994 KPB1000 2020-S0 - Response To Notification of Area Handover Delay
994 KPB1000 2020-S0 - Response To Notification of Area Handover Delay
KILANG PERTAMINA
BALIKPAPAN
To
RDMP Balikpapan JO,
Project Manager EPC iSBL-OSBL
Attn. Mr. Yun Dong Kim
JO Office Menara Jamsostek Level 7
Jl. Gatot Subroto No. 33 Kav 71-73
Jakarta Selatan 12710, Indonesia
Dear Sir,
Owner acknowledges that in any professional contractual relationship it is essential that the
parties involved work together in a conciliatory manner to accomplish a satisfactory outcome.
Bearing this in mind, Owner confirms its willingness, as it has always done, to work with
Contractor to achieve a win/win situation that is fair and equitable to all.
However, clearly notwithstanding the numerous requests and instructions to do so. Contractor's
continuous failure to comply with the Contract by satisfactorily updating its "Control Schedule"
since August 2019 has been a major contributory factor influencing the failure to identify key
issues that have had a direct impact on area handovers.
Contractor's inability to mobilize its resources (plant, labour, equipment, supervisory staff and
temporary facilities) in accordance with the "Control Schedule" has not helped the situation,
resulting in Contractor being unable to address the work fronts available for handover due to
these issues. Moreover, it should be recognized that a lack / late issue of IFC information and IFC
information issued with extensive holds has seriously impeded the Contractor's ability to
undertake work in areas that are available.
Contractor has also not been able to identify beyond reasonable doubt or provide any significant
evidence to support its contentions of delay impact by Owner. This being largely due the failure of
Contractor to update the Control Schedule and the lack of Contractor definition under the
construction activities within the "Control Schedule" that was conditionally approved in August
2019.
Owner will not be drawn or comment on the conclusions reached by Contractor in its letter as to
do so at the present time will not be productive in moving forward to achieve a successful
outcome of the Project. Owner does, however, reserve the right to revisit and reconcile these
Issues under the provisions of the Contract and seek redress at the appropriate time where the
Contract allows for this.
In the meantime, Owner encourages Contractor to diligently proceed with fulfilling its contractual
obligations by bringing the Control Schedule to the appropriate level and working with all parties
involved in the spirit of mutual cooperation.
Development Director
CC:
CC: PMC Project Manager
1. President Director PT Kilang Pertamina Balikpapan
2. PMC Project Manager
Ref. No. : 26071-JO-KPB-LT-00253 Date: 01 July 2020
YourRef. No. : 286/KPB1000/2020-SO
Reply request: . i Yes • No
FT. Kilang Pertamina Balikpapan.
Jl. YosSudarso No.1
Balikpapan, Kalimantan Timur, Indonesia
With reference to the Owner's letter No. 286/KPB1000/2020-30, Contractor hereby responds as
follows.
In general. Owner's statements in the letter are not supported by precise evidence, rather it is a
groundless allegation based on prejudiced, and misleading records. For an objective
understanding of the circumstances, Contractor hereby refutes to Owner's statements point by
point as below.
• Point 1: Contractor has continuously informed Owner of specific areas being delayed or
expected to be delayed, and duly requested handover as listed in 1.1.2.C of attachment 1 of
the Contractor's letter No. 26071-JO-PMC-LT-01846 and Attachment 1 of this letter. Moreover,
Owner has been informed of such information during regular Area Handover meetings.
• Point 2: Contractor provided the updated Level 3 Schedule through 26071-JO-PMC-TR-
00300 dated 10 May 2019. within 90 days after the Contract Effective Date(27 February 2019)
under the Contract, and the Level 3 Schedule Rev.000 was approved by Owner through
Transmittal No. PMC-01-TRANSMIT-003675.
• Point 3~5: The engineering, procurement, and construction Work of the Project shall be
carried out simultaneously, for the smooth execution of the Work. Thus, the performance of
construction Work based on the partial 'Hold' mark on Issue for Construction ("IFC") drawings,
is the essential part of Work for the completion of Project in accordance with Schedule of the
Project. Importantly, such Issuance of IFC drawing with 'Hold' enables Contractor to perform
Construction Work for un-Hold parts. Revisions of such drawings to develop the design and
to release 'Hold' are also the general process of the detail engineering work, thereby allow
Contractor's performance of the Construction Work with properly developed design
information. Hence, Owner's assertion that Contractor has issued drawings with 'Hold' for
cash flow Is groundless, and is misleading in such circumstances.
