Daftar Harga Satuan Pekerjaan Tahun Anggaran 2015 ...........................................................
Daftar Harga Satuan Pekerjaan Tahun Anggaran 2015 ...........................................................
PEKERJAAN PERSIAPAN
1 1 BH PEMBUATAN PAPAN NAMA PROYEK DIGITAL PRINTING A.4 35,000.00 216,000.00 - 251,000.00
PEKERJAAN DINDING
1 1 M2 PASANG BATA MERAH TEBAL 1/2 BATA 1 Pc : 5 Ps D.2 35,450.00 69,639.00 - 105,089.00
2 1 M2 PASANG DINDING BATU TEMPEL HITAM D.5 41,255.00 173,971.00 - 215,226.00
PEKERJAAN PLESTERAN
1 1 M2 PLESTERAN 1 Pc : 5 Ps + ACIAN E.3 44,705.00 10,754.00 - 55,459.00
HARGA SATUAN (Rp.) JUMLAH
NO. URAIAN PEKERJAAN KODE ANALISA
UPAH BAHAN ALAT (Rp.)
1 2 3 4 5 6 7 = (4+5+6)
PEKERJAAN LOGAM, PENUTUP LANTAI DAN DINDING -
1 1 M2 PASANG KERAMIK LANTAI PUTIH POLOS 40x40 CM G.8 56,817.50 85,503.50 - 142,321.00
PEKERJAAN PENGECATAN
1 M2 PENGECATAN TEMBOK BARU 1 LAPIS PLAMIR, 1 LAPIS
1 H.1 8,018.50 12,225.00 - 20,243.50
CAT DASAR, 2 LAPIS CAT PENUTUP
2 1 M2 CAT VERNIS BATU ALAM H.9 28,170.00 9,900.00 - 38,070.00
PEKERJAAN ALUMUNIUM
1 1 M2 MEMBUAT DINDING ALUCUBOND J.3 129,900.00 1,105,950.00 - 1,235,850.00
Indramayu, ……………...……2015
NO HARGA
URAIAN INDEKS SAT. UPAH (RP.) BAHAN (Rp.) JUMLAH (Rp.)
(KODE) SATUAN (Rp.)
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8=(6+7)
A.4 1 BH PEMBUATAN PAPAN NAMA PROYEK DIGITAL PRINTING
BAHAN
Cetak Nama Digital 1.000 Ls 30,000.00 - 30,000.00 #VALUE!
Kayu Reng 3/4 Kruing 0.006 M3 7,200,000.00 - 43,200.00 #VALUE!
Kayu Kaso 5/7 Kruing 0.028 M3 5,100,000.00 - 142,800.00 #VALUE!
UPAH
Design Cetak Nama Digital 1.000 Ls 15,000.00 15,000.00 - #VALUE!
Ongkos Pasang 1.000 Ls 20,000.00 20,000.00 - #VALUE!
JUMLAH .......................... 35,000.00 216,000.00 #VALUE!
NO HARGA
URAIAN INDEKS SAT. UPAH (RP.) BAHAN (Rp.) JUMLAH (Rp.)
(KODE) SATUAN (Rp.)
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8=(6+7)
D.2 1 M2 PASANG BATA MERAH TEBAL 1/2 BATA 1 Pc : 5 Ps
BAHAN
Bata Merah Bakar Kelas 1 70.000 Bh 675.00 - 47,250.00 #VALUE!
Semen Pc 9.680 Kg 1,425.00 - 13,794.00 #VALUE!
Pasir Pasang 0.045 M3 191,000.00 - 8,595.00 #VALUE!
UPAH
Pekerja 0.320 Org 75,000.00 24,000.00 - #VALUE!
Tukang Batu 0.100 Org 90,000.00 9,000.00 - #VALUE!
Kepala Tukang 0.010 Org 95,000.00 950.00 - #VALUE!
Mandor 0.015 Org 100,000.00 1,500.00 - #VALUE!
JUMLAH .......................... 35,450.00 69,639.00 #VALUE!
NO HARGA
URAIAN INDEKS SAT. UPAH (RP.) BAHAN (Rp.) JUMLAH (Rp.)
(KODE) SATUAN (Rp.)
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8=(6+7)
D.5 1 M2 PASANG DINDING BATU TEMPEL HITAM
BAHAN
Batu Tempel Hitam Uk. 10x20 Cm 1.100 M2 145,000.00 - 159,500.00 #VALUE!
Semen PC 6.000 Kg 1,425.00 - 8,550.00 #VALUE!
Pasir Pasang 0.031 M3 191,000.00 - 5,921.00 #VALUE!
UPAH
Pekerja 0.188 Org 75,000.00 14,062.50 - #VALUE!
Tukan Batu 0.225 Org 90,000.00 20,250.00 - #VALUE!
Kepala Tukang 0.038 Org 95,000.00 3,562.50 - #VALUE!
Mandor 0.034 Org 100,000.00 3,380.00 - #VALUE!
JUMLAH .......................... 41,255.00 173,971.00 #VALUE!
NO HARGA
URAIAN INDEKS SAT. UPAH (RP.) BAHAN (Rp.) JUMLAH (Rp.)
(KODE) SATUAN (Rp.)
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8=(6+7)
E.3 1 M2 PLESTERAN 1 Pc : 5 Ps + ACIAN
BAHAN
Semen Pc 5.000 Kg 1,425.00 - 7,125.00 #VALUE!
Pasir Pasang 0.019 M3 191,000.00 - 3,629.00 #VALUE!
UPAH
Pekerja 0.286 Org 75,000.00 21,450.00 - #VALUE!
Tukang Batu 0.214 Org 90,000.00 19,260.00 - #VALUE!
Kepala Tukang 0.021 Org 95,000.00 1,995.00 - #VALUE!
Mandor 0.020 Org 100,000.00 2,000.00 - #VALUE!
JUMLAH ……………………. 44,705.00 10,754.00 #VALUE!
