69 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 7/26/2019 P. Barcelona / D. Bacomo 8/9/2016 DPWH Lab. Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF September 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment :
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -131 Concrete Beam Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 8/9/2016 P. Barcelona / D. Bacomo 8/23/2016 DPWH Lab. Satisfactory
15R021 -132 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/25/2016 P. Barcelona / D. Bacomo 8/26/2016 Contr's. Lab. Satisfactory
15R021 -133 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/25/2016 P. Barcelona / D. Bacomo 8/26/2016 Contr's. Lab. Satisfactory
15R021 -134 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 8/27/2016 P. Barcelona / D. Bacomo 8/29/2016 Contr's. Lab. Satisfactory
15R021 -135 Fine Aggregates 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/27/2016 P. Barcelona / D. Bacomo 8/29/2016 Contr's. Lab. Recommended for use
15R021 -136 Coarse Aggregates 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/27/2016 P. Barcelona / D. Bacomo 8/29/2016 Contr's. Lab. Recommended for use
15R021 -137 Coarse Aggregates 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/27/2016 P. Barcelona / D. Bacomo 8/29/2016 Contr's. Lab. Recommended for use
15R021 -138 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 9/7/2016 P. Barcelona / D. Bacomo 9/8/2016 Contr's. Lab. Satisfactory
15R021 -139 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 9/7/2016 P. Barcelona / D. Bacomo 9/8/2016 Contr's. Lab. Satisfactory
15R021 -140 Fine Aggregates 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 9/10/2016 P. Barcelona / D. Bacomo 9/12/2016 Contr's. Lab. Recommended for use
15R021 -141 Coarse Aggregates 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 9/10/2016 P. Barcelona / D. Bacomo 9/12/2016 Contr's. Lab. Recommended for use
15R021 -142 Coarse Aggregates 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 9/10/2016 P. Barcelona / D. Bacomo 9/12/2016 Contr's. Lab. Recommended for use
15R021 -143 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 9/10/2016 P. Barcelona / D. Bacomo 9/12/2016 Contr's. Lab. Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -21 Reinf. Steel Bar 11813.63 kg. Jobsite U.W 311 (1)f1 P. Barcelona / D. Bacomo P. Barcelona / D. Bacomo 6/18/2016 Contr's. Lab. Satisfactory
15R021 -22 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 6/18/2016 Jobsite Satisfactory
15R021 -23 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/18/2016 Contr's. Lab. Satisfactory
15R021 -24 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Satisfactory
15R021 -25 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Recommended for use
15R021 -26 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Recommended for use
15R021 -27 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Recommended for use
15R021 -28 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Recommended for use
15R021 -29 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Recommended for use
15R021 -30 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 6/20/2016 Jobsite Satisfactory
15R021 -31 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Satisfactory
15R021 -32 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Satisfactory
15R021 -33 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Recommended for use
15R021 -34 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Recommended for use
15R021 -35 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Recommended for use
15R021 -36 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Recommended for use
15R021 -37 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Recommended for use
15R021 -38 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 6/24/2016 Jobsite Satisfactory
15R021 -39 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 6/25/2016 P. Barcelona / D. Bacomo 6/27/2016 Contr's. Lab. Satisfactory
15R021 -40 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 6/27/2016 Jobsite Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF September 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -41 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 6/28/2016 Jobsite Satisfactory
15R021 -42 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 6/29/2016 P. Barcelona / D. Bacomo 6/30/2016 Contr's. Lab. Satisfactory
15R021 -43 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/30/2016 P. Barcelona / D. Bacomo 7/1/2016 Contr's. Lab. Recommended for use
15R021 -44 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/30/2016 P. Barcelona / D. Bacomo 7/1/2016 Contr's. Lab. Recommended for use
15R021 -45 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/30/2016 P. Barcelona / D. Bacomo 7/1/2016 Contr's. Lab. Recommended for use
15R021 -46 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 7/1/2016 Jobsite Satisfactory
15R021 -47 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/1/2016 P. Barcelona / D. Bacomo 7/2/2016 Contr's. Lab. Satisfactory
15R021 -48 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/1/2016 P. Barcelona / D. Bacomo 7/2/2016 Contr's. Lab. Satisfactory
15R021 -49 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 7/2/2016 Jobsite Satisfactory
15R021 -50 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/2/2016 P. Barcelona / D. Bacomo 7/4/2016 Contr's. Lab. Satisfactory
15R021 -51 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 7/4/2016 Jobsite Satisfactory
15R021 -52 Concrete Beam 494.10 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 6/21/2016 P. Barcelona / D. Bacomo 7/5/2016 DPWH Lab. Satisfactory
15R021 -53 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/6/2016 P. Barcelona / D. Bacomo 7/7/2016 Contr's. Lab. Satisfactory
15R021 -54 Concrete Beam 444.69 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 6/24/2016 P. Barcelona / D. Bacomo 7/8/2016 DPWH Lab. Satisfactory
15R021 -55 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/8/2016 P. Barcelona / D. Bacomo 7/9/2016 Contr's. Lab. Recommended for use
15R021 -56 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/8/2016 P. Barcelona / D. Bacomo 7/9/2016 Contr's. Lab. Recommended for use
15R021 -57 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/8/2016 P. Barcelona / D. Bacomo 7/9/2016 Contr's. Lab. Recommended for use