As shown in Hold status of Stone Column("S/C") drawing (Attachment 3), the quantity of
available S/C drawing without hold for construction of each ISBL and OSBL is 126,135 m^
and 75,928 m' respectively, which is 72% and 97% of the total quantity. Based upon the above
Actual records, the figure of 40% S/C's IFC drawing with hold stated by Owner is not correct
data, since the portion of S/C drawing with hold is 28% for ISBL and 3% for OSBL in the total
quantity of the drawing.
Additionallly, the part of design Hold of S/C drawing is originated from Owner EOT Risk events
addressed in the below response to Point 9-11.
Point 6-8: The background of the circumstances is that Owner has continuously postponed
forecasting dates for Site handover and split the area through Area Handover Meetings from
16 September 2019 as referred to the Letter No. 26071-JO-PMC-LT-01846 and Attachment
2. Contractor's plan to mobilize resources has been prevented and disrupted by such Site
handover delay by Owner accordingly.
Despite the above situation, Contractor has mobilized sufTtcient Construction Equipment
having the capacity to carry out cumulative 208,000 m3 of S/C works until the end of May
2020, whereas cumulative work-front as of the end of May 2020 is only around 137,068 m3
based on the transferred area of Site specified in Attachment 2.
Furthermore, continuously changed Site handover schedule by Owner did not allow
Contractor to effectively revise the actual plan of Work, including the mobilization for
manpower and Construction Equipment, Subcontract, Temporary Facilities, and other related
activities, to avoid the significant idle resources as notified through 26071-JO-PMC-LT-00728
and 26071-JO-PMC-LT-01138.
• Point 9-11: The schedules of issuance for S/C drawing and Pile Location Plans were affected
by numerous events previously notified to Owner, including but not limited to deficiencies in
design data, delay, and revocation for Owner's confirmations/instructions and the provision of
updated/required design data.
The Extension of Time request in relation to such events is submitted for Owner's review and
approval through Contractor's letter No. 26071-JO-PMC-LT-01846.
Additionally, the ground of Owner's opinion for the piling productivity rates is not provided in
Owner's letter, therefore Contractor could not review and/or clarify for such argument.
In Contractor's point of view, the productivity rates per mobilized Construction Equipment and
its related resources, provided by valuable Indonesian Subcontractors, are superior and
sufficient to execute Construction Work.
As the S/C work is the pre-requisite of piling work in general, and S/C work has been affected
by the circumstances addressed in the above-mentioned Contractor's response to Point 6-11,
piling work also has been adversely affected accordingly.
In conclusion. Owner failed to provide Contractor with possession of the Site in accordance with
the Level 3 Schedule (Rev.OOO). Furthermore, Owner has continuously changed the forecasting
schedule of Site handover, and split area of Site into total 99 areas rather than 4 Clusters of Site,
which is the concept of Site handover Schedule provided by Owner during the bidding stage as
specified in Attachment 2 of this letter. The split of area for Site handover limits the work-front for
Contractor's construction Work, thereby prevent Contractor's performance of work as planned
and cause the idle resources accordingly. Such idle resources inevitably result in additional cost
and time impact on the Project, and furthermore does not contribute to the execution of
Construction Work due to the limited work front.
As addressed in Attachment 2, only 20 out of 99 Nos. areas of Site have been transferred to
Contractor, and even 22 out of 99 Nos. areas of Site's handover schedule have yet to be
confirmed as of 22 June 2020 (see Attachment 2 marked as "TBD").
Moreover, Contractor's construction Works have been disrupted due to numerous punch items of
Site handover, including unforeseen material such as underground obstacles, unpredictable
existing Facilities, and contaminated soil as notified through letters listed in Attachment 1 of this
letter. Such punch list activities can not be closed out as a simultaneous operation, as Contractor's
construction Work at the area with punch item can only be started after resolution thereof.
Lastly, the way of Owner's assertions provided in the above-mentioned Owner's letter is neither
in the appropriate contractual manner nor in accordance wth recognized international industry
practices.
