DOI 10.5592/otmcj.2013.2.5 This study aims at identifying the risk map for factors affect-
Research paper ing cost overrun in building construction projects in the
West Bank in Palestine from the consultants’ perspective.
The field survey included 26 consultants. 41 factors are iden-
tified through literature review. The factors are divided into 5
groups. The analysis of the identified 41 factors indicates that 1
factor is located in the green zone, 14 factors are located in the
Keywords yellow zone, and 26 factors are located in the red zone of the
Cost Overrun, risk map. The results indicate that the top five affecting factors
Risk Map, Building are: political situation, fluctuation of prices of materials, eco-
Construction, nomic instability, currency exchange, and level of competitors.
Construction in Palestine It is hoped that these findings will guide efforts to enhance the
cost performance of construction industry.
i. mahamid · n. dmaidi · risks leading to cost overrun in building construction fromconsultants’ perspective · pp 860 - 87 3 861
Effect Less profit Less profit Cash flow End user Company
Disputation
Author to client to contractor problems satisfaction failure
Mbachu et al.
(2004)
• • • • •
Zainuddeen et al.
(2008)
• •
Arditi et al.
(1985)
•
Ahmed et al.
(2003)
• •
Charoenngam et
al. (2001)
•
Nega (2008) • • • • •
Table 1. Main effects of cost overrun in construction projects through previous studies
Al-Juwairah (1997) conducted a study concluded that the top affecting factors (site) management or poor cost control,
to identify the most severe factors affect- are: conflict among project participants, delays between design and procure-
ing construction cost in Saudi Arabia. 42 ignorance and lack of knowledge, pres- ment phases, incorrect or inappropri-
factors were considered in the study. He ence of poor project specific attributes ate methods of cost estimation, addi-
concluded that the most severe factors and non existence of cooperation, hos- tional work, improper planning, and
affecting construction cost from the con- tile socio- economic and climatic con- unsupportive government policies.
tractors’ perspective are: cost materials, ditions, reluctance in timely decision, Okpala et al. (1988) studied the
incorrect planning, contract manage- aggressive competition at tender stage causes of delay and cost overrun in con-
ment, wrong estimation method, and and short bid preparation time. struction projects in Nigeria. 20 factors
previous experience in contract. Elinwa et al. (1993) identified 31 fac- were identified as causes of delay and
Al-khaldi (1990) concluded that the tors affecting the construction cost in 27 factors as causes of cost overrun. The
top five factor affecting construction cost Nigerian Construction projects. They results indicated the following:
in Saudi Arabia from contractors’ view concluded that cost of materials, fraudu- 1. ‘’high costs can be minimized by mini-
are previous experience in contracts, lent practices and kickbacks, and fluc- mizing lapses in the management of
payments, availability of management tuation of prices of materials are three human and material resources.
finance and plans, type and size of con- of the most important factors leading to 2. despite some slight differences, the
tract and its content, and project loca- cost overrun. professionals generally agreed that
tion. On the other hand, the top five fac- Frimpong et al. (2003) concluded shortage of materials, methods of
tors from consultants view are previous that the main causes of delay and cost financing and payments for com-
experience of contract, type and size overruns in construction of groundwater pleted works, and poor contract man-
of contract and its content, payments, projects in Ghana are: monthly payment agement are the three major reasons
project location, and contract period. difficulties from agencies, poor contrac- for high construction costs.
Al-Najjar (2008) identified the essen- tor management, material procurement, 3. price fluctuation (in material) was
tial factors and their relative importance poor technical performances, and esca- identified as the most important
that affect cost overrun in construction lation of material prices. factor responsible for the escalation
projects in the Gaza strip. The study Azhar et al. (2008) conducted a of project costs.’’
illustrated that the top affecting fac- study in order to identify the major Nega (2008) found that the most
tors include: prices fluctuations of con- cost overrun factors in construction important causes of cost overrun
structions, contractor’s delay of mate- projects in Pakistan. 42 factors were in building construction projects in
rial delivery and equipment, and prices identified. They found that the top Ethiopia are inflation or increase in the
inflation. ten affecting factors are: fluctuation cost of construction materials, poor
Iyer et al. (2005) conducted a study in prices of raw materials, unstable planning and coordination, change
to identify the factors affecting cost per- cost of manufactured materials, high orders due to enhancement required
formance of Indian construction proj- cost of machineries, lowest bidding by clients, and excess quantity during
ects. 55 factors were identified. They procurement procedures, poor project construction.