NO HARGA
URAIAN INDEKS SAT. UPAH (RP.) BAHAN (Rp.) JUMLAH (Rp.)
(KODE) SATUAN (Rp.)
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8=(6+7)
G.8 1 M2 PASANG KERAMIK LANTAI PUTIH POLOS 40x40 CM
BAHAN
Keramik Putih 40x40 Cm 1.050 M2 65,000.00 - 68,250.00 #VALUE!
Semen PC 8.000 Kg 1,425.00 - 11,400.00 #VALUE!
Pasir Pasang 0.030 M3 191,000.00 - 5,730.00 #VALUE!
Semen Warna 0.013 Kg 9,500.00 - 123.50 #VALUE!
UPAH
Pekerja 0.188 Org 75,000.00 14,062.50 - #VALUE!
Tukang Batu 0.375 Org 90,000.00 33,750.00 - #VALUE!
Kepala Tukang 0.075 Org 95,000.00 7,125.00 - #VALUE!
Mandor 0.019 Org 100,000.00 1,880.00 - #VALUE!
JUMLAH .......................... 56,817.50 85,503.50 #VALUE!
H.1 1 M2 PENGECATAN TEMBOK BARU 1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP
BAHAN
Plamir Tembok 0.100 Kg 17,000.00 - 1,700.00 #VALUE!
Cat Dasar 0.100 Kg 24,500.00 - 2,450.00 #VALUE!
Cat Penutup 2x 0.260 Kg 24,500.00 - 6,370.00 #VALUE!
Roll Cat Tembok 0.010 Bh 20,500.00 - 205.00 #VALUE!
Ampelas 0.500 Lbr 3,000.00 - 1,500.00 #VALUE!
UPAH
Pekerja 0.020 Org 75,000.00 1,500.00 - #VALUE!
Tukang Cat 0.063 Org 90,000.00 5,670.00 - #VALUE!
Kepala Tukang 0.006 Org 95,000.00 598.50 - #VALUE!
Mandor 0.003 Org 100,000.00 250.00 - #VALUE!
JUMLAH .......................... 8,018.50 12,225.00 #VALUE!
NO HARGA
URAIAN INDEKS SAT. UPAH (RP.) BAHAN (Rp.) JUMLAH (Rp.)
(KODE) SATUAN (Rp.)
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8=(6+7)
H.9 1 M2 CAT VERNIS BATU ALAM
BAHAN
Vernis 0.150 Ltr 65,000.00 - 9,750.00 #VALUE!
Kuas 3" 0.010 Bh 15,000.00 - 150.00 #VALUE!
UPAH
Pekerja 0.160 Org 75,000.00 12,000.00 - #VALUE!
Tukang Cat 0.160 Org 90,000.00 14,400.00 - #VALUE!
Kepala Tukang 0.016 Org 95,000.00 1,520.00 - #VALUE!
Mandor 0.003 Org 100,000.00 250.00 - #VALUE!
JUMLAH .......................... 28,170.00 9,900.00 #VALUE!
J.3 1 M2 MEMBUAT DINDING ALUCUBOND
BAHAN
Plat Alucubon Ex. Australia 1.100 M3 915,000.00 - 1,006,500.00 #VALUE!
Besi Hollo 50/50 0.150 Kg 13,000.00 - 1,950.00 #VALUE!
Perlengkapan 1.000 Ls 97,500.00 - 97,500.00 #VALUE!
UPAH
Pekerja 1.200 Org 75,000.00 90,000.00 - #VALUE!
Tukang Las 0.430 Org 90,000.00 38,700.00 - #VALUE!
Kepala Tukang 0.012 Org 95,000.00 1,140.00 - #VALUE!
Mandor 0.001 Org 100,000.00 60.00 - #VALUE!
JUMLAH .......................... 129,900.00 1,105,950.00 #VALUE!
NO HARGA
URAIAN INDEKS SAT. UPAH (RP.) BAHAN (Rp.) JUMLAH (Rp.)
(KODE) SATUAN (Rp.)
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8=(6+7)
K.1 1 BH TITIK LAMPU LENGKAP
BAHAN
Kabel 2x2,5 mm 6.000 M' 12,000.00 - 72,000.00 #VALUE!
UPAH
Tukang Listrik 0.063 Org 90,000.00 5,670.00 - #VALUE!
Mandor 0.045 Org 100,000.00 4,500.00 - #VALUE!
JUMLAH .......................... 10,170.00 72,000.00 #VALUE!
K.2 1 BH PASANG SAKLAR DOUBLE/SERIE
BAHAN
Sakelar Serie 1.000 Bh 24,000.00 - 24,000.00 #VALUE!
UPAH
Tukang Listrik 0.063 Org 90,000.00 5,670.00 - #VALUE!
Mandor 0.045 Org 100,000.00 4,500.00 - #VALUE!
JUMLAH .......................... 10,170.00 24,000.00 #VALUE!
K.3 1 BH PASANG SAKLAR TUNGGAL
BAHAN
Sakelar Tunggal 1.000 Bh 18,000.00 - 18,000.00 #VALUE!
UPAH
Tukang Listrik 0.063 Org 90,000.00 5,670.00 - #VALUE!
Mandor 0.045 Org 100,000.00 4,500.00 - #VALUE!
JUMLAH .......................... 10,170.00 18,000.00 #VALUE!
K.4 1 BH PASANG STOP KONTAK
BAHAN
Stop Kontak 1.000 Bh 18,000.00 - 18,000.00 #VALUE!
UPAH
Tukang Listrik 0.063 Org 90,000.00 5,670.00 - #VALUE!
Mandor 0.045 Org 100,000.00 4,500.00 - #VALUE!
JUMLAH .......................... 10,170.00 18,000.00 #VALUE!
K.5 1 BH PASANG STOP KONTAK AC
BAHAN
Stop Kontak AC 1.000 Bh 65,000.00 - 65,000.00 #VALUE!