In this regard, Contractor has not been able to plan and formulate the efficient mitigation plan,
due to the absence of the fixed Site handover forecasting schedule and pending Owner's
confirmation for design issues. Therefore, Owner is requested to provide a firm Site handover
schedule and confirmation for pending design issues as soon as possible, to avoid further impact
on the Project and to re-plan the Schedule of the Work properly.
Sincerely yours,
Attachment:
#1 Handover Correspondence Log
#2 Log of Site Handover Forecast Dates
#3 Hold status of Stone Column drawing (as of end of April 2020)
Attachment 1. H/O Correspondence Log
Date Description Reference Document No. Reference Docuntent
5-Mar-19 JO request for Owner to handover early work area. 26071 -JO-IPMT-LT-00012 Letter (JO to PMQ
JO asked for Owner permission for use of additional laydown area in the east side of
17-Apr-19 existing construction laydown area, in order to make an additional temporary camp 26071-JO-PMC-LT-00050 Letter (JO to PMQ
for worker.
7-Aug-19 JO requested to Owner to handover gasoline tank area no later than 31 august 2019 26071 -JO-PMC-LT-00304 Letter (JO to PMQ
26-Aug-19 JO request Owner's permission for utilizing existing deep well. 26071 -JO-PMC-LT-00376 Letter (JO to PMC)
28-Aug-19 Owner is requested to resolved problem that occurring in Area 9 regarding oil spill. 26071-JO-PMC-LT-00387 Letter (JO to PMQ
Owner is requested to provide proper road size, reinforce and modify the existing
30-Aug-19 26071-JO-PMC-LT-00394 Letter (JO to PMQ
bridge for preventing any damage during package transportation.
JO informed that all material for batcher plants is already arrived at site therefore, JO
30-Aug-19 request owner to handover Batcher Plant Area{Area 47/51) before end of October 26071-JO-PMC-LT-00397 Letter (JO to PMQ
2019.
Owner is requested to provide additional laydown area which is in the west area of
3-Sep-19 26071-JO-PMC-LT-00412 Letter (JO to PMQ
sulfur handling & storage area.
JO requested for owner permission to do stone column work and its preparation area
10-Sep-19 26071-JO-PMC-LT-00435 Letter (JO to PMQ
31 from early October 2019
JO request for owner permission to use some areas in north fence to be utilized for
23-Sep-19 26071-JO-PMC-LT-00475 Letter (JO to PMQ
temporary facilities (toilet, shelter, sattelite container office)
JO informed owner several findings related to SWI area, JO request owner to
27-Sep-19 26071-JO-PMC-LT-00495 Letter (JO to PMQ
mitigated such conditions in order to avoid further delay.
30-Sep-19 HANDED OVER MEETING #3 26071-JO-PMC-MM-00451 Handover Meeting MOM
JO responded to letter no 4020(X)-00540-PMC-SHRP-LET-0283and request for
1-Oct-19 PMC/Owner to give the latest status regarding dredging permit, dredging status and 26071-JO-PMC-LT-00515 Letter (JO to PMC)
plan.
7-Oct-19 HANDED OVER MEETING #4 26071-JO-PMC-MM-00452 Handover Meeting MOM
JO clarify several additional items to note for SWIarea as requested by PMCin letter
9-Oct-19 26071-JO-PMC-LT-00541 Letter (JO to PMC)
no 402000-00540-PMC-SHRP-LET-0365,
JO responded to Owner letter regarding Heavy Haul Reroute on Gate 4A and Bridge
5A, JO submitted the layout plan road requested by owner. Howeverthe obstacle on
11-0ct-19 26071-JO-PMC-LT-00554 Letter (JO to PMC)
Gate 4A and Bridge 5A must be demolished first in order to acccmimodate the
equipment mobilization.
14-0ct-19 HANDED OVER MEETING #5 26071-JO-PMC-MM-004S3 Handover Meeting MOM
JO notice PMC/Owner regarding handover some areas that may be subject to delay,
16-Oct-19 26071-JO-PMC-LT-00S91 Letter (JO to PMC)
JO asked owner to process the handover area in timely manner.
JO informed existing obstacle that was found between new construction jetty and
22-Oct-19 existing jetty sulfur. JO asked owner to take measure regarding the mentioned 26071-JO-PMC-LT-00622 Letter (JO to PMC)
obstruction.
