QP - NPD - 07 Procedure For Change Management
QP - NPD - 07 Procedure For Change Management
QP - NPD - 07 Procedure For Change Management
QP/NPD/07
Issue No. 01
INTEGRATED SYSTEM Revision Date 05.07.2019
PROCEDURES Page 1 of 3
CHANGE MANAGEMENT
2. Scope: This process covers all activities for new product/ Current Production Run.
5. Procedure:
5.1 Change Inputs are raised by customer through new drawing release/Emails NPD Engg. &
Received from customer. Review should be completed within 10 working R&D Head
days of receipt of notification of Engineering standards/specifications
changes.
5.3 The Changes are Incorporated in the relevant Documents as per the
procedure for product and process changes. NPD Head F/NPD/037
5.4 During the development change History Sheet is uploaded along with the
changed document. NPD Head F/ NPD /14
5.5 Once the product is in the regular production the Changes are incorporated NPD Head F/ NPD /15
through ECR and ECN. F/ NPD /16
Prepared By Approved By
Doc. No. QP/NPD/07
Issue No. 01
INTEGRATED SYSTEM Revision Date 05.07.2019
PROCEDURES Page 2 of 3
CHANGE MANAGEMENT
Customer
In case a Customer Specifies, the approval on the changes is obtained from
5.7 NPD Head approved
the customer before introducing the change in the product.
documents
F/ NPD/16
The date on which changes is implemented is recorded on the ECN & ECN
5.8 NPD Head F/NPD/16A
list Summary sheet to be updated and ECN communicated to concerned
F/NPD/40
personnel.
5.9 Any Change required from the supplier end should be communicated to NPD Head F/NPD/16
concern supplier & same is communicated to customer Purchase Head
5.11 During New Product development any change required updated the timing NPD Head
plan as per changes
5.12 Changes in Man, Machine, Method, and Material are applicable whenever F/NPD/037
any customer demand/Customer Complaints /Location Change NPD Head
/improvement project to increase productivity/quality improvement/Alternate
Supplier Introduced. Any Machine change /Material Change/or Process
(Method Change)/Mistake proofing implementation etc.
5.13 Information has to be given to customer in case of any deviations in product Head Marketing Deviation Form
& process or any changes and If there is any impact on Fit, Form and F/SYS/25 or
Function of Product including performance and/or durability of the product or Customer
whenever customer demands or in-house changes/requirement. approved
Deviated Product or material identified with job card & deviation form documents,
attached till dispatch. Job Card
’F/PRD/01”
NPD Head F/NPD/18
5.14 Process Validation is required in case of any Change or Location Change. Head- F/NPD/18A
Process validation & process capability required at the time of machine Production F/NPD/18B
installation or process change. F/NPD/18C,
F/NPD/019,
F/NPD/12,12A
F/QCD/20
Prepared By Approved By
Doc. No. QP/NPD/07
Issue No. 01
INTEGRATED SYSTEM Revision Date 05.07.2019
PROCEDURES Page 3 of 3
CHANGE MANAGEMENT
5.15 All Key documents like PFMEA/CP/PFD Sample Inspection Report need to NPD Head F/NPD/26,
submit to customer (If Customer demand) F/NPD/27,
F/NPD/28
5.16 Re-PPAP submission is required if customer ask for it or retain all NPD Head
documents at MASU
5.17 After change a “Change Management check sheet “to be filled to covered all NPD Head F/NPD/037
requirements
5.18 Any Change required from the supplier end should be communicated to NPD Head F/NPD/036
concern supplier & same is communicated to customer. /Purchase Head
7. References
Prepared By Approved By