Subject Riyadh Metro Project

Date 4 April 2017 Job No/Ref 239762

1 PTR Information
BACS Ref: M-BMA-1E2DS0-CBCO-NCR-000111
Arup Ref: 20170404-NCR-1E2-00
Station: 1E2

2 NCR Request from VBC


Subject:
Leftover concrete from previous pour due to collapse of adjacent construction joint at base slab
(B07) between grid lines ( 20 / 19) and ( F / C )
Reference files:
M-BAR-1E2DS0-CB00-EDR-010711
M-BAR-1E2DS0-CB00-EDR-010710
Technical requirements:
Base slab reference drawings NO: M-BAR-1E2DS0-CB00-EDR-010711
Base slab key plan reference drawings NO: M-BAR-1E2DS0-CB00-EDR-010710
Non conformance:
The base slab already constructed except for interface B/W tunnel ring with base slab @ north side
(GL -20/19- C/F) outstanding for final pour with construction joint.
However, the re-bar extended from construction joint for next lap @ bottom layer (B1, B2, B3 &
B4) are fused with leftover concrete from previous pour due to collapse of adjacent construction
joint (HYRIB) & tunnel grout flow, which is 300 mm thick (from Blinding to top of B4 re-bar) as
shown in attached drawing.
Recommended disposition:
Please find attached drawing with existing site condition and proposed option (new re-bar placement B1 to
B4) for your acceptance and further recommendation.
Attached files:
M-BAR-1E2DS0-CB00-EDR-010710.pdf
M-BAR-1E2DS0-CB00-EDR-010711.pdf
Proposed sketch as per site condition.PDF
100_3363.JPG

\\GLOBAL.ARUP.COM\LONDON\ILG\JOBS\239000\239762-00 RMP\7 SITE RELATED ACTIVITIES\07 SITE INSTRUCTIONS\20170404-NCR-1E2-00\03 WORKING FILES\20170404-NCR-1E2-


00.DOCX

Arup | F0.13 Page 1 of 3


Subject Riyadh Metro Project
Date 4 April 2017 Job No/Ref 239762

100_3366.JPG

LDFE review:
Dan,
Contractor are unable to remove the leftover concrete from block out (interface B/W tunnel & base
slab), therefore we have to provide NCR with proposed disposition.
Dan, I have attached pictures for your reference, here we have place new re-bar above the unwanted
concrete (300mm).
Please review and forward it to ARUP
PFE review:

BACS EM review:
Please review and advise.
LDE disposition:

3 Arup Response
Dated: 20th April 2017
Owner: Spring Xu, Nils Clementsen
Proposed response:
The proposed remedial measures are not acceptable. The quality of the leftover concrete and the
tunnel grout flow will not be suitable to be incorporated into the permanent works and provide the
required durability.
We propose that 2 layers X25 @ 150mm centres are post-installed into the base slab with Hilti HIT-
HY 200 with 900mm embedment as shown on the sketch below. This is to be implemented on all
three sides of the section of the slab still to be constructed.
All post-installed bars should be installed in accordance with the manufacturer’s recommendations
and the recommendations given in the response to RFI M-BAC-RFI-002504 (Arup ref: 20170206
RFI-LW-00).
The contractor should carry out a cover meter survey to determine the reinforcement layout to help
avoid post-drilling into cast-in reinforcement. It is not permitted to cut any cast-in reinforcement.
The above technical proposal is only applicable for this NCR and is only possible due to the design
forces at this particular location.

\\GLOBAL.ARUP.COM\LONDON\ILG\JOBS\239000\239762-00 RMP\7 SITE RELATED ACTIVITIES\07 SITE INSTRUCTIONS\20170404-NCR-1E2-00\03 WORKING FILES\20170404-NCR-1E2-


00.DOCX

Arup | F0.13 Page 2 of 3


Subject Riyadh Metro Project
Date 4 April 2017 Job No/Ref 239762

Checker: Phil Stephenson


Approver: John Batchelor

\\GLOBAL.ARUP.COM\LONDON\ILG\JOBS\239000\239762-00 RMP\7 SITE RELATED ACTIVITIES\07 SITE INSTRUCTIONS\20170404-NCR-1E2-00\03 WORKING FILES\20170404-NCR-1E2-


00.DOCX

Arup | F0.13 Page 3 of 3