28-Oct-19 HANDED OVER MEETING #7 26071-JO-PMC-MM-00481 Handover Meeting MOM
22-Jan-20 JO request owner to do dredging and shipwreck removal prior to handover 26071-JO-PMC-LT-01073 Letter (JO to PMQ
JO reminded that Owner concluded that Area 48 will be handed over to Contractor
26-Feb-20 26071-JO-PMC-LT-01276 Letter (JO to PMQ
on 30th March 2020.
JO informed the continuous(3 times) delay of handover date for area 48, and
27-Feb-20 26071-JO-PMC-LT- 01222 Letter (JO to PMQ
requested fixed handover date to allow JO's proper forecasting schedule.
24-Apr-20 JO summarize the target dates of the remaining hadnover work and the priority. 26071-JO-PMC-LT-01761 Letter (JO to PMC)
Date Description Reference Document No. Reference Document
JO confirmed that the actual area handover date shall be determined by the date JO Letter (JO to PMQ
24-Apr-20 26071-JO-PMC-LT-01766
siqn on the area handover dossier.
JO request PMC to complete the road preparation including culvert box 4A and
27-Apr-20 bridge SA by 09-Sep-20, Also JO asked if Schedule of Heavy Haul Road Preparation 26071-JO-PMC-LT-01803 Letter (JO to PMC)
in document 2671-JO-PMC-IR-GEN-0023 is still r^evant and on track.
JO informed the continuous delay of handover and requested the fixed handover
29-Apr-20 26071-JO-PMC-LT-01849 Letter (JO to PMQ
schedule.
29-Apr-20 JO submitted the second EOT claim regarding UOP issue and area handover delay 26071-JO-PMC-LT-01846 Claim (JO to PMQ
2-May-20 JO requested PMC the relocation and compaction for the road in DMT area 26071-JO-PMC-LT-01841 Letter (JO to PMC)
2-Mav-20 JO requested PMC the prompt handover for Area 40D 8t 45B 26071-JO-PMC-LT-01848 Letter (JO to PMC)
6-Mav-20 JO requested PMC prompt action for temporary drainage in RFCC area 26071-JO-PMC-LT-01870 Letter (JO to PMQ
6-M3y-20 JO requested PMC prompt action for toxic gas and unforeseen material in area 31 26071-JO-PMC-LT-01871 Letter (JO to PMC)
6-Mav-20 JO requested PMC the fixed face to face handover meetinq schedule 26071-JO-PMC-LT-0ia74 Letter (JO to PMQ
7-May-20 HANDED OVER MEETING #25 26071-JO-PMC-MM-00999 Handover Meetinq MOM
With reference to 402000-00540-PMC-SHRP-LET-0983(SWI sheet pile), JO sent the
7-May-20 26071-JO-PMC-LT-01890 Letter (JO to PMC)
claim notice letter to PMC
JO asked PMC completion of the drainage system in the Area 45, and informed the Letter (JO to PMQ
8-May-20 26071-JO-PMC-LT-01892
UG obstacles in the Area 400
8-May-20 JO informed PMC the UG obstacle in the Area 50 26071-JO-PMC-LT-01891 Letter (JO to PMC)
8-May20 JO requested the proper backfill and compaction for the Area 38 26071-JO-PMC-LT-01872 Letter (JO to PMC)
JO responded to letter 402000-00540-PMC-SHRP-LET-0929 regarding the existing UG
11-May-20 cable. JO requested further information for each area to establish the proper 26071-JO-PMC-LT-O1923 Letter (JO to PMC)
mitigation plan.
JO informed the current situation regarding stone column work front and request
11-May-20 26071-JO-PMC-LT-01921 Letter (JO to PMC)
prompt action for the remaining site preparation work.
JO informed the contaminated soil in the Area 29 and requested PMC the counter
n-M3y-20 26071-JO-PMC-LT-OI922 Letter (JO to PMQ
measure plan by 15th May
JO informed the lack of stone column work front and requested the handover of 28,
13-May-20 26071-JO-PMC-LT-01946 Letter (JO to PMQ
29, 30, 31, 32, 34 and 41 by the end of May.
JO Informed the contaminated soil and UG obstacles in the Area 31 and request
13-May-20 remove that. Also JO requested PMC complete the remaining work in the Area 28,30 26071.JO-PMC-LT-01921 Letter (JO to PMC)
for the stone column work front.
