Professional Documents
Culture Documents
Assignment 4 Problems 2022
Assignment 4 Problems 2022
Assignment 4 Problems 2022
Q.1 (5 Marks) For solving the monte-Carlo simulation, some background of the probability
theory is needed. All the necessary concepts and associated methods also have been discussed in the
reading attached.
To-Do –
(a) You have to solve Example 19.8 and example 19.9 (which are essentially the same problems
but one is presenting a solution by hand and the other presenting a solution by spreadsheet).
(b) You also have to comment in the differences in the answer you obtain in 19.8 and 19.9.
(c) Repeat the calculation in 19.9, for 100 samples, for 1000 samples, and 10,000 samples
(instead of 30 in the original solved example) and provide a comparison of the results obtained (a).
Include the spreadsheet as part of your submission.
To do differently from the steps followed in the reading –
(a) The Table 19-5 in the solved example, shows only the first 5 values. Your solution should show all 30
values.
(b) Use the following table of random numbers instead of the one shown in the Reading. Clearly define
your rule of selecting 30 random numbers. The probability of two students having the same rule is very
low in this case.
Figure 19-11 (Refer to the reading) need not be drawn again in your submission, and the graphs can be
read when applicable. Solution by hand does not mean that the answers cannot be typed using a computer.
Question 2 - (2marks) Rohit has an estimate of the cash inflows after taxes (CFAT) for a
proposed project, whose expected life is 2 years, are shown in the given decision tree. As
shown, the initial investment needed for the project is INR 1,20,000. The cash inflows are
shown on arrows and the associated probabilities are shown inside the circles. Assuming that
there is no correlation between the cash inflows of two years, and, that the annual interest rate
is 10%, the expected net present value of the proposed project is ___________?. Show detailed
analysis steps.
Question 3 (3 Marks) Answer the question on the basis of the cash flow diagram given below.
Show detailed steps in your solution.
Question 5 - (3marks) A creek situated near the thermal station receives wastes daily. When
the creek is full, it is necessary to remove the waste to a dumpyard which is located 8.2
kilometers from the thermal station. Currently, when the creek is full, the waste is removed by
pump into a tank truck and hauled away. This process requires the use of a portable pump that
initially costs $800 and has an 8-year life. The company pays a contract individual to operate
the pump and oversee environmental and safety factors at a rate of $100 per day, plus the truck
and driver must be rented for $200 per day. The company has the option to install a pump and
pipeline to the remote site. The pump would have an initial cost of $1600 and a life of 10 years
and will cost $3 per day to operate. The company’s MARR is 10% per year.
(a) If the pipeline will cost $12 per meter to construct and will have a 10-year life, how many
days per year must the waste in the creek require pumping to justify construction of the
pipeline?
(b) If the company expects to pump the waste in the creek once per week every week of the
year, how much money can it afford to spend now on the 10-year life pipeline to just break
even?
Question 6 - (2marks) Anushka can select from two manufacturing systems for manufacturing
high-end DI pipes . Auto system Hybrid system
( a ) Use an AW relation to determine the minimum number of hours per year to operate the
pumps that will justify the Hybrid system, if the MARR is 10% per year.
( b ) Which system is economically better if it operates 7 hours per day, 365 days per year?
Question 8 - (1marks) A European manufacturing company has new equipment with a first cost
of 12,000 euros, an estimated salvage value of 2000 euros, and a recovery period of 8 years.
Use the Sum-of-Years-Digits Depreciation method to tabulate annual depreciation and book
value.