Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

PERT/CPM

Variability in the Project Completion Date


• In doing Critical Path calculations, estimated activity
times are not certain.
• What is the effect of these uncertainties on calculated
project completion date?
Critical Path determines this date
Critical Path is a sequence of activities
Variation in Critical Path activities can cause variation in the
completion date
Variation in non-Critical Path activities will not usually cause
variation in the completion date
But… if variation along a non-Critical Path uses all of the slack
time, this path may become Critical
But if… if variation along the Critical Path results in an earlier
completion date, a non-Critical Path may become Critical.
3 Estimates for each Activity
Optimistic time ( a )
Everything progresses in an ideal manner
Most probable time ( m )
Most likely under normal conditions
Pessimistic time ( b )
Encounter breakdowns and/or delays

Expected time t
a 4m b
t
6
(a) (m) (b) Expected
Most Time
Activity Optimistic Probable Pessimistic (Weeks)
A 4 5 12 6
B 1 1.5 5 2
C 2 3 4 3
D 3 4 11 5
E 2 3 4 3
F 1.5 2 2.5 2
G 1.5 3 4.5 3
H 2.5 3.5 7.5 4
I 1.5 2 2.5 2
J 1 2 3 2
Expected time t
a 4m b
t
6
(1) (2) (3) (4) Case Study
Earliest Latest Earliest Latest
Activity Start Start Finish Finish
A 0 0 6 6
B 0 7 2 9
C 6 10 9 13
D 6 7 11 12
E 6 6 9 9
F 9 13 11 15
G 11 12 14 15
H 9 9 13 13
I 13 13 15 15
J 15 15 17 17
C F

A D G
J

B H I
(1) (2) (3) (4) (2) - (1) (4) - (3)
Earliest Latest Earliest Latest SLACK SLACK
Activity Start Start Finish Finish (LS - ES) (LF - EF)
A 0 0 6 6 0 0
B 0 7 2 9 7 7
C 6 10 9 13 4 4
D 6 7 11 12 1 1
E 6 6 9 9 0 0
F 9 13 11 15 4 4
G 11 12 14 15 1 1
H 9 9 13 13 0 0
I 13 13 15 15 0 0
J 15 15 17 17 0 0
C F

A D G
J

B H I
Project Duration
T stands for the project duration
The activities along the Critical Path are A – E – H – I – J
Expected
Time
Activity (Weeks) T t A tE tH tI tJ
A 6
B 2
C 3
D 5 T 6 3 4 2 2 17
E 3
F 2
G 3
H 4
I 2
J 2
Variance in Project Activities
2
b a
Variance of an activity time =
6
(a) (m) (b) Expected
Most Time Variance
2
Activity Optimistic Probable Pessimistic (Weeks) σ
A 4 5 12 6 1.78
B 1 1.5 5 2 0.44
C 2 3 4 3 0.11
D 3 4 11 5 1.78
E 2 3 4 3 0.11
F 1.5 2 2.5 2 0.03
G 1.5 3 4.5 3 0.25
H 2.5 3.5 7.5 4 0.69
I 1.5 2 2.5 2 0.03
J 1 2 3 2 0.11
Variance in Project Duration
2 2 2 2 2 2
A E H I J
2
1.78 A 0.11E 0.69 H 0.03I 0.11J 2.72
Variance
Activity σ2
A 1.78
B 0.44
Standard Deviation in Project Duration C 0.11
D 1.78
2.72 1.65
E 0.11
F 0.03
G 0.25
H 0.69
I 0.03
J 0.11
Final Assumption
The distribution of project completion time T is
Normally distributed.
The next step:
• Given the Expected Completion time (mean of the Normal)
• Given the Expected Standard Deviation in the Expected
Completion time (standard deviation of the Normal)
• Convert this Normal Curve to an equivalent Z-Normal Curve

17 This “says” that any time you want to know the


1.65 “what if” probability that another completion
time (x) might actually occur, it represents a
x
z random variable associated with this normal
distribution … and can be converted to an
equivalent z normal value…
What if… example
What is the probability that the project would be
completed in 20 weeks or less?
This would be an x = 20 from this normal distribution.
Convert the x to a z

17
1.65 This “says” that a completion time
x of 20 is 1.82 standard deviations
z above the mean (17).
x 17
z 1.82
1.65
Here is where we use the Table
Handout

Z table gives the area to x


the left, but only to the z
mean line.
You need to add in the x 17
0.50 to get the z 1.82
probability. 1.65

Z=0 Z = 1.82
µ = 17 x = 20
Steps
1. Develop list of activities
2. Draw the network
3. Estimate expected activity time and variance for each
activity
4. Use expected activity time estimates to determine
earliest start & finish and latest finish and start for each
activity
5. Use the project completion time as the finishing time
6. Compute the slack for each activity & identify the
Critical Path
7. Use the variability in the project completion date to
compute probabilities of meeting a specified date

You might also like