13-May-20 JO informed PMC the detection of H2S qas in the Area 29. 26071-JO-PMC-LT-01941 Letter (JO to PMC)
13-May20 JO proposed the fixed face to face handover meetinq schedule 26071-JO-PMC-LT-01949 Letter (JO to PMC)
13-May-20 JO informed the H2S qas detection in the Area 28 26071-JO-PMC-LT-01941 Letter (JO to PMC)
JO summarized the cuirent status of stone column wortc front and requested PMC to
13-May-20 26071-JO-PMC-LT-D1950 Letter (JO to PMQ
handover the area prcwriotly
13-May-20 JO informed the working stop in the Area 28. 29, 31 26071-K)-PMC-LT-01935 Letter (JO to PMC)
JO responded to letter 402000-00540-PMC.SHRP-LET-0984, 402000-00540-PMC-SHRP
-LET-0985 and 402000-00540-PMC-SHRP-LET-0987 regarding the remaining UG
13-May-20 26071-JO-PMC-LT-01951 Letter (JO to PMQ
material. JO Informed the cost estimation for UG unforeseen materials and asked
Owner to remove considering the schedule and cost.
19-May-20 JO informed aqain that area 34 to be handover by 31 may 2020 26071-JO-PMC-LT-02010 Letter (JO to PMQ
21-May-20 HANDED OVER MEETING #26 26071-JO-PMC-MM-01082 Handover Meeting MOM
22-May-20 JO asked Owner not to handover the remaining site preparation work 26071 -JO-PMC-LT-02030 Letter (JO to PMC)
29-May20 JO informed PMCthe late handover and requested the updated HO schedule 26071-JO-PMC-LT-02073 Letter (JO to PMQ
29-May-20 HANDED OVER MEETING #27 26071 -JO-PMC-MM-OI099 Handover Meeting MOM
JO responded to letter 201/KPB1000/2020-SO and 218/KP01OCIO/2O2O-SO regarding
3-Jur-20 the partial handover of the Area 41. JO proposed the partial handover of 64, 67 and 26071-JO-PMC-LT-02119 Letter (JO to PMC)
167 unit.
JO notified the work stop in R61/62 due to leakages in existing facilities since 01 June
3-Jun-20 26071 •JO-PMC-LT-02022 letter (JO to PMQ
2020.
JO responded to letter 216/KP81000/2020-S0 regarding the toxic gas in the area 28,
29,30 and 31.
9-1un-20 JO will inform whenever the UG obstacles are discovered. 26071-JO-KPB-LT-00031 Letter (JO to Owner)
JO asked the entire removal of toxic gas instead of providing lime stone powder.
JO requested the comlete removal of contaminated soil by Owner.
1 OSBL 2A Cluster 1 337 SWIlO Handover Completed Completed Corr^leled Completed Compleled Completed
2 06BL 2B Cluster 1 337 SWRO (AcirfFlare) •2O.W07 •20.04.30 •20.05.12 '20 06 21 Crsmpleted CoiTvpleted
3 06BI iA Clutter 1 337 Demln Water Storarie Handover Completed Completed Completed Compleled Completed Completed
* OSBL 3B Cluster 1 337 Cuy Wire of Add Flare '20.04 07 •20.04.30 •20.05.12 •20 06.21 Completed Completed
5 OSBL Clutter 1 341 65-101 Handover Completed Completed Compleled Completed Completed Completed