UPAH
Tukang Listrik 0.063 Org 90,000.00 5,670.00 - #VALUE!
Mandor 0.045 Org 100,000.00 4,500.00 - #VALUE!
JUMLAH .......................... 10,170.00 65,000.00 #VALUE!
K.6 1 BH PASANG BOX MCB
BAHAN
Box MCB (4 grup) 1.000 Bh 55,000.00 - 55,000.00 #VALUE!
MCB 4 buah 4.000 Bh 70,000.00 - 280,000.00 #VALUE!
UPAH
Tukang Listrik 0.063 Org 90,000.00 5,670.00 - #VALUE!
Mandor 0.045 Org 100,000.00 4,500.00 - #VALUE!
JUMLAH .......................... 10,170.00 335,000.00 #VALUE!
K.7 1 BH PASANG LAMPU PL 5 WATT+DUDUKAN
BAHAN
Lampu PL 5 Watt 1.000 Unit 31,000.00 - 31,000.00 #VALUE!
Dudukan Lampu 1.000 Unit 5,000.00 - 5,000.00 #VALUE!
UPAH
Tukang Listrik 0.063 Org 90,000.00 5,670.00 - #VALUE!
Mandor 0.045 Org 100,000.00 4,500.00 - #VALUE!
JUMLAH .......................... 10,170.00 36,000.00 #VALUE!
K.8 1 BH PASANG LAMPU PL 11 WATT+DUDUKAN
BAHAN
Lampu PL 11 Watt 1.000 Bh 34,000.00 - 34,000.00 #VALUE!
Dudukan Lampu 1.000 Bh 5,000.00 - 5,000.00 #VALUE!
UPAH
Tukang Listrik 0.063 Org 90,000.00 5,670.00 - #VALUE!
Mandor 0.045 Org 100,000.00 4,500.00 - #VALUE!
JUMLAH .......................... 10,170.00 39,000.00 #VALUE!
NO HARGA
URAIAN INDEKS SAT. UPAH (RP.) BAHAN (Rp.) JUMLAH (Rp.)
(KODE) SATUAN (Rp.)
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8=(6+7)
K.9 1 BH PASANG LAMPU PL 15 WATT+DUDUKAN
BAHAN
Lampu PL 15 Watt 1.000 Unit 38,000.00 - 38,000.00 #VALUE!
Dudukan Lampu 1.000 Unit 5,000.00 - 5,000.00 #VALUE!
UPAH
Tukang Listrik 0.063 Org 90,000.00 5,670.00 - #VALUE!
Mandor 0.045 Org 100,000.00 4,500.00 - #VALUE!
JUMLAH .......................... 10,170.00 43,000.00 #VALUE!
K.10 1 BH PASANG LAMPU PL 18 WATT+DUDUKAN DOWNLIGHT
BAHAN
Downlight 6" 1.000 Unit 57,000.00 - 57,000.00 #VALUE!
Lampu PL 18 watt 1.000 Bh 44,000.00 - 44,000.00 #VALUE!
UPAH
Tukang Listrik 0.063 Org 90,000.00 5,670.00 - #VALUE!
Mandor 0.045 Org 100,000.00 4,500.00 - #VALUE!
JUMLAH .......................... 10,170.00 101,000.00 #VALUE!
K.11 1 UNIT PASANG PENANGKAL PETIR
BAHAN
Kawat BC 35 mm 21.300 M' 49,000.00 - 1,043,700.00 #VALUE!
Pipa Tembaga/pentanahan P. 3 m 1.000 Btg 205,000.00 - 205,000.00 #VALUE!
Pipa Tembaga/tombak T. 0,5 m 2.000 Btg 55,000.00 - 110,000.00 #VALUE!
Perlengkapan 15% dari harga bahan 1.000 Ls 46,350.00 - 46,350.00 #VALUE!
UPAH
Pekerja 0.040 Org 75,000.00 3,000.00 - #VALUE!
Tukang Listrik 0.400 Org 90,000.00 36,000.00 - #VALUE!
Kepala Tukang 0.025 Org 95,000.00 2,375.00 - #VALUE!
Mandor 0.045 Org 100,000.00 4,500.00 - #VALUE!
JUMLAH .......................... 45,875.00 1,405,050.00 #VALUE!
NO HARGA
URAIAN INDEKS SAT. UPAH (RP.) BAHAN (Rp.) JUMLAH (Rp.)
(KODE) SATUAN (Rp.)
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8=(6+7)
L.12 1 M2 PASANG KACA POLOS T. 5 MM
BAHAN
Kaca Polos t. 5 mm 1.100 M2 117,000.00 - 128,700.00 #VALUE!
UPAH
Pekerja 0.015 Org 75,000.00 1,125.00 - #VALUE!
Tukang Kayu 0.150 Org 90,000.00 13,500.00 - #VALUE!
Kepala Tukang 0.015 Org 95,000.00 1,425.00 - #VALUE!
Mandor 0.001 Org 100,000.00 75.00 - #VALUE!
JUMLAH .......................... 16,125.00 128,700.00 #VALUE!
NO HARGA
URAIAN INDEKS SAT. UPAH (RP.) BAHAN (Rp.) JUMLAH (Rp.)
(KODE) SATUAN (Rp.)
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8=(6+7)
N.4a 1 M2 PASANG PARTISI DOUBLE GRC RANGKA HOLLO
BAHAN
Besi Hollo 40x40x0,34 mm 1.222 Btg 42,000.00 - 51,324.00 #VALUE!
Perlengkapan (35% dari harga hollo) 1.000 Ls 14,700.00 - 14,700.00 #VALUE!
Plat GRC 120x240x4 cm 0.364 Lbr 69,000.00 - 25,116.00 #VALUE!
UPAH
Pekerja 0.054 Org 75,000.00 4,050.00 - #VALUE!
Tukang Las 0.050 Org 90,000.00 4,500.00 - #VALUE!
