GENERAL CONDITIONS
I shall provide all necessary labor and materials, and perform all work of every nature on the proposed
renovation in accordance with this contract, the specifications required by original specs for the structure per the
Home Manufacturer, and all updated specifications needed for the accompanying drawings. I shall obtain the
building permit. Any contractors and/or subcontractors will take out their own permits and pay for them. All
work is to be executed in a workmanlike manner in accordance with the contract, plans, and specifications.
WORK GUARANTEE
All labor and material, except those products manufactured and guaranteed by the manufacturer or supplier,
executed or furnished by a contractor or subcontractor under the terms of this agreement shall be guaranteed
for 1 year starting at the last full working day. All labor and material as guaranteed will be completed only after
all money in accordance with any contract and/or change orders have been paid to the contractor/subcontractor
by me.
APPROVAL
In view of changing labor and material conditions this proposal is void unless accepted in writing and this or
other mutually acceptable agreement signed within 30 days of proposal date. Proposal is subject to approval and
signature of the original home manufacturer. This agreement is binding upon the heirs, executors,
administrators, successors and assigns of the owner.
PROJECT COSTS
Bathrooms Accessories
Hardware I/contractor/subcontractor to 4 $0.00 / EA $0.00
Delta install Hardware as needed in all
three bathrooms and possible Labor: $0.00
Delta Vene an Bronze half bath.
Cres ield 3-Piece Bath Other: $0.00
Accessories Kit
487323
Bathrooms Fixtures
Bathrooms Sink
Sink Faucet I/contractor/subcontractor to 4 $0.00 / EA $0.00
GROHE install sink faucets in all three
bathrooms and possible half bath Labor: $0.00
GROHE Starlight Chrome
Conce o 1-Handle Low- Other: $0.00
Arc Bathroom Faucet
172387
Bathrooms Vanity
Electrical Ligh ng
Can Ligh ng I/Contractor/Subcontractor to 60 $0.00 / EA $0.00
Lithonia install Can Ligh ng throughout
en re house to include all Labor: $0.00
Lithonia White 6" Can bedrooms, bathrooms, living
Lights Other: $0.00
room, kitchen, closets, and
548099 u lity room.
Floors Laminate
I/Contractor/Subcontractor
Laminate to install Laminate Flooring 1 $0.00 / SF $0.00
Pergo throughout living room,
Pergo Hand Sawn Oak kitchen, all three bedrooms and Labor: $0.00
Pergo XP Hand Sawn Oak possible half bath, closets a
u lity room.
Other: $0.00
10 mm Thick x 4-7/8 in.
Wide x 47-7/8 in. Length
Laminate Flooring
539985
Kitchen Appliances
Kitchen Cabinets
Kitchen Countertops
Roof Sheathing
COMPLETION TIME
It will take an estimated three to five months to complete the entire renovation per the specifications needed
to complete the project based on the rehab plan and new layout of the floor plans, which will be submitted
along with this rehab plan.
I agree to diligently pursue work through to completion, but shall not be responsible for delays for any of the
following reasons: acts of neglect or omissions of my employees or My agent, acts of God, stormy or inclement
weather, strikes, lockouts, boycotts, or other labor union activities, civil communion, Inability to secure materials
through regular allocation of materials, failure of Me to make payment to any Contractors and/or subcontractors
pay when due, or delays caused by inspectors of governmental bodies concerned.
(i) To assume for Myself/Contractor all responsibilities and obligations Contractor has assumed for Owner so far as
the subcontract work is concerned.
(ii) To start work when notified by Myself/Contractor and to complete subcontract work at such times as will enable
Myself/Contractor to fully comply with the scope of work, and to be bound by provisions in any contract with Myself/
Contractor for liquidated damages if caused by Subcontractor,
(iii) To not assign or sublet any portion of responsibilities or obligations without the written consent from Myself.
(iv) To clean up all refuse and debris upon the completion of any unit of the subcontract work, and to promptly
remove all excess material, tools, structures, etc., that have been brought on the premises or erected by
Subcontractor. In the event of failure to do so, I/Contractor may, after reasonable notice to Subcontractor, clean up
(he premises at the cost and expense of Subcontractor.
(v) To at all rimes carry on this subcontract lo the full and complete satisfaction of Myself/Contractor, It is
understood that if at any time I am/Contractor is of the opinion Subcontractor is not proceeding satisfactorily then I/
Contractor shall have the right, after reasonable notice, to take over subcontract work and to complete the same at
the cost and expense of Subcontractor.
PAYMENT SCHEDULE for ANY CONTRACTOR or SUBCONTRACTOR
ACCEPTANCE OF PROPOSAL
The prices, specifications, and conditions are satisfactory and are hereby accepted. I am authorized to screen and hire all
Contractors/Subcontractors that may perform some/all of the work as specified. Payment will be made to any Contractor/
Subcontractor as outlined in this contract.
I, as the OWNER of the PROPERTY LOCATED at 5517 ADALEE RD, DECLARE that ANY PERSON or COMPANY FURNISHING LABOR or
MATERIALS for the improvement of real property may enforce a mechanic's lien upon the improved land if they are not paid for their
contributions, even if such parties have no direct contractual relationship with the owner of the property.