6 OSBL 6 Clutter 1 337 Remirserallution '20.04 07 '20.04.30 •20.95.02 Completed Completed Completed
7 OSBL 6 Clutter 1 331 STG Handover Completed Completed Completed Completed Completed Completed
e OSBL 7 Clutter 1 341 56-111 Handover Completed Completed Completed Compleled Completed Completed
9 OSBL S Clutter 1 332 UtiljlyCoclino Tower Handover Completed Completed CoiTBileled Compleled Completed Compleled
10 OSBL Clutter 1 320 F£En Tank Handover Completed Completed Corrpleled Compleled Compleled Completed
11 OSBL 11A Clutter 1 331 GTG Handover Completed Completed Completed Completed Compleled Compleled
12 OSBL 11B Clutter 1 331 GTG •20.11.20 •20.11.20 20.11.20 20.11.20 TBD lUt'
13 OSBL 14 Clutter 2 336 N2 Plant '20 0602 •20.06.02 TBD TBD TBD •20.0626
14 OSBL IS Clutter 2 341 56-103 '20.08.02 '20.08.02 TBD TBD TBD •20.09.06
IS OSBL 17 Clutter 2 06S HMU •20.07.31 '20.07.31 •20.07.31 •20.07.31 TBD •20.1028
16 OSBL 18 Clutter 2 31S Fuel Oil 6ys1em '20 0624 20.0624 TBD TBD TBD •20.09.06
17 OSBL 19 Clutler 2 334 WWTP •20.04 11 •20.04.11 '2006.30 •20 0630 TBD inn
IB OSBL 20 Cluster 2 341, 325 66-104, Caustic treatment •20 04.30 •20.04.30 •20.04.30 •200601 TBD IBP
19 OSBL 21 Clutter 2 334 WWTP '20.04.30 '20.04.30 '2004.30 TBD TBD IBD
20 PhAi« 2 22A Clutter 2 Phete 2 Temporary Facility •20 05.20 '20 06.20 •20.0530 •20 06.30 20.08.30 •20.0630
21 OSBL 22B Clutter 2 319 RFCC Flare KO Drum •20 04 16 '20 04 30 •2007.01 •200601 TBD IBP
22 OSBL 24 Clutter 2 341 Tiisjuno Batu Control Room & Melerirtg •20.06.31 •20.05.31 •20O631 •2006.31 TBD top
23 OSBL 27A Clutler 2 337 Sea Water Intake Handover Completed Com^led Completed Com^ted Compleled Completed
24 OSBL 27B Clutter 2 337, 341 Sea Water Intake. 66-106 •20 06.31 •20.05 31 '2006.30 '200630 '2006 30 20.07.08
26 ISBl 2B Clutler 2 DBS H2 Comprettor •20.01.30 •20.M30 TBD TBD TBD •20.0630
26 ISBL 29A Clutter 2 064 DKT •20.05.19 •20.05.19 TBD TBD TBD '20.0730
27 tSBl 29B Clutler 2 064 DHT 21.04.30 •21.04 21 •210621 •210521 2106 21 21.0521
2B ISBL 30 Clutler 2 341, 316 66-116, Fuel Gat System •20.01.30 •20.O4J0 •20.0430 •20.04.30 TBD 100
29 ISBL 31A Clutler 2 0B3 DHT •20.02.17 •20.04.27 •20.0427 TBD TBD •20.06.30
30 ISBL 31B Clutter 2 083 DHT •21.03.01 •21.04 21 •21 0421 •21.04.21 2104 21 •21,05.21
31 tSBL 32 Clutter 2 341 Mca •20.05.30 •20.05.30 •200630 •2006.30 •20.07.30 '20.08.18
92 ISBL 34 Clutter 2 001 CDU-IV Preflash •2007.04 '2005.31 '20.05.31 20.05.31 •20.0621 •20.06.21
33 ISBL 36 Clutler 2 DB4 NHT •2001.16 •20 06 15 '20.07.15 •2007.15 20.07 15 •20.07.15
34 Phite 2 36A Clutter 2 Ptrese 2 RD6U 20 01.27 '20 04.08 •2004.08 Completed Compleled Completed
36 Phue 2 36B Clutler 2 Phase 2 RD5U •21.03.01 •21.03.01 •21.06.21 21,05.21 21.05.21 •21.06.21