Kepala Tukang 0.009 Org 95,000.00 855.00 - #VALUE!
Mandor 0.027 Org 100,000.00 2,700.00 - #VALUE!
JUMLAH .......................... 12,105.00 91,140.00 #VALUE!
NO HARGA
URAIAN INDEKS SAT. UPAH (RP.) BAHAN (Rp.) JUMLAH (Rp.)
(KODE) SATUAN (Rp.)
1 2 3 4 5 6 = (3 x 5) 7 = (3 x 5) 8=(6+7)
Indramayu, …………………2015
............................................................
RENCANA ANGGARAN BIAYA
KEGIATAN : PEMBANGUNAN HSRT BANDENG DAN KELENGKAPANNYA
PEKERJAAN : PEMBANGUNAN HATCHERY BANDENG
LOKASI : KECAMATAN JUNTINYUAT
SUMBER DANA DAK TAHUN ANGGARAN 2011
I. PEKERJAAN SANITARY
1 Pas. Pipa Suplay PVC dia. 4" SNI 59.00 M' O.13 #N/A #N/A
2 Pas. Pipa untuk Tiang PVC dia. 4" SNI 16.00 M' O.13 #N/A #N/A
3 Pas. Pipa untuk Telur PVC dia. 4" SNI 46.00 M' O.13 #N/A #N/A
4 Pas. Pipa Hisap PVC dia. 3" SNI ( Di Dasar Laut ) 25.00 M' O.12 #N/A #N/A
5 Pas. Stop Kran 4" SNI 10.00 Bh - 160,000.00 1,600,000.00
6 Pas. Pipa Cabut PVC 4" SNI, P. 1 M 3.00 M' O.13 #N/A #N/A
7 Pas. Pipa Cabut PVC 4" SNI, P. 2 M 6.00 M' O.13 #N/A #N/A
8 Pas. Pipa Cabut PVC 4" SNI, P. 3 M 9.00 M' O.13 #N/A #N/A
9 Pek. Besi Tangga Bak dia. 6" mm ( 250x250x350 ) 7.50 Kg F.5 17,990.00 134,925.00
10 Pek. Jaring Pengaman PVC dia. 2" SNI-PE 254.00 M2 - 0.00
11 Pas. Pipa Udara PVC - AW dia. 1/2" 54.50 M' O.10 #N/A #N/A
12 Pas. Stop Kran Pipa Oxigen 1/2" SNI 6.00 Bh - 46,000.00 276,000.00
13 Pas. Stop Kran dia. 6" SNI ( Saluran Ke Laut ) 1.00 Bh - 205,000.00 205,000.00
14 Pas. Dop dia. 4" SNI 1.00 Bh - 0.00
15 Pek. Pipa Galvanis 2" ( Pegangan Pipa 20 ttk, P. 1,5 M ) 30.00 M' O.13a #N/A #N/A
16 Pek. Pipa PVC Hisap Dasar Laut ( Lengkap ) 10" Berlubang 8.00 M' - 345,000.00 2,760,000.00
17 Upah Pemasangan Pipa 10" di Dasar Laut 1.00 Ls - 2,500,000.00 2,500,000.00
18 Pek. Isolasi Busa, Ijuk, Tali 1.00 Ls - 700,000.00 700,000.00
19 Pek. Pipa PVC Hisap Dasar Laut ( Lengkap ) 3" 20.00 M' - 55,000.00 1,100,000.00
20 Pek. Accessories Pipa ( V. Sock T ) 1.00 Ls - 1,500,000.00 1,500,000.00
21 Pek. Bak Air Disinfektan 400x300x15 Cm 2.00 M2 D.2 105,089.00 210,178.00
22 Pek. Bak Air Disinfektan 120x50x15 Cm 12.60 M2 D.2 105,089.00 1,324,121.40
23 Pek. Trap tangga bak telur
- Pas. Bata Merah (Pas 1/2 Bata) 1 Pc : 5 Ps 7.30 M2 D.1 110,817.25 808,965.93
- Pek. Plesteran 1 : 5 + Acian 15.90 M2 E.3 55,459.00 881,798.10
- Urugan Pasir 1.83 M3 B.6 45,625.00 83,493.75
24 Pek. Kanopi kayu Genteng Lama
- Kayu Balok Borneo 0.07 M3 - 4,222,250.00 295,557.50
- Pek. Gording kayu borneo 0.04 M3 Q.22 #N/A #N/A
- Pek Genteng 3.00 M2 M.1a #N/A #N/A
- Pek. Baud Ø 16 mm 4.00 Bh - 5,000.00 20,000.00
- Pek. Baud Ø 12 mm 4.00 Bh - 5,000.00 20,000.00
- Pek Rangka Atap Kayu Borneo 3.00 M2 Q.23 #N/A #N/A
- Pek. Pengecatan 3.60 M2 H.5 66,094.00 237,938.40
- Pek. Plafond GRC 3.00 M2 N.8d #N/A #N/A
JUMLAH I. #N/A
REKAPITULASI
Mengetahui : Dibuat :
Kepala Dinas Cipta Karya CV. DUTA GRAHA Consultant
Kabupaten Indramayu
JUMLAH I. ###
II. PEKERJAAN TANAH/PASIR
1 Pek. Galian Tanah 46.64 M3 B.1 34,000.00 1,585,760.00
2 Pek. Urugan Tanah kembali 11.66 M3 B.5 16,300.00 190,058.00
3 Pek. Urugan tanah site 383.93 M3 B.10 89,500.00 ###
4 Pek. Urugan Pasir alas pondasi plat t. 5 cm 5.58 M3 B.7 185,500.00 1,035,090.00
5 Pek. Urugan Pasir alas lantai t. 5 cm 9.91 M3 B.7 185,500.00 1,838,305.00
6 Pek. Urugan Pasir bawah rabat lantai t. 5 cm 1.89 M3 B.7 185,500.00 350,595.00
7 Pek. Urugan tanah peninggian lantai 18.04 M3 B.10 89,500.00 1,614,580.00
JUMLAH V. ###
VI. PEKERJAAN BETON K-175
1 Pek. Pondasi plat 60/60x20 1.89 M3 F.2+F.5a46+F.11a46 4,344,352.56 8,210,826.34
2 Pek. Lantai kerja bawah pondasi plat t.5 cm 0.30 M3 F.1 718,655.00 215,596.50
3 Pek. Sloof 15/20 4.17 M3 F.2+F.5a1+F.11a1 5,261,771.71 ###
4 Pek. Kolom teras 15/25 0.28 M3 F.2+F.5a16+F.11a16 6,407,411.53 1,794,075.23
5 Pek. Kolom praktis 12/12 2.63 M3 F.2+F.5a6+F.11a6 6,462,891.59 ###
6 Pek. Balok Latei 12/15 2.07 M3 F.2+F.5a41+F.11a41 6,462,891.59 ###
7 Pek. Ring Balok 15/20 4.17 M3 F.2+F.5a23+F.11a23 5,261,771.71 ###
8 Pek. Balok teras 15/25 0.26 M3 F.2+F.5a25+F.11a25 5,592,356.27 1,454,012.63
9 Pek. Beton tumbuk lantai dan rabat t. 5cm 11.80 M3 F.1 718,655.00 8,480,129.00
10 Pek. Cor Meja Beton t.10 cm 0.25 M3 F.2+F.5a43+F.11a43 3,920,796.71 980,199.18
11 Pek. Beton kanopi L. 40 cm, T. 8 cm 0.22 M3 F.3+F.5a41+F.11a41 3,678,345.45 809,236.00
JUMLAH X. #REF!