cost of labor
cost of machinary
transportation cost
cost of insurance
waste on site
contract management
additional work
contractual procedure
disputes on site
poor planning
4) Environmental factors
level of competitors
manipulation of suppliers
economic instability
effects of weather
government policies
monopoly by suppliers
number of competitors
i. mahamid · n. dmaidi · risks leading to cost overrun in building construction fromconsultants’ perspective · pp 860 - 87 3 863
political situation
poor productivity
project location
5) Financing factors
currency exchange
inflationary pressure
project financing
A number of studies were conducted Questionnaire design Index (%) = ∑ a (n/N)∗100/5 (1)
to investigate the effects of cost overrun The questionnaire is divided into two Where; a is the constant express-
in construction projects. Table 1 summa- main parts. Part I is related to gen- ing weighting given to each response
rizes some of these effects as presented eral information for the company. The (ranges from 1 for very low up to 5 for
in some previous studies. consultants were requested to answer very high)
questions pertaining to their experi- n is the frequency of the responses
Research methodology ence in building construction and their N is total number of responses
41 factors that might affect cost overrun opinions about the percentage average Table 3 shows the scale used to
in building construction projects were cost overrun in building construction determine the severity and frequency
defined through a detailed literature projects they have experienced. Part levels for cost overrun factors. When
review. The similar factors were grouped II includes the list of the identified fac- the factor’s severity and frequency
under one main group; the factors were tors affecting cost overrun in building levels are calculated, its location in
divided into 5 groups: cost estimating, construction. For each factor two ques- the risk map is identified according to
construction items, project partici- tions were asked: what is the degree of Figure 1 and Table 4.
pants, environmental, and financing severity of this factor on cost overrun in Figure 1 and Table 4 show the stan-
(Table 2). The factors were tabulated building construction? And what is the dard risk map which is used to deter-
into a questionnaire form. Then the draft frequency of occurrence for this factor? mine the risk zone for each identified
questionnaire was discussed with some Both frequency and severity were cat- cost overrun factor. The map is 5x5
construction parties who are involved egorized on a five-point scale as follows: matrix with severity ranging from VL to
in building construction to evalu- very high, high, moderate, little and VH on the horizontal axis and frequency
ate the content of the questionnaire. very little (on 5 to 1 point scale). (with the same range) on the vertical
Modifications and changes have been axis. Three zones are presented in the
done. Recommendations for minimizing Data analysis map: green, yellow and red (The U.S.
cost overrun in building construction Frequency index (F.I) and severity index Federal Highway Administration Office
projects were emphasized in view of (S.I) are calculated for each factor of International Programs, 2007).
the results of the study. according to the following formula The zones have the following
characteristics:
� Green zone: risks in this zone are low
level, and can be ignored.
Index value (Scale) Severity Frequency
� Yellow zone: risks in this zone are of
≤ 20% very low (VL) very low (VL) moderate importance; if these things
20% - 40% low (L) low (L) happen, one can cope with them and
move on. However, if their frequency
40% - 60% moderate (M) moderate (M)
is moderate it should be reduced and
60% - 80% high (H) high (H) if their severity is moderate, it should
be controlled and reduced and a con-
80% - 100% very high (VH) very high (VH)
tingency plans should be in place just
Table 3. Scale used to identify factor’s severity and frequency level in case they do.
H
Frequency M
L
VL
VL L M H VH
Severity
� Red zone: risks in this zone are of contribution in identifying the risk map Size of cost overrun in building
critical importance. These are the top for the considered 41 factors in terms of construction projects
priorities, and are risks that a close severity and frequency using an ordinal The analysis of the participants’
attention should be paid to them. scale. A total of 26 consultants filled responses regarding the cost over-
the questionnaire. The response rate run in building construction projects
Results and findings of the by the consultants is 87%. reveals that 100% of respondents indi-
research Figure 2 shows the distribution of cated that the average cost overrun
the respondents according to their in building construction projects that
General characteristics of experience in building construction. they have experienced is between 10%
respondents It shows that most of respondents have and 30% of the original estimated cost
The questionnaire was sent out to a experience of more than 15 years in of a project. More illustration is shown
total of 30 consultants, asking their building construction. in Figure 3.
80 %
are located in the yellow zone. The table
60 % shows that there is no factor under this
40 % group is located in the green zone.