36 ISBL 37 Clutter 2 082 homer •2001.16 •20.06.15 •20.07.15 •20.07.15 '2007 15 •20.07.16
37 ISBL 3BA Clutler 2 341 66-115 •20.06.02 '20.06.02 •20.0630 •20.06.30 •20.06.30 •20.06.30
3B ISBL 3BB Clutler 2 341 66-116 •20.06.02 '20.06.02 '2006.30 •20.0630 •20.0630 •20.09.03
99 Ph4S« 2 39A Clutter 2 Phase 2 ARU 20.02.06 •20.05.31 •2007,16 20.07,15 •20.07.15 •20.07.15
40 ISBL 39B Clutler 2 319 Souin AodOat FUr* StiA. KO Drum Bl Incanaialor •20.06.16 •20.06.16 •20.0630 •20.06.30 '20.0630 •20.08.02
41 ISBL 40A Clutler 2 062, 062. 063 RFCC Handover Completed Compleled Compleled Compleled Completed Compleled
42 ISBL 4081 Clutler 2 052. 062.063 RFCC Handover Completed Competed Completed Compleled Compleled Completed
43 ISBL 40B2 Clutler 2 052. 062. 063 RFCC Handover Completed Compleled Completed Completed Completed Corr^eted
44 ISBL 40C Clutter 2 052. 062. 063 RFCC •20.03.16 •20.0t.08 20.04.08 Compleled Completed Completed
46 ISBL 4001 Clutter 2 052. 062. 063 RFCC (Read) •20.07.07 •20.04.21 •2005.30 2 0 05 30 '20 0616 •20.06.15
46 ISBL 4002 Clutler 2 052 062.063 RFCCfRttad) •20.07.07 •20.06.15 2006.30 •20.06.30 '200630 •20.07.15
47 ISBL 41A Clutler 2 NLP •2007.05 •20.07.06 2007.05 •2007.05 •20.06.16 •20.0626
41 ISBL 41B Clutter 2 NIP •20.07.05 •20.07.06 20.07.05 200705 •20 07.05 '20 09.03
49 ISBL 42 Clutter 2 341 65-106/108 '20.06.14 •20.06.14 •2006.30 •20.06 30 •20 06 30 '2009.03
so ISBL 43 Clutter 2 065 Bl 066 AJkylation. Wet Gat Sulphuric •20.01.06 •20.04 OB •2QO4.08 •2004.06 7B0 •20.04.08
SI ISBL 44 Clutter 2 059 CCRPlatformlrsj LFnit 20.01.31 •20.01.31 •20.06.30 '20 05 30 '20 0630 •200625
52 ISBL 46A Clutter 2 053 NHT •20.02.16 •20.04.30 •20.0630 •2006.30 •20.0630 '20.06.30
63 ISBL 45B Clutter 2 053 NHT •2006.17 •20.0421 •20.06.30 2006 30 20.0727 '20.0631
64 ISBL 46A Clutter 2 053 NHT •20 06 17 •20.06.17 •200617 •20.0617 •20.06.30 '20.0616
56 ISBL 47A Clutter 2 169 6RU '20.06.31 •20.05.31 •200530 '20 05.30 •2006.17 •20.06.26
66 ISBL 47B Clutter 2 169 SRU •20.06.31 •20.05.31 •200630 '2006 30 •20.09.11 •20.09.08
57 OSBL 48 Clutter 3 320 Pr^ylene Tank •20 05.11 •20.0521 •20.0515 •20 0616 •20.07 15 •20.07,15
SB OSBL 49A Clutter 3 320 320 Propylene Pump '20.06 28 •20.05.31 •20.0615 '20.0630 •20.06.30 •20.0630
69 OSBL 49B Clutter 3 320 320 Propylene Pump •20.05.28 •20.05.31 •200615 20.0630 TBD •20.10.30
60 ISBL 60A Cluster 2 341 66-109 •20.06.22 •20.06.15 •20.0630 20.0630 20.06.30 •20.07,16
61 ISBL SOB Cluster 2 065/066 AJkylatlon '2002.17 •20.02.17 •200530 •2006.30 20.06 30 •20.06.30
62 fhtit 2 61A Cluster 2 Phase 2 Sulphur Recovery Pirate 2 Handover Completed Completed Compleled Completed Completed Compleled