#VALUE!
Plt. Kepala Dinas Kesehatan Selaku Pejabat Pelaksana Teknis Kegiatan (PPTK)
Pejabat Pembuat Komitmen Dinas Kesehatan
Kab. Indramayu Kabupaten Indramayu
KEGIATAN :
PEKERJAAN :
LOKASI :
SUMBER DANA :
JUMLAH
HARGA
NO. URAIAN PEKERJAAN VOLUME ANALISA PELAKSANAAN
SATUAN (Rp)
(Rp)
1 2 3 4 5 6=3x5
JUMLAH I. 4,251,000.00
1 2 3 4 5 6=3x5
1 2 3 4 5 6=3x5
JUMLAH V. 925,086.50
JUMLAH I. #VALUE!
1 2 3 4 5 6=3x5
2 Pas. Saklar double/serie 1.00 Bh K.2 34,170.00 34,170.00
3 Pas. Saklar tunggal 1.00 Bh K.3 28,170.00 28,170.00
4 Pas. Stop Kontak 5.00 Bh K.4 28,170.00 140,850.00
5 Pas. Stop Kontak AC 1.00 Bh K.5 #VALUE! #VALUE!
6 Pas. Lampu PL 18 watt + dudukan downLight Ø 6'' 3.00 Bh K.10 111,170.00 333,510.00
7 Pas. AC 1 PK Setara LG 1.00 Bh Ls 5,500,000.00 5,500,000.00
JUMLAH I. #VALUE!
1 2 3 4 5 6=3x5
#VALUE!
Diperiksa : Dibuat :
.................................. ..................................
.....................................
.................................. Direktur
NIP :,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,
Disetujui : Mengetahui :
.................................. ......................................
..................................... .....................................
NIP ,,,,,,,,,,,,,,,,,,,,,,, NIP :
Disetujui : Mengetahui :
.................................. ......................................
JUMLAH
HARGA
NO. URAIAN PEKERJAAN VOLUME ANALISA PELAKSANAAN
SATUAN (Rp)
(Rp)
1 .....................................
2 3
.....................................
4 5 6=3x5
NIP ,,,,,,,,,,,,,,,,,,,,,,, NIP :
DAFTAR HARGA UPAH PEKERJA
TAHUN ANGGARAN 2015
............................................................
1 2 3 4 5
Indramayu, …………………2015
............................................................
.................................................
Direktur
DAFTAR HARGA BAHAN BANGUNAN
TAHUN ANGGARAN 2015
CV. DUTA GRAHA Consultant
1 2 3 4 5
1 2 3 4 5
16 Kayu Meranti batu, papan M3 5,200,000.00
17 Kayu Stoot Btg 55,000.00
18 Reng kruing 3/4 M3 7,200,000.00
19 Reng Borneo 2/3 M3 3,775,000.00
20 Reng kruing 2/3 M3 5,290,000.00
21 Kaso Albasia 5/7 M3 2,500,000.00
22 Kaso Borneo 5/7 M3 3,700,000.00
23 kaso Kruing 5/7 M3 5,100,000.00
24 Multiplek 9 mm (120x240) Lmb 135,000.00
25 Multiplek 12 mm (120x240) Lmb 185,000.00
26 Triplek 3 mm Lmb 55,000.00
27 Triplek 4 mm Lmb 66,000.00
28 Triplek 6 mm Lmb 78,000.00
29 List Kayu Profil M' 11,000.00
30 Dolken d. 8-10/400 cm Btg 78,000.00
1 2 3 4 5
38 Rangka Atap Baja Ringan Zingallum C (0.75-1.00 mm) Reng 32 M2 179,000.00
39 Polycarbonate Sheet/Twin lite UK. 11,8 x 2,1 Lmb 2,100,000.00
40 Folding Gate (Pintu lipat) M2 480,000.00
NO. JENIS BAHAN SATUAN HARGA (Rp.) KET.
