Rencana Kerja Instrument Libur Lebaran 2022

Tanggal
No Deskripsi Pekerjaan Personil Sparepart
###28 29 30 1 2 3 4
1 Setting controller untuk capasity of 2nd generator Sydiq, Riki
Bambang, Sydiq, thermocouple type K; transmitter STG
2 Instalasi thermocouple dan Pressure Transitter PTRS
Riki 700; kabel NYY 2x1,5mm
3 Cleaning Computer DCS Suroyo
4 Back up data Server dan PC DCS L Suroyo
I thermis 1x6A; box thermis; rel thermis;
5 Pasang thermis untuk PC DCS B Suroyo, Riki terminal isi 3; wire deck 45x45mm;
U kabel NYY 2x1,5mm
6 Ganti thermowell boiler 01 R Bambang, Sydiq thermowell wear
7 Pindah controller desuperheater ekstraksi turbin All personil
8 Pasang inverter pompa demin Bambang, Sydiq,
Riki inverter ACS580
9 Persiapan start boiler dan turbin All personil

Dibuat Oleh, Disetujui Oleh, Mengetahui,

Feni Fitriani Supriyono Erwin Rahardianto,


Ka. Sie Instrument Ka. Bag Instrument Ast. Manager PP
Keterangan Sparepart

No Sparepart Jumlah Status Sparepart


1 Thermocouple type K 1 pcs Ready
2 Transmitter STG 700 1 pcs Ready
3 Kabel NYY 2x1,5mm 100 m Ready
4 Thermis 1x6A 10 pcs Ready
5 Box thermis 1 phase 10 pcs Not Yet
6 Rel thermis 10 btg Not Yet
7 Terminal isi 3 10 pcs Not Yet
8 Wire deck 45x45mm; 10 btg Not Yet
9 Thermowell wear 6 pcs Ready
10 Inverter ACS580 1 pcs Ready