Factors related to project participants
20 %
Table 7 and Figure 6 illustrate the risk
0% map for factors related to project partici-
<5 5 to 10 10 to 15 > 15
pants. 6 factors are considered under
Experience (years) this group. The results indicate that all
Figure 2. Distribution of the respondents according to their experience factors under this group are located in
in building construction the red zone.
i. mahamid · n. dmaidi · risks leading to cost overrun in building construction fromconsultants’ perspective · pp 860 - 87 3 865
Frequency of consultants
100 %
Top affecting factors
Table 10 shows the top priority factors
80 %
that affecting cost overrun in building
responces
Frequency
Factor S.I Severity level F.I Map zone
level
Frequency
Factor S.I Severity level F.I Map zone
level
disputes on site
lack of coordination between designers and contractors
poor financial control on site
poor planning
previous experience of contract
relationship between managers and labors
� 6 factors are related to construction human related, meaning that these fac- Statistical analyses
parties tors could be controlled and reduced by Tables 12 presents the statistical analy-
� 8 factors are related to environmental improving the skills of the participants ses for the severity and frequency
group (i.e. contractors, consultants, design- responses of cost overrun factors as
� 3 factors are related to financing ers, owners, labors, and suppliers). assessed by consultants. The table con-
group The results are supported by some tains the computation of the weighted
It can be seen that all factors related investigated previous studies as mean, standard deviation, and coef-
to construction parties are identified shown in Table 11. ficient of variation. These statistics
as critical factors. These factors are are used to interpret the dispersion,
i. mahamid · n. dmaidi · risks leading to cost overrun in building construction fromconsultants’ perspective · pp 860 - 87 3 867
Frequency
Factor S.I Severity level F.I Map zone
level
Frequency
Factor S.I Severity level F.I Map zone
level
currency exchange
inflationary pressure
project financing
relationship between managers and labors 62.50 H 64.42 H 40.26 project participants
number of projects going at the same time 63.46 H 55.77 M 35.39 environmental
compactness, and the degree of homo- indicating that there is a good data Visually, it can be seen from Figure
geneity of the collected data consistency and agreement between 11 and Figure 12 that as the factors
Table 12 shows that the standard consultants on the severity and fre- weighted mean increase, the coeffi-
deviations of the cost overrun factors quency of the identified factors. cient of variation decrease, meaning
for severity and frequency responses Table 12 also shows that the sta- that the participants are highly agreed
are ranging from 0.55 to 1.24 and 0.63 tistical analyses of the severity and on the impact of the top affecting
to1.06, respectively. A visual indica- frequency responses have reasonable factors.
tion obtained from the scatter diagram coefficient of variations, ranging from
shown in Figure 9 and Figure 10 shows 15%-40% and 16%-43% respectively.
that the data has good compactness,
i. mahamid · n. dmaidi · risks leading to cost overrun in building construction fromconsultants’ perspective · pp 860 - 87 3 869
Critical cost overrun factor in this study Supported by
Poor planning Al-Juwaireh (1997), Nega (2008), and Azhar et al. (2008)
Lack of coordination between construction parties Iyer et al. (2005) and Nega (2008)
Long period between design and time of tendering Azhar et al. (2008)
Table 11. Comparison between findings of this study and previous studies
Conclusion the risk map for 41 cost overrun factors. is a good data consistency and agree-
This study is conducted to investigate 26 factors were concluded as critical ment between consultants on the
the cost overrun in Palestinian building factors. Inputs of the consultants under- severity and frequency of the identi-
construction projects from consultants’ line that the top five factors affecting fied cost overrun factors. It also shows
perspective through a questionnaire cost overrun in building construction that the participants are highly agreed
survey. The analysis of the participants’ projects are: political situation, fluc- on the impact and frequency of the top
responses reveals that the cost overrun tuation of prices of materials, level of affecting factors.
in building construction projects is a competitors, currency exchange, and Based on the study findings, the fol-
severe problem. 100% of the respon- economic instability. lowing points are suggested in order to
dents indicated that the average cost The statistical analyses of the sever- minimize and control cost overrun in
overrun that they have experienced is ity and frequency responses indicate building construction projects:
between 10% and 30% of the project’s that the data has good compactness � Training courses and workshops
estimated cost. The study also identified and homogeneity, meaning that there should be conducted to improve
i. mahamid · n. dmaidi · risks leading to cost overrun in building construction fromconsultants’ perspective · pp 860 - 87 3 871
2.00
managerial skills of project
1.80
participants
� Material prices and labor rates 1.60
should be updated continuously. 1.40
� Sufficient time should be given for
1.20
Standard Deviation
preparing feasibility studies, plan-
ning, design, information documen- 1.00
tation and tender submission. This 0.80
helps avoiding or minimizing late
0.60
changes
� Progress payment should be paid on 0.40
time 0.20
� More communication and coordina-
0.00
tion between project participants 0.00 1.00 2.00 3.00 4.00 5.00
during all project phases.
� Top management must react posi- Mean
References 2.00
40 % 19(6): 325-335.
i. mahamid · n. dmaidi · risks leading to cost overrun in building construction fromconsultants’ perspective · pp 860 - 87 3 873