63 Ph4ic 2 SIB Cluster 2 Phase 2 Sulphur RecoveryPhate 2 •20.06.27 •20.12.31 •20.12.31 •20.12.31 TBD ton
64 OSBL 62 Cluster 3 341 Codtng Water System •20.07 03 •20.07.03 •2007.03 20.07.03 20.03.27 •20.0827
66 OSBL S3 Cluster 3 320 Gasoline Blending •20.04.28 •20.12.3! •20.12.31 •20.12.31 TBD 10D
66 OSBL S4A Cluster 2 321 Sulfur Handlinq & Storage 5ntide fencing)! '20.06 30 TBD •2008.31 •20.0631 TBD TOIJ
67 OSBL 66 Cluster 4 320 Gasoline Tank •2004 09 •20 05.22 •20.05.30 20 06.30 •20.06 14 •20.0630
61 OSBL 66 Cluster 3 341 New Gat^lne Transfer Pumps '20.0624 20.06.24 TBD '20 0624 TBD I0D
69 OSBL 69 Cluster 2 341 56-114 '20.04 30 TBD TBD TBD TBD IBD
70 OSBL 61 Cluster 2 341 65-76 •20.03 31 TBD T8D TBD TBD ISO
71 OSBL 66 Cluster 3 320 G320-02 05 A/B. 06 A/B. 12 A/B TBD TBD TBD IBD
74 OSBL 69 Cluster 2 321 Interconnecting Pjpeway Hartdover Completed Completed Competed Completed Completed Completed
76 OSBL 70 Cluster 2 Offshore Flare Trestle RFCC Offshore '20.04 30 '2007.15 •2007.15 •2007.15 •20.07.16 •20.07.15
76 OSBL 71 Cluster 3 341 Operator shelter 341-OP-004 - TBD TBD TBD TBD 10!)
77 OSBL 72 Clutter 3 341 peralor shelter 34)-OP-005 -
TBD TBD TBD TBD TBD
7B OSBL 73 Cluster 3 341 341-OP-OlS •20.04.17 •20.04.30 •200615 •200630 •2006.16 20.0626
79 OSBL 74 Clutter 3 341 Operator shelter 341-09-007 - 7BD TBD TBD IBD
BO OSBL Drtdging work Clutler 4 337 5WI offshore pipe •20.04.03 •20.04.03 20.04.03 •20.04.03 TBD •20.0530
81 OSBL Exiitlng Jetty Cluster 4 323 Jetty 6A-1(North P/R) 20 02.1B •2002.18 2007.15 200M5 TBD •20.07.16
fn Mfailulea of Handed over meetlisg
ROMP Aree Hendover
Status Report
OSBt/ atES
No. AREA No. Cluiter No. UNrr DESCRIPTION (402000-00540-CM-REP-0002) *26
BBL 2020-04-20
(aa of 22 March 2920} 2C2Q-OS-11 #27 #28 #29
(2(071-J0-
[basis of 2nd EOT! (26071-JO-KPB' 2029-OS-18 202(M>«-08 2020-06-22
PMC-MM-
M84-00002)
nH199)
82 ISBL Existing jetty Cluster 4 323 Jetty 1-S upgarading loading arm TBD •20.09.03
83 ISBl Jetty Sulfur Cluster 2 169 Container Crane 20.08.17 •2008.17 '20.08.17
85 osai Intercon P/R-A1 Clutter 1 321 Intercon P/R (R4a/41) •20.04.15 Completed Completed Completed Cample ted Campleted
86 OSBL Interton P/R-A2 Cluster 2 321 Intercon P/R (R50J •20.05.31 '20.05.30 •20.06.30 •20.06.30 TBD •20.0630
87 OSSl Intertnn P/R-A2 Cluster 2 321 Intercon P/R (R72J •20.05.31 •20.05.30 •2005.30 '20.05.30 •20.05.30 TBD
83 osai Intercon P/R-B Cluster 2 321 Intercon P/RffilO/ll) •20.05.31 •20.05.30 •20.07.15 •20.07.15 •2007.15 '20.0730
88 osai Intercon P/R-C1 Cluster 2 321 Intercon P/R (R61/62) •20.02.29 •20.04.30 •20.05.30 •20.05,30 TBD TBD
90 osai Intercon P/R-C2 Cluster 2 321 InUixon P/R IR60/12/13) •20.10.01 •20.10.01 •2010.01 •20.10.01 •2010.01 •20.10.01
91 0S9L Intercon P/R-D Cluster 3 321 InlBicon P/R (ReO/8V94/85) •20.05.31 •20.05 31 •20.05.31 •20.05.31 TBD •20.05.31
92 OSSL Intercon P/R-D Cluster 3 321 Intercon P/R 181) •20.06.30 •20.06.30 •20.05.30 •20.05.30 •2006 22 •20.07.05
93 OSBL Intercon P/R-D Cluster 3 321 Intercon P/R (82) •20.06.30 •20.06,30 •2007.30 20.07.30 •20.07.30 •20.07.30
94 OSBL Bridge TBD Bridge Bridge 4A •20.07.30 •2008.06 •20.0S.06 •20.08.06 '20.0830
95 OSBL Bridge TBD Bridge Bridge iA •20.0607 •20.0B.31 •20.0831 •20.08.31 '20.09.30
98 OSBL <%slec(e TBD Road Existing Fire Water Line at Jetty •20,07.15