Professional Documents
Culture Documents
Overview of Drilling Operations MAY 2011 SEM
Overview of Drilling Operations MAY 2011 SEM
PAB 2024
1
LESSON OBJECTIVES
At the end of this lesson you should be able to:
1. Describe the process of rotary drilling;
2. Determine Rig Selection;
3. Describe the data Acquisition and Monitoring
System
2
INTRODUCTION
• Drilling for oil and natural gas requires two major
constituents: manpower and hardware systems.
3
The Process of Rotary Drilling
• several elements are needed
to drill the hole successfully
and economically (illustrated
in fig. 1-2), including:
6
The Process of Rotary Drilling
7
Rotary Drilling Rigs
• The power of rotary rigs is generally generated
by diesel or gas-driven engines.
8
Rotary Drilling Rigs
The electric drive system was introduced to
rotary rigs in the mid of 50’s for use in offshore
operations.
9
Rotary Drilling Rigs
• The overall efficiency of power-generating
systems defined as follows:
1-1a
or
1-1b
11
Rotary Drilling Rigs
• Example 1
A drilling rig has three diesel engines for generating the rig power requirement.
Determine the total daily fuel consumption for an average engine running speed
of 900 rpm, average output torque of 1,610 ft-lbs, and engine efficiency of 40%.
The heating value of diesel oil is 19,000 BTU/lb.
Solution:
From equations ( 1.1)-(1.3), the fuel consumption per engine can be solved
for and is given by :
12
Rotary Drilling Rigs
• Hence:
13
Rig Selection
• The main objective of rig selection is to choose from the available
rigs the one that will closely meet the criterion for drilling a usable
hole at the lowest overall cost of the proposed well.
14
Rotary Drilling System
• Hoisting System
Function: to hoist the drill and casing strings
during drilling and casing operations,
respectively.
15
HOISTING SYSTEM
• Consist of :
1. Draw Work
2. Crown Block
3. Dead Line anchor
4. Travelling Block
5. Hook
6. Drilling line
16
HOISTING SYSTEM
• Hoisting Design Consideration
The procedure to carrying out hoisting design calculation are as
follow:
1. Determine the deepest hole to be drilled;
2. Determine the worst drilling loads or casing load;
3. To select drilling line and derrick capacity.
17
HOISTING SYSTEM
• Example 2
The following well data refer to a 1.5 inch block line with 10 lines strung of extra improved
plough Steel wire rope strung to travelling block.
Table-1
Hole depth = 10,000 ft
Drillpipe = 5 inch OD; 4.27 inch ID, 19.5 lb/ft
Drill collars = 500 ft, 8 inch / 2.825 inch, 150 lb/ft
Mud weight = 10 ppg
Line and sheave efficiency Coefficient = 0.9616
Buoyancy factor = 0.847
Determine:
1. Weight of drill string in air and mud;
2. Hook load, assuming weight of travelling block and hook to be 23,500 lb;
3. Dead line and fast line loads, assuming an efficiency factors of 0.81
4. Dynamic crown load;
5. Wire line design factor during drilling if breaking strengths of wire is 228,000 lb;
6. Wire line design factor when running casing 7 inch of 29lb/ft.
18
HOISTING SYSTEM
• Solution
1. Weight drill string in air (unit in lb) :
Weight of DP and DC (unit in lb)
Where : N: number of line strung, K = Line efficiency per sheave (see Table-1)
HL : Hook Load, lb
19
HOISTING SYSTEM
4. Dynamind Crown Load (unit in lb) :
Dead line load + fast line load + Hook Load
20
Rotary Drilling System
• Drawworks
3. To determine the drawworks horsepower required for drilling a well, the hook horsepower is
first calculated using the weight of the heaviest drill string in air, along with a reasonable
hoisting speed. A minimum of 100 ft/min is recommended for rating a rig.
An overall hoisting efficiency of 65% is recommended to calculate the required drawworks
horsepower rating .
21
Rotary Drilling System
• Example 3:
What minimum drawworks horsepower is required in order to drill a well
when using 10,000 ft of 16.6 lb/ft drill pipe with an outside diameter (OD) of
4 ½ inches (in.) and 50,000 lbs of drill collars? (the rotary table speed of
100 ft/min) and overall hoisting efficiency of 65%.
Solution:
22
Rotary Drilling System
Block and drilling line.
• The principle function is to provide a mechanical advantage while raising and
lowering the extremely heavy loads into the wellbore. Their efficiency is measured
by equation (1-1a).
• The output power is define as follows: The input power is define :
1-4 1-5
23
Rotary Drilling System
The magnitude of Ftp depends on the number of lines strung between the crown
Block and the traveling block and the frictional forces induced between the contact
surfaces of the lines and block sheaves. Utilizing equations (1.4) and (1.5), equation
(1.1a) becomes :
1-6
1-7
24
Rotary Drilling System
• Therefore ,
1-8
where n is the number of lines strung between the crown block and the traveling
block.
Example 1-4 .
A rotary rig that can handle triples is equipped with 1.200 hp draw-works and 90 ft
line strung (Ls). The output of the drawwork is 927 hp and the efficiency of the
hoisting system is 81%. Determine the time it takes to pull one stand at a hook load
of 300,000Ibs.
25
Rotary Drilling System
• Solution:
26
Rotary Drilling System
This method neglects the effect of buoyancy and the weight of
the block and hook. In straight holes, buoyancy can be assumed
to be offset by pipe drag. In directional holes, drag has to be
Considered.