1 2 3 4 5
41 Sliding Door (Pintu geser) Unit 290,000.00
42 Fiber glass (Acyrlic) tebal 5 mm Lmb 1,050,000.00
43 Rolling Door 0.4mm/Grile M2 325,000.00
44 Pagar BRC ulir t. 120 cm, p. 240 cm Lmb 420,000.00
45 Door Closer Bh 225,000.00
1 2 3 4 5
1 2 3 4 5
6 Keramik putih polos 40x40 cm kw. 1 M2 65,000.00
7 Keramik warna/corak 40x40 cm M2 75,000.00
8 Keramik warna/corak 20x25 cm M2 52,000.00
9 Keramik putih polos 20x25 cm M2 48,000.00
10 Granit warna/corak 60x60 cm M2 205,000.00
11 Keramik Essenza 40x40 cm M2 225,000.00
12 Stiffnes Tangga 10x40 Bh 27,000.00
13 Kuku Macan Polos M' 75,000.00
14 Kuku Macan Spiral M' 80,000.00
15 Parquet jati M2 160,000.00
F. BAHAN KACA
1 Kaca polos t. 3 mm M2 70,000.00
2 Kaca polos ES t. 3 mm M2 77,000.00
3 Kaca polos t. 5 mm M2 117,000.00
4 Kaca polos ES t. 5 mm M2 139,000.00
5 Kaca Rayband t. 3 mm M2 83,000.00
6 Kaca Rayband t. 5 mm M2 123,000.00
1 2 3 4 5
7 Expanolete Ps 105,000.00
NO. JENIS BAHAN SATUAN HARGA (Rp.) KET.
1 2 3 4 5
H. BAHAN ALAT LISTRIK
1 Box MCB ( 4 group ) Bh 55,000.00
2 MCB Bh 70,000.00
3 Saklar tunggal Bh 18,000.00
4 Saklar double Bh 24,000.00
5 Stop Kontak Bh 18,000.00
6 Stop Kontak AC Bh 65,000.00
7 Lampu Pijar 25 watt Bh 15,000.00
8 Lampu PL 5 Watt Bh 31,000.00
9 Lampu PL 11 Watt Bh 34,000.00
10 Lampu PL 18 watt Bh 44,000.00
11 Lampu PL 15 Watt Bh 38,000.00
12 Lampu TL 2 x 20 watt + Kap Bh 95,000.00
13 Lampu TL 1 x 40 watt + Kap Bh 88,000.00
14 Dudukan Lampu TL max. 1x18 W Bh 42,000.00
15 Dudukan Lampu PL Bh 5,000.00
16 Dudukan Lampu downlight bahan stainlesstell 6" Bh 57,000.00
17 Kabel NYM 2 x 1,5 mm M' 11,000.00
18 Kabel NYM 2 x 2,5 mm M' 12,000.00
19 Kabel NYM 3 x 1,5 mm M' 13,000.00
20 Kabel NYM 3 x 2,5 mm M' 14,000.00
21 Kawat BC 25 mm M' 41,000.00
22 Kawat BC 35 mm M' 49,000.00
23 Tombak Tembaga (Arde) Btg 55,000.00
24 Tombak Tembaga (Arde petir) Btg 205,000.00
I. ALAT BANTU
1 Cangkul/sekop Bh 55,000.00
2 Parang Bh 60,000.00
3 Pikulan dan 2 bakul Bh 35,000.00
Indramayu, …………………2015
............................................................
0.00
.................................................
Direktur
Analisa Harga Satuan ini hanya ANALISA HARGA SATUAN
KODE
dipergunakan sebagai dasar/ pendekatan GALIAN TANAH UNTUK KONSTRUKSI
dalam menyusun DASK dan mengevaluasi
Harga Penawaran K.224
(MENGGUNAKAN BURUH)
PROSES : ANGGAPAN :
Pekerjaan ini harus dilaksanakan sesuai : 1. Menggunakan alat berat (40 m3/hari)
2. Kapasitas kerja per orang 1,3 M3/hari
1. Bab satuan pekerjaan ini, spesifikasi umum 3. Kedalaman rata-rata galian sampai dengan 3 m
Jalan Kabupaten, Bina Marga, Maret 1992 4. Umur alat bantu rata-rata 1 bulan / orang / @ 3 set
PEKERJA #REF!
HARGA SUB JUMLAH
NO. MATERIAL SATUAN KODE TOTAL VOL BIAYA (Rp.)
SATUAN (Rp.) (Rp.)
MATERIAL 97,560.00
HARGA SUB JUMLAH
NO. PERALATAN JUMLAH HARI KERJA KODE JAM KERJA BIAYA (Rp.)
(Rp./Jam) (Rp.)
PERALATAN -
TOTAL (Rp.) #REF!
PROSES : ANGGAPAN :
PEKERJA #REF!
HARGA SUB JUMLAH
NO. MATERIAL SATUAN KODE TOTAL VOL BIAYA (Rp.)
SATUAN (Rp.) (Rp.)
MATERIAL #REF!
HARGA SUB JUMLAH
NO. PERALATAN JUMLAH HARI KERJA KODE JAM KERJA BIAYA (Rp.)
(Rp./Jam) (Rp.)
PERALATAN 2,393,000.00
TOTAL (Rp.) #REF!
PROSES : ANGGAPAN :
Pekerjaan ini harus dilaksanakan sesuai : 1. Menggunakan alat berat ( 200 M3/hari )
2. 20 % dibuang di lokasi tanpa diangkut dengan truck
1. Bab satuan pekerjaan ini, spesifikasi umum 3. 80 % dibuang dan diangkut dengan truck
Jalan Kabupaten, Bina Marga, Maret 1992 4. Jarak 1 Rit PP < 2 Km
5. 2,5 Rit PP/Jam/Truck
2. Atau Addendum yang berlaku.
PEKERJA #REF!
HARGA SUB JUMLAH
NO. MATERIAL SATUAN KODE TOTAL VOL BIAYA (Rp.)
SATUAN (Rp.) (Rp.)
MATERIAL 19,512.00
HARGA SUB JUMLAH
NO. PERALATAN JUMLAH HARI KERJA KODE JAM KERJA BIAYA (Rp.)