15R021 -58 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/8/2016 P. Barcelona / D. Bacomo 7/9/2016 Contr's. Lab. Satisfactory
15R021 -59 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/11/2016 Contr's. Lab. Satisfactory
15R021 -60 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/11/2016 Contr's. Lab. Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF September 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -61 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/11/2016 Contr's. Lab. Recommended for use
15R021 -62 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/11/2016 Contr's. Lab. Recommended for use
15R021 -63 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/11/2016 Contr's. Lab. Recommended for use
15R021 -64 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 7/11/2016 Jobsite Satisfactory
15R021 -65 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/12/2016 P. Barcelona / D. Bacomo 7/10/2016 Contr's. Lab. Satisfactory
15R021 -66 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/14/2016 Contr's. Lab. Satisfactory
15R021 -67 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/14/2016 Contr's. Lab. Satisfactory
15R021 -68 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/14/2016 Contr's. Lab. Recommended for use
15R021 -69 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/14/2016 Contr's. Lab. Recommended for use
15R021 -70 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/14/2016 Contr's. Lab. Recommended for use
15R021 -71 Concrete Beam 378.81 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 7/4/2016 P. Barcelona / D. Bacomo 7/18/2016 DPWH Lab. Recommended for use
15R021 -72 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Recommended for use
15R021 -73 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Recommended for use
15R021 -74 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Recommended for use
15R021 -75 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Recommended for use
15R021 -76 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Recommended for use
15R021 -77 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Satisfactory
15R021 -78 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 7/18/2016 Jobsite Satisfactory
15R021 -79 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/20/2016 P. Barcelona / D. Bacomo 7/21/2016 Contr's. Lab. Satisfactory
15R021 -80 Agg. Sub-Base Course Quality Test Sicaba River LC 200 (1) P. Barcelona / D. Bacomo 7/20/2016 P. Barcelona / D. Bacomo 7/22/2016 Contr's. Lab. Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF September 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -81 Agg. Sub-Base Course Quality Test Sicaba River AL 200 (1) P. Barcelona / D. Bacomo 7/20/2016 P. Barcelona / D. Bacomo 7/22/2016 DPWH Lab. Satisfactory
15R021 -82 Concrete Beam 362.34 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/23/2016 DPWH Lab. Satisfactory
15R021 -83 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 7/24/2016 Jobsite Satisfactory
15R021 -84 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Satisfactory
15R021 -85 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Recommended for use
15R021 -86 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Recommended for use
15R021 -87 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Recommended for use
15R021 -88 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Recommended for use
15R021 -89 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Recommended for use
15R021 -90 Agg. Sub-Base Course Quality Test Sicaba River AL 200 (1) P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 DPWH Lab. Satisfactory
15R021 -91 Coarse Aggregate Quality Test Malogo River AL 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 DPWH Lab. Satisfactory
15R021 -92 Concrete Beam 345.87 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/27/2016 DPWH Lab. Satisfactory
15R021 -93 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/26/2016 P. Barcelona / D. Bacomo 7/27/2016 Contr's. Lab. Satisfactory
15R021 -94 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/27/2016 P. Barcelona / D. Bacomo 7/28/2016 Contr's. Lab. Recommended for use
15R021 -95 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/27/2016 P. Barcelona / D. Bacomo 7/28/2016 Contr's. Lab. Recommended for use
15R021 -96 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/27/2016 P. Barcelona / D. Bacomo 7/28/2016 Contr's. Lab. Recommended for use
15R021 -97 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/28/2016 P. Barcelona / D. Bacomo 7/29/2016 Contr's. Lab. Satisfactory
15R021 -98 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/28/2016 P. Barcelona / D. Bacomo 7/29/2016 Contr's. Lab. Satisfactory
15R021 -99 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/28/2016 P. Barcelona / D. Bacomo 7/29/2016 Contr's. Lab. Satisfactory
15R021 -100 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/28/2016 P. Barcelona / D. Bacomo 7/29/2016 Contr's. Lab. Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF September 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -101 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/28/2016 P. Barcelona / D. Bacomo 7/29/2016 Contr's. Lab. Satisfactory
15R021 -102 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/29/2016 P. Barcelona / D. Bacomo 7/30/2016 Contr's. Lab. Satisfactory
15R021 -103 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/29/2016 P. Barcelona / D. Bacomo 7/30/2016 Contr's. Lab. Satisfactory
15R021 -104 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 7/30/2016 Jobsite Satisfactory
15R021 -105 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Satisfactory
15R021 -106 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Satisfactory
15R021 -107 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Satisfactory
15R021 -108 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Recommended for use
15R021 -109 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Recommended for use
15R021 -110 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Recommended for use
15R021 -111 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 8/2/2016 Jobsite Satisfactory
