Professional Documents
Culture Documents
Answers To PMP Question Set - 4
Answers To PMP Question Set - 4
TO
PMI-PMP® QUESTION SET – 4
Answers
17. c. The path CDHR has duration of nine days. Hence H can be delayed by four days before
the next event can begin.
18. d. Job security, salary, clean and safe working conditions are examples of hygiene factors.
Appreciation at work is not a hygiene factor, but instead a motivating factor.
19. b. Physiological factors appear at the lowest level of Maslow's hierarchy triangle.
20. a. The other three options are examples of benefit measurement method.
21. d. Dynamic Programming is an example of Constrained Optimization method. Murder
board is an example of benefit measurement method.
22. c. Murder board is a process where a committee asks questions from project
representatives as part of the project selection process.
23. c. Control Scope process is part of scope management knowledge area.
24. a. WBS dictionary is the best option. WBS Dictionary identifies all the components used in
the WBS
25. d. Scope Validation is the process of the customer accepting the project deliverables.
26. d. Mean for PERT is defined as (P+4M+O)/6 which comes out to be 16 days.
27. b. Control Procurements is a process in the Project Procurement Management Knowledge
area.
28. c. In oligopoly, the action of one seller has an impact on other sellers, as there are very few
sellers.
29. b. Each year $200 gets removed from the value of computer. After three years the value
becomes $400.
30. c. The others are true statements about analogous estimating.
31. d. Learning curve estimation uses the principal that the cost per unit will decrease as more
units of work are manufactured.
32. a. The behavior described is an illustration of Halo's effect.
33. c. Close Procurements and Close Project or phase are the two closure processes.
34. d. The Configuration (or Change) Control Board has the authority to approve or deny
change requests.
35. b. Cost baseline includes the project budget for each month.
36. a. WBS should focus on deliverables.
37. d. WBS is an output of the Create WBS.
38. b. Project Manager is identified as part of the Develop Project Charter process.
39. d. Mandatory dependency represents dependencies due to nature of work.
Sujoy Dutta, PMP http://www.sujoydutta.in 3
Answers to PMP Question Set – 4 Page 4 of 5
65. b. The other two are conditions that indicate the process is out of control.
66. c. Statistical Sampling is the standard technique that is used to test only a small sample of
products instead of all the products manufactured.
67. d. This is the only correct statement.
68. a. Contract Closeout is performed before administrative Closeout
69. c. Risk Register is the only output of the Risk identification process.
70. b. A numeric value is assigned to risks impact and probability during the Quantitative Risk
Analysis process.
71. C - This is an ethics question dressed up as a stakeholder management question. What
happens next is an impact assessment. Under the mandatory Responsibility section: "We
inform ourselves and uphold the policies, rules, regulations and laws that govern our
work..."
72. C - Expert judgment is not a tool and technique of Mange Stakeholder Engagement.
PMBOK® Guide, 5th edition, p. 398
73. d. Cleaning the building is a repetitive task that is done everyday. Hence it is not an
example of a project.
74. B – This exactly describes the Salience model. PMBOK® Guide, 5th edition, p. 396
75. A - stakeholder management is about the creation and maintenance of relationships
between the project team and stakeholders. Under specific circumstances, answers B and
C may be partially or. Answer D is incorrect: what is created as the stakeholder
management plan, not the stakeholder management strategy. PMBOK® Guide, 5th edition,
p. 400