(Rp./Jam) (Rp.)
PROSES : ANGGAPAN :
Pekerjaan ini harus dilaksanakan sesuai : 1. Menggunakan alat berat ( 8 m x 500 m / hari
2. DAMIJA dibersihkan dari semak dll.
1. Bab satuan pekerjaan ini, spesifikasi umum 3. Lebar dasar jalan 8 m
Jalan Kabupaten, Bina Marga, Maret 1992
PEKERJA #REF!
HARGA SUB JUMLAH
NO. MATERIAL SATUAN KODE TOTAL VOL BIAYA (Rp.)
SATUAN (Rp.) (Rp.)
MATERIAL 260,160.00
HARGA SUB JUMLAH
NO. PERALATAN JUMLAH HARI KERJA KODE JAM KERJA BIAYA (Rp.)
(Rp./Jam) (Rp.)
PROSES : ANGGAPAN :
Pekerjaan ini harus dilaksanakan sesuai : 1. Menggunakan alat berat ( 8 m x 500 m / hari )
2. DAMIJA dibersihkan dari semak dll.
1. Bab satuan pekerjaan ini, spesifikasi umum 3. Lebar dasar jalan 8 m
Jalan Kabupaten, Bina Marga, Maret 1992 4. Hasil kerja menyiapkan dasar jalan 500 m / hari
PEKERJA #REF!
HARGA SUB JUMLAH
NO. MATERIAL SATUAN KODE TOTAL VOL BIAYA (Rp.)
SATUAN (Rp.) (Rp.)
MATERIAL 13,008.00
HARGA SUB JUMLAH
NO. PERALATAN JUMLAH HARI KERJA KODE JAM KERJA BIAYA (Rp.)
(Rp./Jam) (Rp.)
PERALATAN 1,938,000.00
TOTAL (Rp.) #REF!
PROSES : ANGGAPAN :
Pekerjaan ini harus dilaksanakan sesuai : 1. Menggunakan alat berat (200 m3/ hari, pemadatan 2000 m bahu jalan/ hari
2. 10 cm timbunan padat dibutuhkan untuk 1 m lebar bahu jalan
1. Bab satuan pekerjaan ini, spesifikasi umum 3. Material timbunan yang termurah dikirim ke lokasi pekerjaan oleh pemasok
Jalan Kabupaten, Bina Marga, Maret 1992 4. Pemasok menimbun material timbunan sepanjang bahu jalan
5. Material disebar dengan grader
2. Atau Addendum yang berlaku. 6. 200 m3 dihampar dan dipadatkan setiap hari
7. Koefisien pemadatan 1,4
PEKERJA #REF!
HARGA SUB JUMLAH
NO. MATERIAL SATUAN KODE TOTAL VOL BIAYA (Rp.)
SATUAN (Rp.) (Rp.)
MATERIAL 6,388,192.00
HARGA SUB JUMLAH
NO. PERALATAN JUMLAH HARI KERJA KODE JAM KERJA BIAYA (Rp.)
(Rp./Jam) (Rp.)
PERALATAN 1,631,000.00
TOTAL (Rp.) #REF!
PROSES : ANGGAPAN :
Pekerjaan ini harus dilaksanakan sesuai : 1. Menggunakan tenaga manusia (150 M3 / hari )
2. Grader memotong bahu jalan setinggi 10 cm, selebar 1,5 m,
1. Perbaiki bahu jalan yang tingginya sepanjang 1 Km pada satu sisi jalan
melebihi permukaan jalan antara parit 3. Jarak membuang 1 rit PP < 2 Km
dan perkerasan jalan 4. 2,5 Rit PP / jam / truck
2. Menggunakan loader untuj membuat sisa
galian ke dump truck
3. Buang semua sisa galian
PEKERJA #REF!
HARGA SUB JUMLAH
NO. MATERIAL SATUAN KODE TOTAL VOL BIAYA (Rp.)
SATUAN (Rp.) (Rp.)
MATERIAL 19,512.00
HARGA SUB JUMLAH
NO. PERALATAN JUMLAH HARI KERJA KODE JAM KERJA BIAYA (Rp.)
(Rp./Jam) (Rp.)
PROSES : ANGGAPAN :
Pekerjaan ini harus dilaksanakan sesuai : 1. Menggunakan tenaga manusia (150 M3 / hari )
2. Buldozer memotong dan meratakan tanah
1. Perbaiki bahu jalan yang tingginya 3. Koefisien pemadatan tanah = 1,3
melebihi permukaan jalan antara parit
dan perkerasan jalan
2. Menggunakan loader untuk memotong dan
mendorong tanah
3. Pemadatan tanah dengan menggunakan
mesin gilas 3 Roda 6 - 8 ton
4. Buang semua sisa galian
PEKERJA #REF!
HARGA SUB JUMLAH
NO. MATERIAL SATUAN KODE TOTAL VOL BIAYA (Rp.)
SATUAN (Rp.) (Rp.)
MATERIAL 19,512.00
HARGA SUB JUMLAH
NO. PERALATAN JUMLAH HARI KERJA KODE JAM KERJA BIAYA (Rp.)
(Rp./Jam) (Rp.)
PROSES : ANGGAPAN :
Pekerjaan ini harus dilaksanakan sesuai : 1. Menggunakan alat berat (150 m3/hari)
2. Material ditimbun sepanjang jalan oleh pemasok
1. Bab satuan pekerjaan ini, spesifikasi umum 3. 6 % sirtu dengan ukuran lebih dipisah pada saat penghamparan
Jalan Kabupaten, Bina Marga, Maret 1992 dengan grander
4. Lapisan pondasi bawah dipadatkan samai tebal padat 15 cm
2. Atau Addendum yang berlaku. 5. Koefisien pemadatan = 1,3
PEKERJA #REF!
HARGA SUB JUMLAH
NO. MATERIAL SATUAN KODE TOTAL VOL BIAYA (Rp.)
