Annexure B': (Scope of Work & Specifications)
Annexure B': (Scope of Work & Specifications)
Annexure B': (Scope of Work & Specifications)
Item Remarks
Description
Excavation
Earth work excavation Upto required
depth and levels as per the design,
drawing and as per the site condition in all
kind of soils and earth mixed with fair
sized boulders, hard morum either
manually or by using machinery and in all
conditions such as dry, wet, slurry etc.,
disposal and depositing the excavated
soil in the premises or disposing it outside
as directed.(Note: The work is including of
site leveling clearing the bushes, dressing
after the excavation and ramming for
surface ready for laying of PCC.
Anti Termite treatment to be
Earth filling up to floor levels as per the
PLINTH FILLING done before carrying out
drawing in inside the plinth of the building
any filling activities.
with good morum soils. Compaction of the
earth with water and vibrating plate
compactor. Filling and compaction upto
proposed floor level depending upon the
levels of site and road (Consolidation &
Compaction shall be done as per IS
standards).
R.C.C. framed structure on footings over MAKE:
FOUNDATION &
hard strata by using reinforced steel and
STRUCTURE STEEL :
cement of reputed make, including
RADHA/JAYRAJ/DHANALAK
placing the electrical conduiting, as per SHMI
Structural Engineers design. This
includes PCC, Shuttering, Supply of steel, CEMENT
Bar bending, Installation, supply and :
laying of concrete including curing. ULTRATECH/BIRLA/PENN
A
Sand and Metal will be used of the best
quality. Design mix report to be submitted ELECTRICAL CONDUITING
before first concrete casting for client :
approval. Reports of strength of concrete FINOLEX/SUDHAKAR
will also be submitted after 28 days of
casting for all slabs. Makes and brand of the
materials shall be as per
Consultant /Client approval
1
Make and technical
BRICKWORK EXTERNAL :
specifications such as
Brick Masonry with 200mm thick NCL strength, sound absorption
make AAC blocks. levels of the block should
be approved by
INTERNAL : Consultants / Client
Brick Masonry with 115 mm thick Red
clay bricks.(Note: including all kind of
RCC like CC beds, hole fasteners, lintels
and chajjas etc.,)
PLUMBING
All fittings, plumbing lines and sewage
pipelines as per Architect’s design shall
be as follows :
NOTE
All low side Electrical and complete
plumbing works including all type
of chambers, collecting pits and
rain water recharge pits
construction are in the scope of
the Contractor.
Highside works such as Transformer,
connection charges are in Client
scope.
All Pipes to be concealed and fixed
properly, wherever specified and
required by Client / Consultant/
Architects
The rain water from the terrace & open
RAIN WATER
areas will be collected through rain water
DISPOSAL
pipes, which will be discharged into the
rain water harvesting pits to recharge the
underground water.
WATER SUMP
to be constructed beneath the ground as
AND SEPTIC TANK
per the drawings and location given by
the architect.
DRAINAGE
SWR Pipes from the septic tank to the
drain shall be installed, taking levels of
drain into consideration, at sites where
drain is available.