15R021 -112 Concrete Beam 428.22 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 7/20/2016 P. Barcelona / D. Bacomo 8/3/2016 DPWH Lab. Satisfactory
15R021 -113 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/3/2016 Contr's. Lab. Satisfactory
15R021 -114 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/3/2016 Contr's. Lab. Satisfactory
15R021 -115 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Satisfactory
15R021 -116 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Satisfactory
15R021 -117 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Satisfactory
15R021 -118 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Recommended for use
15R021 -119 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Recommended for use
15R021 -120 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Recommended for use
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF September 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -121 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 8/5/2016 Jobsite Satisfactory
15R021 -122 Agg. Sub-Base Course Quality Test Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Satisfactory
15R021 -123 Agg. Sub-Base Course Quality Test Sicaba River AL 200 (1) P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 DPWH Lab. Satisfactory
15R021 -124 Portland Cement 1,000 bags Jobsite FT 200 (1) P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Satisfactory
15R021 -125 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Satisfactory
15R021 -126 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Recommended for use
15R021 -127 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Recommended for use
15R021 -128 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Recommended for use
15R021 -129 Concrete Beam 444.69 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 7/26/2019 P. Barcelona / D. Bacomo 8/9/2016 DPWH Lab. Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF September 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment :
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -131 Concrete Beam Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 8/9/2016 P. Barcelona / D. Bacomo 8/23/2016 DPWH Lab. Satisfactory
15R021 -132 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/25/2016 P. Barcelona / D. Bacomo 8/26/2016 Contr's. Lab. Satisfactory
15R021 -133 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/25/2016 P. Barcelona / D. Bacomo 8/26/2016 Contr's. Lab. Satisfactory
15R021 -134 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 8/27/2016 P. Barcelona / D. Bacomo 8/29/2016 Contr's. Lab. Satisfactory
15R021 -135 Fine Aggregates 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/27/2016 P. Barcelona / D. Bacomo 8/29/2016 Contr's. Lab. Recommended for use
15R021 -136 Coarse Aggregates 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/27/2016 P. Barcelona / D. Bacomo 8/29/2016 Contr's. Lab. Recommended for use
15R021 -137 Coarse Aggregates 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/27/2016 P. Barcelona / D. Bacomo 8/29/2016 Contr's. Lab. Recommended for use
15R021 -138 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 9/7/2016 P. Barcelona / D. Bacomo 9/8/2016 Contr's. Lab. Satisfactory
15R021 -139 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 9/7/2016 P. Barcelona / D. Bacomo 9/8/2016 Contr's. Lab. Satisfactory
15R021 -140 Fine Aggregates 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 9/10/2016 P. Barcelona / D. Bacomo 9/12/2016 Contr's. Lab. Recommended for use
15R021 -141 Coarse Aggregates 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 9/10/2016 P. Barcelona / D. Bacomo 9/12/2016 Contr's. Lab. Recommended for use
15R021 -142 Coarse Aggregates 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 9/10/2016 P. Barcelona / D. Bacomo 9/12/2016 Contr's. Lab. Recommended for use
15R021 -143 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 9/10/2016 P. Barcelona / D. Bacomo 9/12/2016 Contr's. Lab. Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF September 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -21 Reinf. Steel Bar 11813.63 kg. Jobsite U.W 311 (1)f1 P. Barcelona / D. Bacomo P. Barcelona / D. Bacomo 6/18/2016 Contr's. Lab. Satisfactory
15R021 -22 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 6/18/2016 Jobsite Satisfactory
15R021 -23 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/18/2016 Contr's. Lab. Satisfactory
15R021 -24 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Satisfactory
15R021 -25 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Recommended for use
15R021 -26 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Recommended for use
15R021 -27 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Recommended for use
15R021 -28 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Recommended for use
15R021 -29 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/18/2016 P. Barcelona / D. Bacomo 6/19/2016 Contr's. Lab. Recommended for use
15R021 -30 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 6/20/2016 Jobsite Satisfactory
15R021 -31 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Satisfactory
15R021 -32 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Satisfactory
15R021 -33 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Recommended for use
15R021 -34 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Recommended for use
15R021 -35 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Recommended for use
15R021 -36 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Recommended for use
15R021 -37 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/23/2016 P. Barcelona / D. Bacomo 6/24/2016 Contr's. Lab. Recommended for use
15R021 -38 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 6/24/2016 Jobsite Satisfactory
15R021 -39 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 6/25/2016 P. Barcelona / D. Bacomo 6/27/2016 Contr's. Lab. Satisfactory
15R021 -40 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 6/27/2016 Jobsite Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF September 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -41 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 6/28/2016 Jobsite Satisfactory
15R021 -42 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 6/29/2016 P. Barcelona / D. Bacomo 6/30/2016 Contr's. Lab. Satisfactory
