Estimating and Costing
Estimating and Costing
Lecture 4
Intent
To understand the different methods of
calculating the quantities of materials/items of
works for estimating the cost of building works.
LONG WALL SHORT WALL
OR
INDIVIDUAL WALL METHOD
LONG WALL SHORT WALL OR INDIVIDUAL WALL METHOD
The walls running in one direction are termed as "long walls” and
the walls running in the transverse direction, as "Short walls",
without keeping in mind which wall is lesser in length and which
wall is greater in length.
Lengths of long walls are measured or found "Out-to out" and
those of short walls as "In-to-in".
Different quantities are calculated by multiplying the length by
the breadth and the height of the wall.
The same rule applies to the excavation in foundation, to concrete
bed in foundation, D.P.C., masonry in foundation and super
structure etc.
• For symmetrical footing, the center line remains same for
super structure, foundation and plinth. So, the simple
method is to find out the center-to-center lengths of long
walls and short walls from the plan.
• Long wall length out-to-out
= Center to center length + half breadth on one Side + half
breadth on other side.
= Center to center length + one breadth
greater in length.
Plan
Estimate the quantities of the following items of a
1BHK flat from the given plan and section:
Earthwork in excavation
Lean conc. In foundation
Brick work in foundation
D.P.C.
Brick work in super structure
Length of excavation for long wall = C/C length + Breadth of excavation
Centre to Centre length
1.Earthwork in excavation
Length same
Short Walls 2 5.145 1m .20 m 2.058 cu for
m m excavation.
Total Quantity of Lean Concrete =4.27 cu m
3.Brick Work(1st class) in 1:6 Cement Mortar in
foundation and plinth
For Long Walls
Particular No Length Breadth Height or Quantity Explanatory
of Items Depth Note
1st Step 2 5.335 m .805 m .150 m 1.288 cu L=4.3+.23+.8
m 05=5.335m
2nd Step 2 5.22 m .690 m .150 m 1.08 cu m L=4.3+.23+.6
9=5.22m