Professional Documents
Culture Documents
MIDTERM
MIDTERM
MIDTERM
NETWORK
A network consists of a set of nodes linked by arcs (or branches). The notation for
describing a network is (N, A), where N is the set of nodes, and A is the set of arcs. As an
illustration, the network in Figure 1 is described as:
N = {1, 2, 3, 4, 5}
A = { (1,2), (1,3), (2,3), (2,5), (3,4), (3,5), (4,2), (4,5)}
Figure 1 Figure 2
DYNAMIC PROGRAMMING
It determines the optimum solution of a multivariable problem by decomposing it into
stages, each stage comprising a single variable sub-problem. The advantage of the
decomposition is that the optimization process at each stage involves one variable only,
a simpler task computationally than dealing with all the variables simultaneously. ADP
model is basically a recursive equation linking the different stages of the problem in a
manner that guarantees that each stage's optimal feasible solution is also optimal and
feasible for the entire problem.
It can also be used to handle both probabilistic and deterministic problems. This
approach divides the problem into a number of sub-problems or stages. The decision we
make at each stage influences not only the next stage but also every stage to the end of
the problem.
RECURSIVES NATURE OF COMPUTATIONS IN DP
Computations in DP are done recursively, so that the optimum solution of one sub-
problem is used as an input to the next sub-problem. By the time the last sub-problem is
solved, the optimum solution for the entire problem is at hand. The manner in which
the recursive computations are carried out depends on how we decompose the original
problem. In particular, the sub-problems are normally linked by common constraints. As
we move from one sub-problem to the next, the feasibility of these common constraints
must be maintained.
PRINCIPLE OF OPTIMALITY
Future decisions for the remaining stages will constitute an optimal policy regardless of
the policy adopted in previous stages.
PROJECT NETWORKS
It is a network used to represent a project.
It consists of a number of nodes (typically shown as small circles or rectangles) and a
number of arcs (shown as arrows) that connect two different nodes.
There are three types of information needed to describe a project:
1. Activity information: Break down the project into its individual activities (at the
desired level of detail).
2. Precedence relationships: Identify the immediate predecessor(s) for each activity.
3. Time information: Estimate the duration of each activity.
CRITICAL PATH
A path through a project network is one of the routes following the arcs from the start
node to the finish node.
The length of a path is the sum of the (estimated) durations of the activities on the path.
The (estimated) project duration equals the length of the longest path through the
project network.
The longest path is called the critical path.
Note: If more than one path tie for the longest, they are all considered as critical paths.
SCHEDULING THE PERT/CPM PROJECT
The PERT/CPM scheduling procedure begins by addressing the question: When can the
individual activities start and finish (at the earliest) if no delays occur?
Having no delays means:
1. The actual duration of each activity turns out to be the same as its estimated
duration.
2. Each activity begins as soon as all its immediate predecessors are finished.
The starting and finishing times of each activity if no delays occur anywhere in the
project are called the earliest start time and the earliest finish time of the activity.
SCHEDULING THE PERT/CPM PROJECT
These times are represented by the symbols:
o ES = earliest start time for a particular activity
o EF = earliest finish time of a particular activity
o EF = ES + (estimated) duration of the activity
If an activity has only a single immediate predecessor, then:
o ES for the activity = EF for the immediate predecessor
If an activity has two or more immediate predecessors, then:
o ES for the activity = Largest EF of the immediate predecessors
SLACK
The slack for an activity is the difference between its latest finish time and its earliest
finish time.
In symbols,
o Slack = LF – EF
o Slack = LS - ES
EXAMPLE
EXAMPLE
Given the following distances between destination nodes, what is the minimum distance that
connects the nodes?
DECISION THEORY
1. A set of possible future conditions (states of nature) that will have a bearing on the results of
the decision.
2. A list of alternatives to choose from.
3. A known payoff for each alternative under each possible condition.
IMPORTANT TERMS
Alternative – a course of action or strategy that may be chosen by the decision maker.
State of nature – an occurrence or a situation over which the decision maker has little or no
control.
Payoff – the benefit which accrues from a given combination of decision alternative and state of
nature.
DECISION MAKING
The information for a decision is often summarized in a payoff table, which shows the expected
payoffs for each alternative under the various possible states of nature. These tables are helpful
in choosing among alternatives because they facilitate comparison of alternatives.
DECISION ENVIRONMENTS
Operations management decisions are classified according to the degree of certainty present.
There are three basic categories:
1. Decision making under Certainty – In this environment, only one state of nature exists,
there is complete certainty about the future. It means that all parameters such as costs,
capacity and demand have known values.
2. Decision making under Uncertainty – In this environment, more than one state of nature
exists, but the decision maker has no knowledge about the various states, not even
sufficient knowledge to permit the assignment of probabilities to the states of nature.
3. Decision making under Risk - In this environment, more than one state of nature exists,
but the decision maker has information which will support the assignment of
probabilities to the states of nature.
DECISION MAKING UNDER CERTAINTY
When it is known for certain which of the possible future conditions will actually
happen, the decision is usually relatively straightforward: Simply choose alternative that
has the best payoff under the state of nature.
DECISION TREE
Any problem that can be presented in a decision table can also be graphically
represented in a decision tree.
Decision trees are most beneficial when a sequence of decisions must be made.
All decision trees contain decision points and state-of-nature points.
EXAMPLES
1. A manager for a well drilling company must recommend whether to build a new facility,
expand his existing one, or do nothing. He estimates that long-run profits (in dollars) will vary
with the amount of precipitation (rainfall) as follows:
Low Normal High
Do Nothing -100 100 300
Expand 350 500 200
Build New 750 300 0
If he uses the maximax criterion, which alternative will he decide to select?
If he uses the laplace criterion, which alternative will he decide to select?
If he uses the maximin criterion, which alternative will he decide to select?
If he uses the minimax regret criterion, which alternative will he decide to select?
If he uses the Hurwicz criterion, which alternative will he decide to select using α = 0.8?
Solutions:
2. A student who has to decide whether to stop his studies and for a job paying P1,500 per
month or continue his studies, after which a job awaits him paying P2,500 per month provided
he passes his remaining subjects. He feels that he can pass his remaining subjects is 40%. Which
choice is better for the student and the expected value?
3. Two professors at a nearby university want to co-author a new textbook in either economics
or statistics. They feel that if they write an economics book, they have a 50% chance of placing
it with a major publisher, and it should ultimately sell about 40,000 copies. If they can’t get a
major publisher to take it, then they feel they have an 80% chance of placing it with a smaller
publisher, with ultimate sales of 30,000 copies. On the other hand, if they write a statistics
book, they feel they have a 40% chance of placing it with a major publisher, and it should result
in ultimate sales of about 50,000 copies. If they can’t get a major publisher to take it, they feel
they have a 50% chance of placing it with a smaller publisher, with ultimate sales of 35,000
copies. Construct the decision tree.