15R021 -43 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/30/2016 P. Barcelona / D. Bacomo 7/1/2016 Contr's. Lab. Recommended for use
15R021 -44 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/30/2016 P. Barcelona / D. Bacomo 7/1/2016 Contr's. Lab. Recommended for use
15R021 -45 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 6/30/2016 P. Barcelona / D. Bacomo 7/1/2016 Contr's. Lab. Recommended for use
15R021 -46 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 7/1/2016 Jobsite Satisfactory
15R021 -47 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/1/2016 P. Barcelona / D. Bacomo 7/2/2016 Contr's. Lab. Satisfactory
15R021 -48 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/1/2016 P. Barcelona / D. Bacomo 7/2/2016 Contr's. Lab. Satisfactory
15R021 -49 Subgrade Existing FDT 105 (1)b P. Barcelona / D. Bacomo 7/2/2016 Jobsite Satisfactory
15R021 -50 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/2/2016 P. Barcelona / D. Bacomo 7/4/2016 Contr's. Lab. Satisfactory
15R021 -51 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 7/4/2016 Jobsite Satisfactory
15R021 -52 Concrete Beam 494.10 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 6/21/2016 P. Barcelona / D. Bacomo 7/5/2016 DPWH Lab. Satisfactory
15R021 -53 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/6/2016 P. Barcelona / D. Bacomo 7/7/2016 Contr's. Lab. Satisfactory
15R021 -54 Concrete Beam 444.69 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 6/24/2016 P. Barcelona / D. Bacomo 7/8/2016 DPWH Lab. Satisfactory
15R021 -55 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/8/2016 P. Barcelona / D. Bacomo 7/9/2016 Contr's. Lab. Recommended for use
15R021 -56 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/8/2016 P. Barcelona / D. Bacomo 7/9/2016 Contr's. Lab. Recommended for use
15R021 -57 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/8/2016 P. Barcelona / D. Bacomo 7/9/2016 Contr's. Lab. Recommended for use
15R021 -58 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/8/2016 P. Barcelona / D. Bacomo 7/9/2016 Contr's. Lab. Satisfactory
15R021 -59 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/11/2016 Contr's. Lab. Satisfactory
15R021 -60 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/11/2016 Contr's. Lab. Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF September 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -61 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/11/2016 Contr's. Lab. Recommended for use
15R021 -62 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/11/2016 Contr's. Lab. Recommended for use
15R021 -63 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/11/2016 Contr's. Lab. Recommended for use
15R021 -64 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 7/11/2016 Jobsite Satisfactory
15R021 -65 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/12/2016 P. Barcelona / D. Bacomo 7/10/2016 Contr's. Lab. Satisfactory
15R021 -66 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/14/2016 Contr's. Lab. Satisfactory
15R021 -67 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/14/2016 Contr's. Lab. Satisfactory
15R021 -68 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/14/2016 Contr's. Lab. Recommended for use
15R021 -69 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/14/2016 Contr's. Lab. Recommended for use
15R021 -70 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/14/2016 Contr's. Lab. Recommended for use
15R021 -71 Concrete Beam 378.81 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 7/4/2016 P. Barcelona / D. Bacomo 7/18/2016 DPWH Lab. Recommended for use
15R021 -72 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Recommended for use
15R021 -73 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Recommended for use
15R021 -74 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Recommended for use
15R021 -75 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Recommended for use
15R021 -76 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Recommended for use
15R021 -77 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/16/2016 P. Barcelona / D. Bacomo 7/18/2016 Contr's. Lab. Satisfactory
15R021 -78 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 7/18/2016 Jobsite Satisfactory
15R021 -79 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/20/2016 P. Barcelona / D. Bacomo 7/21/2016 Contr's. Lab. Satisfactory
15R021 -80 Agg. Sub-Base Course Quality Test Sicaba River LC 200 (1) P. Barcelona / D. Bacomo 7/20/2016 P. Barcelona / D. Bacomo 7/22/2016 Contr's. Lab. Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF September 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -81 Agg. Sub-Base Course Quality Test Sicaba River AL 200 (1) P. Barcelona / D. Bacomo 7/20/2016 P. Barcelona / D. Bacomo 7/22/2016 DPWH Lab. Satisfactory
15R021 -82 Concrete Beam 362.34 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 7/9/2016 P. Barcelona / D. Bacomo 7/23/2016 DPWH Lab. Satisfactory
15R021 -83 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 7/24/2016 Jobsite Satisfactory
15R021 -84 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Satisfactory
15R021 -85 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Recommended for use
15R021 -86 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Recommended for use
15R021 -87 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Recommended for use
15R021 -88 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Recommended for use
15R021 -89 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 Contr's. Lab. Recommended for use
15R021 -90 Agg. Sub-Base Course Quality Test Sicaba River AL 200 (1) P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 DPWH Lab. Satisfactory
15R021 -91 Coarse Aggregate Quality Test Malogo River AL 311 (1)f1 P. Barcelona / D. Bacomo 7/23/2016 P. Barcelona / D. Bacomo 7/25/2016 DPWH Lab. Satisfactory
15R021 -92 Concrete Beam 345.87 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 7/13/2016 P. Barcelona / D. Bacomo 7/27/2016 DPWH Lab. Satisfactory
15R021 -93 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/26/2016 P. Barcelona / D. Bacomo 7/27/2016 Contr's. Lab. Satisfactory
15R021 -94 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/27/2016 P. Barcelona / D. Bacomo 7/28/2016 Contr's. Lab. Recommended for use