SATUAN (Rp.) (Rp.)
MATERIAL #REF!
HARGA SUB JUMLAH
NO. PERALATAN JUMLAH HARI KERJA KODE JAM KERJA BIAYA (Rp.)
(Rp./Jam) (Rp.)
PERALATAN 1,902,000.00
PROSES : ANGGAPAN :
PEKERJA #REF!
HARGA SUB JUMLAH
NO. MATERIAL SATUAN KODE TOTAL VOL BIAYA (Rp.)
SATUAN (Rp.) (Rp.)
MATERIAL #REF!
HARGA SUB JUMLAH
NO. PERALATAN JUMLAH HARI KERJA KODE JAM KERJA BIAYA (Rp.)
(Rp./Jam) (Rp.)
PERALATAN 1,167,000.00
PROSES : ANGGAPAN :
Pekerjaan ini harus dilaksanakan sesuai : 1. Menggunakan alat berat (150 m3/hari)
2. Material ditimbun sepanjang jalan oleh pemasok
1. Bab satuan pekerjaan ini, spesifikasi umum 3. Dihampar dan dipadatkan sampai tebal padat 10 cm
Jalan Kabupaten, Bina Marga, Maret 1992 4. Koefisien pemadatan = 1,3
PEKERJA #REF!
HARGA SUB JUMLAH
NO. MATERIAL SATUAN KODE TOTAL VOL BIAYA (Rp.)
SATUAN (Rp.) (Rp.)
MATERIAL #REF!
HARGA SUB JUMLAH
NO. PERALATAN JUMLAH HARI KERJA KODE JAM KERJA BIAYA (Rp.)
(Rp./Jam) (Rp.)
PERALATAN 1,902,000.00
PROSES : ANGGAPAN :
PEKERJA #REF!
HARGA SUB JUMLAH
NO. MATERIAL SATUAN KODE TOTAL VOL BIAYA (Rp.)
SATUAN (Rp.) (Rp.)
MATERIAL #REF!
HARGA SUB JUMLAH
NO. PERALATAN JUMLAH HARI KERJA KODE JAM KERJA BIAYA (Rp.)
(Rp./Jam) (Rp.)
PERALATAN 5,137,500.00
TOTAL (Rp.) #REF!
PROSES : ANGGAPAN :
Pekerjaan ini harus dilaksanakan sesuai : 1. Harga bahan, perangko ( siap dilokasi )
2. Perbandingan aspal dengan minyak tanah = 100 bagian aspal : 100
1. Bab satuan pekerjaan ini, spesifikasi umum bagian minyak tanah, berdasarkan berat
Jalan Kabupaten, Bina Marga, Maret 1992 3. Berat jenis minyak tanah 0,86
4. Berat jenis aspal 1,03
2. Atau Addendum yang berlaku.
PEKERJA #REF!
HARGA SUB JUMLAH
NO. MATERIAL SATUAN KODE TOTAL VOL BIAYA (Rp.)
SATUAN (Rp.) (Rp.)
MATERIAL #REF!
HARGA SUB JUMLAH
NO. PERALATAN JUMLAH HARI KERJA KODE JAM KERJA BIAYA (Rp.)
(Rp./Jam) (Rp.)
PERALATAN 300,000.00
TOTAL (Rp.) #REF!
PROSES : ANGGAPAN :
Pekerjaan ini harus dilaksanakan sesuai : 1. Harga bahan, perangko ( siap dilokasi )
2. Perbandingan aspal dengan minyak tanah = 100 bagian aspal : 25
1. Bab satuan pekerjaan ini, spesifikasi umum bagian minyak tanah, berdasarkan berat
Jalan Kabupaten, Bina Marga, Maret 1992 3. Berat jenis minyak tanah 0,86
PEKERJA #REF!
HARGA SUB JUMLAH
NO. MATERIAL SATUAN KODE TOTAL VOL BIAYA (Rp.)
SATUAN (Rp.) (Rp.)
MATERIAL #REF!
HARGA SUB JUMLAH
NO. PERALATAN JUMLAH HARI KERJA KODE JAM KERJA BIAYA (Rp.)
(Rp./Jam) (Rp.)
PERALATAN 213,000.00
TOTAL (Rp.) #REF!
PROSES : ANGGAPAN :
Pekerjaan ini harus dilaksanakan sesuai : 1. Menggunakan alat berat 1500 m2/hari
2. Hot Rolled Sheet (Lataston) dikirim ke lokasi pekerjaan oleh
1. Bab satuan pekerjaan ini, spesifikasi umum pemasok dari AMP
Jalan Kabupaten, Bina Marga, Maret 1992 3. Tebal padat rata-rata 3 cm
4. BJ Lataston padat 2,2 ton/m3
2. Atau Addendum yang berlaku. 5. Sesuai spek. B.M. No.12/PT/B/1983 (tebal 3,3) dan rev.Spek.Umum
B.M Maret '89-Buku 3
PEKERJA #REF!
HARGA SUB JUMLAH
NO. MATERIAL SATUAN KODE TOTAL VOL BIAYA (Rp.)
SATUAN (Rp.) (Rp.)
MATERIAL #REF!
HARGA SUB JUMLAH
NO. PERALATAN JUMLAH HARI KERJA KODE JAM KERJA BIAYA (Rp.)
(Rp./Jam) (Rp.)
BULLDOZER D.65.D
Kecepatan Alat Dorong / Isi = 2 Km / Jam
Mundur / Dosong = 6 Km / Jam
Kecepatan Rata-rata = 4 Km / Jam
Lebar alat = 2 M'
Banyak Lintasan = 4 Lintasan
Tebal Lapisan = 0.20 M'
FIBRO GETAR
Kecepatan Alat Kecepatan Alat Rata-rata = 5 Km / Jam
Lebar alat = 1.5 M'
Banyak Lintasan = 8 Lintasan
Tebal Lapisan = 0.2 M'