27
Mud System Evaluation
• The function of the Fluid circulating system in rotary
drilling is to allow the movement of a drilling fluid
from the surface to the hole bottom and back to
surface again. The main components of the system
include
• Mud pumps/air compressors
• High-pressure surface connections
• Drill string
• Drill bit
• Return annulus
• Mud pits
• Mud treatment equipment
28
Mud System Evaluation
• Mud pumps
Rotary rig pumps are reciprocating
positive-displacement units and are
either duplex or triplex pumps.
Duplex pumps have two liners and
move fluid on the forward and
backward stokes (double acting).
Triplex pumps have three liners and
move fluids only on the forward stoke
(single acting).
29
Mud System Evaluation
Example 5 (Horse Power req. of mud Pump)
Calculate the power requirement for the following pump:
Flow rate = 1200 gpm; pump pressure = 2000 psi and
mechanical efficiency = 0.85
Solution:
- Determine hydraulic HP = (Flow rate (gpm) x Pressure) / 1713.6
- Power equired from motor = hydraulic HP / mechanical eff.
30
Well Control System
• Primary Function??
The system requirements are to safely permit:
1) shutting in the well at the surface,
(2) controlling the removal of formation fluids from
the wellbore.
(3) pumping higher-density mud into the hole, and
(4) stripping the drill pipe in to or out of the hole.
31
Well Control System
• The basic components of the well control system are:
• Annular preventer
1. Ram preventers
2. Spools
3. Internal preventers
4. Casing head
5. Flow and choke lines and fittings
6. Kill lines and connections
7. Mud- and gas-handling facilities
8. Accumulators
• Ram preventer
Pipe ram preventers are mechanical
devices that close in the annular space
around the drill pipe or casing when they
are hydraulically activated.
33
Well Control System
• Rams that are designed to close in the annulus
when no pipe is present are called blind rams.
• Rams that are designed to shear off drill pipe
while string is in hole are referred to as shear
rams.
• These kind of rams are activated only if all
other preventers fail to shut the well.
34
Well Control System
• Annular preventer : well control devices that
employ a ring of reinforced synthetic rubber
as a packing unit that surround the drill string
to cause the shut- off.
• These preventers will close and shut in the
well regardless of the shape or diameter of
the conduit that might be in the hole.
35
Well Control System
• Drilling spools
• are drill-through-type fittings that are placed
in the BOP stack assembly to provide space
between two consecutive pipe rams for
temporary storage of tool joints during
stripping operations and to allow attachment
of the kill and choke lines.
36
Data Acquisition and Monitoring System
37
Data Acquisition and Monitoring System
• Drilling problems ?
• can be easily detected by the monitoring
equipment.
• Drilling breaks, which are easily seen on the
drilling rate chart can provide information on
changes of lithology and formation pressures.
• Excessive torques may indicate a bit bearing
failure or an extremely high concentration of
drilled cuttings in the wellbore annulus.
38
Data Acquisition and Monitoring System
40
Special Systems for Offshore Drilling
• Riser system and components
The marine riser is an extension of the
wellbore from the ocean floor to the derrick
floor above the water surface. Its purpose is to
guide and protect the drill string and to serve
as a conduit for the return of drilling fluid and
cutting to the surface
41
Special Systems for Offshore Drilling
Large fixed-end moments are avoided by using ball joints at the riser ends. Ball joints
are normally designed for rotations of up to 8-100 in any direction However, the drill
string has to pass freely through the joints, which limits the drilling operation to bail
joint angles of at maximum. 4-5°.
42
Marine Riser
43
SUPPLEMENTARY PROBLEM
• PROBLEM-1:
The following well data refer to a 1.5 inch block line with 10 lines strung of extra improved
plough Steel wire rope strung to travelling block.
Table-1
Hole depth = 12,000 ft
Drillpipe = 5 inch OD; 4.27 inch ID, 19.5 lb/ft
Drill collars = 500 ft, 8 inch / 2.825 inch, 150 lb/ft
Mud weight = 14 ppg
Line and sheave efficiency Coefficient = 0.9616
Buoyancy factor = 0.847
Determine:
1. Weight of drill string in air and mud;
2. Hook load, assuming weight of travelling block and hook to be 23,500 lb;
3. Dead line and fast line loads, assuming an efficiency factors of 0.81
4. Dynamic crown load;
5. Wire line design factor during drilling if breaking strengths of wire is 228,000 lb;
6. Wire line design factor when running casing 12,000 ft 7 inch of 29 lb/ft.
44
SUPPLEMENTARY PROBLEM
• PROBLEM-2:
A drilling rig has three diesel engines for generating the rig
power requirement. Determine the total daily fuel consumption
for an average engine running speed of 800 rpm, average output
torque of 1,610 ft-lbs, and engine efficiency of 45%.
The heating value of diesel oil is 18,000 BTU/lb.
45
SUPPLEMENTARY PROBLEM
• PROBLEM-3.
Compute the tension in the fast line when lifting
a 500,000 lb load for 6, 8, 10 and 12 line strung
between the crown block and travelling block.
46
SUPPLEMENTARY PROBLEM
• PROBLEM-4.
Discuss the function of this marine drilling
equipment:
1. Marine riser
2. Ball Joint
3. Pneumatic tensioning device,
4. Bumper sub
5. Slip joint
6. Taut-line Inclinometer.
47
SUPPLEMENTARY PROBLEM
48