15R021 -95 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/27/2016 P. Barcelona / D. Bacomo 7/28/2016 Contr's. Lab. Recommended for use
15R021 -96 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/27/2016 P. Barcelona / D. Bacomo 7/28/2016 Contr's. Lab. Recommended for use
15R021 -97 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/28/2016 P. Barcelona / D. Bacomo 7/29/2016 Contr's. Lab. Satisfactory
15R021 -98 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/28/2016 P. Barcelona / D. Bacomo 7/29/2016 Contr's. Lab. Satisfactory
15R021 -99 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/28/2016 P. Barcelona / D. Bacomo 7/29/2016 Contr's. Lab. Satisfactory
15R021 -100 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/28/2016 P. Barcelona / D. Bacomo 7/29/2016 Contr's. Lab. Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF September 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -101 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/28/2016 P. Barcelona / D. Bacomo 7/29/2016 Contr's. Lab. Satisfactory
15R021 -102 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/29/2016 P. Barcelona / D. Bacomo 7/30/2016 Contr's. Lab. Satisfactory
15R021 -103 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/29/2016 P. Barcelona / D. Bacomo 7/30/2016 Contr's. Lab. Satisfactory
15R021 -104 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 7/30/2016 Jobsite Satisfactory
15R021 -105 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Satisfactory
15R021 -106 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Satisfactory
15R021 -107 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Satisfactory
15R021 -108 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Recommended for use
15R021 -109 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Recommended for use
15R021 -110 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 7/30/2016 P. Barcelona / D. Bacomo 8/1/2016 Contr's. Lab. Recommended for use
15R021 -111 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 8/2/2016 Jobsite Satisfactory
15R021 -112 Concrete Beam 428.22 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 7/20/2016 P. Barcelona / D. Bacomo 8/3/2016 DPWH Lab. Satisfactory
15R021 -113 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/3/2016 Contr's. Lab. Satisfactory
15R021 -114 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/3/2016 Contr's. Lab. Satisfactory
15R021 -115 Agg. Sub-Base Course 300 m³ Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Satisfactory
15R021 -116 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Satisfactory
15R021 -117 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Satisfactory
15R021 -118 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Recommended for use
15R021 -119 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Recommended for use
15R021 -120 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/3/2016 P. Barcelona / D. Bacomo 8/4/2016 Contr's. Lab. Recommended for use
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
SUMMARY REPORT OF FIELD TEST PERFORMED FOR
THE MONTH OF September 2016
Name of Project and Location : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road along Bacolod North Road Calatrava & Escalante City, Negros Occidental K0092+069 - K0127+759 (15R00021)
Implementing Office : DPWH -Neg. Occ. 1st. Dist. Eng'g. Office Name of Contractor : Alfies Const. & Const. Supply, Inc.
Project Duration : 271 C.D. DPWH Project Inspector :
a) Date started : March 15, 2016 Project Accomplishment : 31.25 %
b) Target Completion Date : Project Cost : ₱ 92,181.025.77
SAMPLED TESTED
LAB NO. KIND OF MATERIALS QUANTITY ORIGINAL SOURCE OF KIND OF TEST At REMARKS
REPRESENTED MATERIALS SPECS ITEM NO. BY DATE BY DATE
15R021 -121 Agg. Sub-Base Course Sicaba River FDT 200 (1) P. Barcelona / D. Bacomo 8/5/2016 Jobsite Satisfactory
15R021 -122 Agg. Sub-Base Course Quality Test Sicaba River G/P 200 (1) P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Satisfactory
15R021 -123 Agg. Sub-Base Course Quality Test Sicaba River AL 200 (1) P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 DPWH Lab. Satisfactory
15R021 -124 Portland Cement 1,000 bags Jobsite FT 200 (1) P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Satisfactory
15R021 -125 Portland Cement 1,000 bags Jobsite FT 311 (1)f1 P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Satisfactory
15R021 -126 Fine Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Recommended for use
15R021 -127 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Recommended for use
15R021 -128 Coarse Aggregate 75 m³ Malogo River G 311 (1)f1 P. Barcelona / D. Bacomo 8/5/2016 P. Barcelona / D. Bacomo 8/6/2016 Contr's. Lab. Recommended for use
15R021 -129 Concrete Beam 444.69 m² Jobsite FLEX. 311 (1)f1 P. Barcelona / D. Bacomo 7/26/2019 P. Barcelona / D. Bacomo 8/9/2016 DPWH Lab. Satisfactory
Note: 1. Indicate the name of batching plant as source of ready-mix concrete and hot-bituminous mix original source of materials
2. Indicate the name of testing laboratories on the tested
PREPARED BY: CHECKED BY: ATTESTED BY: RECOMMENDED FOR APPROVAL: APPROVED:
PETE LESTER D. BARCELONA GENO S. VITO EVANGELINE N. LIMOS REMELY B. MAGHANOY LEA N. DELFINADO, CESO IV
Materials Engineer -Alfies Cons't. & Cons't. Supply, Inc. Materials Engineer -DPWH Project Engineer -DPWH OIC -Chief, Quality Assurance and Hydrology Division OIC -Regional Director
QUALITY CONTROL PROGRAM
NAME OF PROJECT : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Roads along Bacolod North Road, Calatrava & Escalante Section
K0092+069 - K0128+759 (15R00021)
CONTRACTOR : Alfies Const. & Const. Supply LIMITS :
LOCATION : Calatrava & Escalante City, Neg. Occ. COST : ₱ 92,181,025.77 SOURCE : GAA 2016
PAVT. PAVT.
LENGTH : 2.85 Km. WIDTH : 7.32 m. THICKNESS : 0.30 m.
EFFECTIVITY DURATION
DATE : March 15, 2016 (C.D.) : 271
DATE :
A. TESTS TO BE PERFORMED
APROVED:
NAME OF PROJECT : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Roads along Bacolod North Road, Calatrava & Escalante Section
K0092+069 - K0128+759 (15R00021)
CONTRACTOR : Alfies Const. & Const. Supply LIMITS :
LOCATION : Calatrava & Escalante City, Neg. Occ. COST : ₱ 92,181,025.77 SOURCE : GAA 2016
PAVT. PAVT.
LENGTH : 2.85 Km. WIDTH : 7.32 m. THICKNESS : 0.30 m.
