Internship On Building Construction: MEVADA AKHIL C. (180610106027)
Internship On Building Construction: MEVADA AKHIL C. (180610106027)
INTERNSHIP ON BUILDING
CONSTRUCTION
•SUBJECT:
INTERNSHIP (3180601)
•Prepare by:
❑MEVADA AKHIL C. (180610106027)
•FACULTY GUIDE:
❑PROF. Y. J. CHAUHAN.
➢ INTRODUCTION
➢ OBJECTIVES
➢ SUMMARY OF INTERNSHIP
➢ My project is based on construction of R.C.C. structures. This
internship bridge the gap between theory and practical
knowledge and provides to us practical, field based and real
world experiences during the years of studies.
➢ During my internship training period I learned how to relate
our theoretical knowledge with practical fields. What are the
difficulties faced by an engineer. How to manage difficulties
and what are the duties of engineer for these practical and
technical skills that all things learn for I joined in offline
internship programme under construction company whose
name “PRAMUKH MASTANA CORPORATION”.
➢ Address: SURVEY NO.-210, FINAL PLOT NO.- 144 TP-13,
NR. DEVANSHI HOSPITAL VAVOL,
GANDHINAGAR.
➢ The internship develops our skills to implement
theoretical knowledge into practical fields.
➢ To gain practical experience related to the
construction site.
➢ To understand planning, design, and drawing of
structure and their construction.
Introduction to site:
• Name of construction project: Burj Mastana.
• Location of site: Vavol,Gandhinagar.
➢ Key highlight of site:
• Built up area= 3.0 lakhs sq. ft. (approx.)
• Community building.
• 9 Bungalows.
• G+7 floors of six towers (A to F).
• 20 Shops (Commercial space).
➢ I did on the first week:
• Visited the construction site and reporting to the project
manager.
• I was take brief overview and information of site and
which construction materials, equipments and techniques
are used at site that was understood.
➢ Augering is done by tractor mounted spiral auger up to depth of
6m to make borehole for cast in situ piles from ground level for
community building.
➢ Cast in situ piles which are cast in position inside the ground.
Augering.
➢ Soil and Foundation details:
• Soil type: Silty soil.
• Soil bearing capacity: 32 tonnes (approx.)
• Foundation: Deep (Pile) foundation.
• Type of pile: Under reamed pile (Uncased cast in situ)
with 2-bulbs each.
• Pile- P1:
✓ Shaft size: 300mm (dia.)
✓ Bulb size: 750mm (2.5 * shaft size)
✓ Load carrying capacity: 24 tonnes.
• Pile- P2:
✓ Shaft size: 450mm (dia.)
✓ Bulb size: 1125mm (2.5 * shaft size)
✓ Load carrying capacity: 50 tonnes.
First I get information about procedure of construction
and installation of the under reamed pile from the site
supervisor. Also, about useful equipments for installations
of pile. Like…
1) Spiral auger: For Boring purpose.
2) Boarding guide: To keep borehole vertical.
3) Under reamer: Making bulbs in borehole.
Under reamer
➢ Arrangement of rebar's to make reinforcement cage for piles.
➢ Calculations of volume of
concrete for pile P1 and P2,
also quantity of materials
required for piles.
➢ Calculations:
A. Pile- P1: ▪ Quantity of materials required:
• Length, L= 6m. • Vp1= 0.557 cum. (Wet volume)
• No. of bulbs, N= 2.
Therefore;
• Bulb dia. D= 0.75m.
Dry volume= 1.10* Vp1
• Shaft dia. d= 0.30m.
= 1.10* 0.557
▪ Volume of concrete required for
pile P1; = 0.613 cum.
✓ Vp1= π/4{L*d^2+0.4N(D^2- d^2) Now; M-25 grade (1:1:2)= 4.
* (D-d)} ✓ Cement= ¼*0.613*1/0.035
=3.14/4{6*(0.3)^2+0.4* = 5 bags (approx.)
2(0.75^2- 0.3^2)*(0.75-0.3) ✓ Sand= ¼*0.613
Therefore; =0.154 cum.
Vp1= 0.557 cum. (approx.)
✓ Aggregates= 2/4*0.613
=0.3065 cum.
B. Pile- P2:
• Length, L= 6m. ▪ Quantity of materials required:
• No. of bulbs, N= 2. • Vp2= 1.404 cum. (Wet volume)
• Bulb dia. D= 1.125m. Therefore;
• Shaft dia. d= 0.45m. Dry volume= 1.10* Vp2
▪ Volume of concrete required = 1.10* 1.404
for pile P2; = 1.550 cum.
✓ Vp2= π/4{L*d^2+0.4N(D^2- d^2)
* (D-d)} Now; M-25 grade (1:1:2)= 4.
=3.14/4{6*(0.45)^2+0.4*
2(1.125^2- 0.45^2)* ✓ Cement= ¼*1.550*1/0.035
(1.125-0.45) = 11 bags (approx.)
Therefore; ✓ Sand= ¼*1.550
Vp2= 1.404 cum. (approx.) =0.3875 cum.
✓ Aggregates= 2/4*1.550
= 0.775 cum.
Study of ground floor plan of Plot/Bungalows no. 1 to 7 (4 BHK).
single winder.
• Width of stair: 1 m.
2 nos.- 8mm Ø
+ 4 nos.- 10mm Ø.
Preparation of slab formwork at Plot no. 1 & 2.
• SLAB:
1) All slabs are: Two way slab.
2) Slab area= 1500 sq. ft.
3) Thickness of slab: 125mm (cover= 25mm).
4) Reinforcement arrangement:
✓ Lx: 8mmØ- 150mm c/c (Alt. arranged)
✓ Ly: 10mmØ- 150mm c/c (Alt. arranged)
✓ Extra/ curtailment: 8mmØ- 300mm c/c and;
length of curtailment (0.3*length of slab).
➢ Done arrangement of
beam and slab on the
formwork with suitable
concrete cover block.
Done concrete filling in ground floor slab of plot no. 1 & 2, with M- 25
grade concrete.
➢ Masonry work:
➢ Calculation of quantity of AAC blocks and Block jointing
mortar required for block wall works:
➢ Details of wall:
• Size of AAC wall = 4.2m*0.1m*1.2m. (Partition wall)
• Size of AAC block = 600mm*200mm*100mm.
= 0.6m*0.2m*0.1m.
• Bond thickness of mortar = 3mm = 0.003m.
➢ now;
1) Volume of block wall = L*B*H = 4.2*0.1*1.2
= 0.504 cum.
2) Volume of AAC block = l*b*h = 0.6*0.2*0.1
= 0.012 cum.
➢ Volume of the AAC block
with mortar bond thickness;
= 0.603*0.203*0.1
= 0.01225 cum.
➢ Now;