EFFECTIVITY DURATION
DATE : March 15, 2016 (C.D.) : 271
DATE :
A. TESTS TO BE PERFORMED
APROVED:
NAME OF PROJECT : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Roads along Bacolod North Road, Calatrava & Escalante Section
K0092+069 - K0128+759 (15R00021)
CONTRACTOR : Alfies Const. & Const. Supply LIMITS :
LOCATION : Calatrava & Escalante City, Neg. Occ. COST : ₱ 92,181,025.77 SOURCE : GAA 2016
PAVT. PAVT.
LENGTH : 2.85 Km. WIDTH : 7.32 m. THICKNESS : 0.30 m.
EFFECTIVITY DURATION
DATE : March 15, 2016 (C.D.) : 271
DATE :
A. TESTS TO BE PERFORMED
NORMITA A. NOBLE
Engineer III
STATUS OF TEST
Name of Project : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Roads along Bacolod North Road, Calatrava & For the Period Ending: Sept. 22, 2016
Escalante Section K0092+069 - K0128+759 (15R00021)
A.1.1 (8) Provision of Field Office for the Engineers (Rental Basis) 1.00 month I.R. I.R.
101 (3)b Removal of Actual Structures / Obstruction, ACP 12,505.00 m² I.R. I.R.
101 (3)a Removal of Actual Structures / Obstruction, PCCP 5,798.27 m² I.R. None
102 (2) Surplus Common Excavation 4,540.63 m³ I.R. I.R.
103 (1)a Structure Excavation (Common Soil) 1,515.93 m³ I.R. None
104 (1)a Embankment (Roadway Excavation) 1,087.94 m³ Q -1 ; FDT -16 Q -1 FDT -16
105 (1)b Sub-Grade Preparation (Exist. Pavement) 29,447.09 m² Q -1 ; FDT -59 Q - 1 ; FDT -40 FDT -19
200 (1) Aggregate Sub-Base Course 8,178.83 m³ Q -6 ; CBR -4 Q -4 ; CBR -3 Q -2 ; CBR -1
G/P -28 ; FDT -129 G/P -20 ; FDT -50 G/P -8 ; FDT -79
300 (3) Crushed Aggregate Surface Course 1,371.77 m³ Q -1 ; G/P -5 ; FDT -19 None Same as Req'd.
311 (1)f1 PCC Pavement (Unreinforced) 300mm thk. 14 days 21,479.32 m² DM w/ TM DM w/ TM
a. Reinforcing Steel Bar 11,813.63 kgs. Q -3 (U.W) Q -3 (U.W) None
b. Fine Aggregates 3,545 m³ Q -3 ; G -48 Q -1 ; G -18 Q -2 ; G -30
c. Coarse Aggregates 6,444 m³ Q -5 ; G -86 Q -2 ; G -33 Q -3 ; G -53
d. Portland Cement 61,217 bags Q -31 ; FT -307 Q -13 ; FT -130 Q -18 ; FT -177
e. Concrete 6,443.80 m³ 1 Set of 3 Beam Sample/ Flex. -27
day of Pouring
f. Completed Pavement 21,479.32 m² Thickness Determination
5 holes / km / lane
505 (5) Grouted Riprap (Class A) 1,033.73 m³
a. Cement 3,102 bags Q -2 ; FT -16 None Q -2 ; FT -6
b. Sand 259 m³ G -4 None G -4
c. Gravel Fill 16 m³ I.R. None I.R
d. Boulders 1,086 m³ U.W -4 None U.W -4
506 (1) Stone Masonry 127.90 m³
a. Cement 704 bags Q -1 ; FT -4 None Q -1 ; FT -4
b. Sand 39 m³ G -1 None G -1
c. Gravel Fill 3 m³ I.R. None I.R.
d. Boulders 135 m³ U.W -1 None U.W -1
603 (3)a Metal Guardrail (Metal Beam) Including Post 1,702.00 l.m. Q None
612 (1) Reflectorized Thermoplastic Pavement Markings White 713.35 m² Q None
B.9 Mobilization & Demobilization 1.00 L.s. I.R. I.R.
B.8 Traffic Management 9.03 months I.R. I.R.
B.5 Project Billboard / Signboard 3.00 each I.R. I.R.
B.7 Occupational Safety & Health Program 9.03 months I.R. I.R.
A.1.2(1) Provision of 4x4 Pick up type service for the Engineers 1.00 each I.R.
NORMITA A. NOBLE
Engineer III
STATUS OF TEST
Name of Project : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Roads along Bacolod North Road, Calatrava & For the Period Ending: Sept. 22, 2016
Escalante Section K0092+069 - K0128+759 (15R00021)
Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Roads along Bacolod North Road, Calatrava &
PROJECT : Escalante Section K0092+069 - K0128+759 (15R00021)
CONTRACTOR : Alfies Const. & Const. Supply, Inc. DATE: September 1, 2016
We hereby certify that we have conducted an inspection and verification on work accomplished on the
aforementioned project for the period August 23 - 31, 2016 ; We further certify that we have found out that the
quality of materials in the following items of work corresponding to the quantity accomplished conforms with the
approved POW Standard Specifications and Special provisions of the contract, viz.:
A -1.1(8) Provision of Field Office for the Engineer (Rental Basis) 1.00 month 3.00 33 %
101 (3)b Removal of Actual Structures / Obstruction, ACP 12,505.00 m² 11,522.90 92 %
101 (3)a Removal of Actual Structures / Obstruction, PCCP 5,798.27 m²
102 (2) Surplus Common Excavation 4,540.63 m³ 2,677.86 59 %
103 (1)a Structure Excavation (Common Soil) 1,515.93 m³
104 (1)a Embankment (Roadway Excavation) 1,087.94 m³ 158.87 15 %
105 (1)b Sub-Grade Preparation (Exist. Pavement) 29,447.09 m² 19,494.48 66 %
200 (1) Aggregate Sub-Base Course 8,178.83 m³ 178.00 5,635.98 69 %
300 (3) Crushed Aggregate Surface Course 1,371.77 m³
311 (1)f1 PCC Pavement (Unreinforced) 300mm thk. 21,479.32 m² 7,032.69 33 %
505 (5) Grouted Riprap (Class A) 1,033.73 m³
506 (1) Stone Masonry 127.90 m³
603 (3)a Metal Guardrail (Metal Beam) Including Post 1,702.00 l.m.
612 (1) Reflectorized Thermoplastic Pavement Markings White 713.35 m²
B.9 Mobilization & Demobilization 1.00 L.s. 0.35 35 %
B.8 Traffic Management 9.03 months 3.00 33 %
B.5 Project Billboard / Signboard 3.00 each 3.00 100 %
B.7 Occupational Safety & Health Program 9.03 months 3.00 33 %
A.1.2 (1) Provision of 4x4 Pick up type service for the Engineers 1.00 each
Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Roads along Bacolod North Road, Calatrava &
PROJECT : Escalante Section K0092+069 - K0128+759 (15R00021)
CONTRACTOR : Alfies Const. & Const. Supply, Inc. DATE: September 8, 2016
We hereby certify that we have conducted an inspection and verification on work accomplished on the
aforementioned project for the period September 1 - 7, 2016 ; We further certify that we have found out that the
quality of materials in the following items of work corresponding to the quantity accomplished conforms with the
approved POW Standard Specifications and Special provisions of the contract, viz.:
A -1.1(8) Provision of Field Office for the Engineer (Rental Basis) 1.00 month 3.00 33 %
101 (3)b Removal of Actual Structures / Obstruction, ACP 12,505.00 m² 11,522.90 92 %
101 (3)a Removal of Actual Structures / Obstruction, PCCP 5,798.27 m²
102 (2) Surplus Common Excavation 4,540.63 m³ 2,677.86 59 %
103 (1)a Structure Excavation (Common Soil) 1,515.93 m³
104 (1)a Embankment (Roadway Excavation) 1,087.94 m³ 158.87 15 %
105 (1)b Sub-Grade Preparation (Exist. Pavement) 29,447.09 m² 19,494.48 66 %
200 (1) Aggregate Sub-Base Course 8,178.83 m³ 5,635.98 69 %
300 (3) Crushed Aggregate Surface Course 1,371.77 m³
311 (1)f1 PCC Pavement (Unreinforced) 300mm thk. 21,479.32 m² 7,032.69 33 %
505 (5) Grouted Riprap (Class A) 1,033.73 m³
506 (1) Stone Masonry 127.90 m³
603 (3)a Metal Guardrail (Metal Beam) Including Post 1,702.00 l.m.
612 (1) Reflectorized Thermoplastic Pavement Markings White 713.35 m²
B.9 Mobilization & Demobilization 1.00 L.s. 0.10 0.45 45 %
B.8 Traffic Management 9.03 months 1.00 4.00 44 %
B.5 Project Billboard / Signboard 3.00 each 3.00 100 %
B.7 Occupational Safety & Health Program 9.03 months 1.00 4.00 44 %
A.1.2 (1) Provision of 4x4 Pick up type service for the Engineers 1.00 each
Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Roads along Bacolod North Road, Calatrava &
PROJECT : Escalante Section K0092+069 - K0128+759 (15R00021)
CONTRACTOR : Alfies Const. & Const. Supply, Inc. DATE: September 16, 2016
We hereby certify that we have conducted an inspection and verification on work accomplished on the
aforementioned project for the period September 8 - 15, 2016 ; We further certify that we have found out that
the quality of materials in the following items of work corresponding to the quantity accomplished conforms with
the approved POW Standard Specifications and Special provisions of the contract, viz.:
A -1.1(8) Provision of Field Office for the Engineer (Rental Basis) 1.00 month 4.00 44 %
101 (3)b Removal of Actual Structures / Obstruction, ACP 12,505.00 m² 11,522.90 92 %
101 (3)a Removal of Actual Structures / Obstruction, PCCP 5,798.27 m²
102 (2) Surplus Common Excavation 4,540.63 m³ 2,677.86 59 %
103 (1)a Structure Excavation (Common Soil) 1,515.93 m³
104 (1)a Embankment (Roadway Excavation) 1,087.94 m³ 158.87 15 %
105 (1)b Sub-Grade Preparation (Exist. Pavement) 29,447.09 m² 19,494.48 66 %
200 (1) Aggregate Sub-Base Course 8,178.83 m³ 194.00 5,829.98 71 %
300 (3) Crushed Aggregate Surface Course 1,371.77 m³
311 (1)f1 PCC Pavement (Unreinforced) 300mm thk. 21,479.32 m² 7,032.69 33 %
505 (5) Grouted Riprap (Class A) 1,033.73 m³
506 (1) Stone Masonry 127.90 m³
603 (3)a Metal Guardrail (Metal Beam) Including Post 1,702.00 l.m.
612 (1) Reflectorized Thermoplastic Pavement Markings White 713.35 m²
B.9 Mobilization & Demobilization 1.00 L.s. 0.45 45 %
B.8 Traffic Management 9.03 months 4.00 44 %
B.5 Project Billboard / Signboard 3.00 each 3.00 100 %
B.7 Occupational Safety & Health Program 9.03 months 4.00 44 %
A.1.2 (1) Provision of 4x4 Pick up type service for the Engineers 1.00 each
Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Roads along Bacolod North Road, Calatrava &
PROJECT : Escalante Section K0092+069 - K0128+759 (15R00021)
CONTRACTOR : Alfies Const. & Const. Supply, Inc. DATE: September 23, 2016
We hereby certify that we have conducted an inspection and verification on work accomplished on the
aforementioned project for the period September 16 - 22, 2016 ; We further certify that we have found out that
the quality of materials in the following items of work corresponding to the quantity accomplished conforms with
the approved POW Standard Specifications and Special provisions of the contract, viz.:
A -1.1(8) Provision of Field Office for the Engineer (Rental Basis) 1.00 month 4.00 44 %
101 (3)b Removal of Actual Structures / Obstruction, ACP 12,505.00 m² 11,522.90 92 %
101 (3)a Removal of Actual Structures / Obstruction, PCCP 5,798.27 m²
102 (2) Surplus Common Excavation 4,540.63 m³ 2,677.86 59 %
103 (1)a Structure Excavation (Common Soil) 1,515.93 m³
104 (1)a Embankment (Roadway Excavation) 1,087.94 m³ 158.87 15 %
105 (1)b Sub-Grade Preparation (Exist. Pavement) 29,447.09 m² 19,494.48 66 %
200 (1) Aggregate Sub-Base Course 8,178.83 m³ 5,829.98 71 %
300 (3) Crushed Aggregate Surface Course 1,371.77 m³
311 (1)f1 PCC Pavement (Unreinforced) 300mm thk. 21,479.32 m² 7,032.69 33 %
505 (5) Grouted Riprap (Class A) 1,033.73 m³
506 (1) Stone Masonry 127.90 m³
603 (3)a Metal Guardrail (Metal Beam) Including Post 1,702.00 l.m.
612 (1) Reflectorized Thermoplastic Pavement Markings White 713.35 m²
B.9 Mobilization & Demobilization 1.00 L.s. 0.45 45 %
B.8 Traffic Management 9.03 months 4.00 44 %
B.5 Project Billboard / Signboard 3.00 each 3.00 100 %
B.7 Occupational Safety & Health Program 9.03 months 4.00 44 %
A.1.2 (1) Provision of 4x4 Pick up type service for the Engineers 1.00 each
Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Roads along Bacolod North Road, Calatrava &
PROJECT : Escalante Section K0092+069 - K0128+759 (15R00021)
CONTRACTOR : Alfies Const. & Const. Supply, Inc.
We hereby certify that we have conducted an inspection and verification on work accomplished on the aforementioned
project for the period April 8 - 15, 2015 ; We further certify that we have found out that the quality of materials in the
following items of work corresponding to the quantity accomplished conforms with the approved POW Standard
Specifications and Special provisions of the contract, viz.:
BILL NO. :
DATE : July 14, 2016
ALFIES CONST. & CONST. SUPPLY, INC.
(Name of Contractor/Supplier)
Bacolod City
(Address)
Note:
Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Road
along Bacolod North Road K0074+848 - K0075+007; K0087+000 -
K0087+540; K0091+270 - K0091+537, Sagay City, Neg. Occ.
(15R0016)
ARNEL P. TORREFRANCA
Engineer III
APPROVED:
INSPECTION REPORT
Name of Project : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Roads along Bacolod North Road, Calatrava & Escalante Section
K0092+069 - K0128+759 (15R00021)
QUANTITY
ITEM NO. DESCRIPTION REMARKS
Planned Actual
101 (3)b Removal of Actual Structure / Obstruction, ACP 12,505.00 m² 11,522.90 m² The indicated item of works have
been accomplished in accordance
with the plans, specifications and
102 (2) Surplus Common Excavation 4,540 m³ 2,677.86 m³ program of works.
Inspected by:
EVANGELINE N. LIMOS
Project Engineer-DPWH Neg. Occ. 1st Eng'g. Dist.
INSPECTION REPORT
Name of Project : Rehab. / Recons't. / Upgrading of Damaged Paved Nat'l. Roads along Bacolod North Road, Calatrava & Escalante Section
K0092+069 - K0128+759 (15R00021)
QUANTITY
ITEM NO. DESCRIPTION REMARKS
Planned Actual
A.1.1 (8) Provision of Field Office for the Engineers 9.03 month 4.00 month The indicated item of works have
(Rental Basis) been accomplished in accordance
with the plans, specifications and
program of works.
B.9 Mobilization / Demobilization 1.00 L.s. 0.50 L.s.
B.7 Occupational Safety & Health Program 9.03 month 4.00 month
Inspected by:
EVANGELINE N. LIMOS
Project Engineer-DPWH Neg. Occ. 1st Eng'g. Dist.