Case Study Malikai TLP

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Case Study

Malikai TLP
Client Preparation Investment Volume Origin and
TMJV Technip / Period Approx. Approx. Destination
MMHE Aug. 2014 to USD 2,972,000 4,020 FRT From USA to
Dec. 2015 Malaysia

Case Study:
Malikai TLP Deepwater
Project
An oil major has awarded Technip the EPC contract for the first
tension leg platform phase of the project in Malaysia. Technip and
Malaysia Marine & Heavy Engineering Sdn Bhd (MMHE) formed a
joint venture under the name of TMJV to execute the Malikai Project.

Construction of the platform took


place at MMHE’s yard in Pasir
Gudang, a city in the state of Johor.
Once finalized, the platform was
towed to its final destination in the
Malikai oil field, about
100 kilometers off of Sabah,
Malaysia.

The platform is working in water


about 500 meters deep and is
moored securely in place by
specially coated tendons. tendons, however, resulted in an similar tendons. In parallel, deugro was to be able to reuse the
out-of-contract scope, which was Houston had several meetings and materials used on the river barge
This case study describes the tendered for among competitive cargo inspections at the coating when transferring the cargo to
transportation of the above- bidding with several freight yard to optimize the cargo handling the oceangoing vessel at the port.
mentioned tendons from the forwarders. and stowage procedures. Avoiding This was only possible by closely
special coating facility in New damages to the highly specialized

» Part of the transport


Iberia, Louisiana, USA to Pasir The challenges that this shipment and sensitive coating of the
Gudang, Malaysia. would pose to the teams in tendons was put forward as a top
Singapore and Houston was at that priority.
stage not foreseeable. design challenge was to be
able to reuse materials. «
Project background Over the course of a year, deugro
deugro Singapore’s project designed, engineered and
deugro was awarded the execution management team had several fabricated a dedicated grillage,
of freight forwarding services for meetings with Technip, the oil dunnage and sea-fastening system working together with the carrier’s
the overall equipment and material major and MMHE to understand in cooperation with dteq Transport engineering and cargo supervision
required as part of the Malikai the requirements and the lessons Engineering Solutions (dteq) for the teams.
Project. The transportation of the learned from past operations with job. Part of the design challenge

2 3
deugro’s scope of work Main challenges Shipment highlights Loading sequence

The transportation scope included In tender clarification meetings with The multimodal transportation Determining the loading sequence
the movement of 60 tendons plus Technip, we learned that damages involved the full charter of the for transfer from barge to vessel
14 pallets of spare parts, Free In in to the coating of the tendons had heavy lift vessel MV Industrial was quite intricate.
New Iberia, Louisiana and Liner Out been a major issue in the past. Kelly (P1 type), equipped with two
at MMHE in Pasir Gudang. 80-metric-ton safe working load The final transportation manual was
These damages were caused by (SWL) cranes. a 13-page document describing
deugro had to charter two 260-foot movement and friction during the the detailed loading sequence. The
barges, as well as suitable tugs and ocean voyage, which was the result Her hold was just long enough to sequence is unique and had to be
an oceangoing heavy lift vessel, of insufficient grillage and dunnage. accommodate the tendons with a followed to a T.
specially for this project. length of up to 73.5 meters.
It was therefore deemed mandatory It took dteq’s engineers many
The length of the tendons and the for our transportation proposal not Dedicated stanchions nearly hours to come up with a concept
requirement to load them under to only be commercially viable but 3.5 meters high at the forward end that allowed for the reuse of the
deck limited us to vessels with also to include a technical proposal of the vessel provided the required materials used on the barges on
cargo holds that are not separated outlining measures to avoid strength to hold the tendons board the vessel, thus reducing
by bulk heads. We settled on the damages. in place against longitudinal costs for additional materials.
Industrial Kelly, a P1-type vessel acceleration forces.
that offers a hold up to 87 meters in Significant funds and man-hours

» Determining the loading


length. were invested to come up with a Stevedores at the Port of New
Pipe stow grillage dedicated sea-fastening design. Orleans built a special dunnage
ready for installation Furthermore, it was deugro’s The sophistication of our proposal structure to fill the gap between
on board responsibility to arrange was the major differentiator and led the tendons and the stanchion sequence for transfer from barge
to vessel was quite intricate. «
for stevedoring during the to an award for the scope. stoppers. All wood works were
transshipment from barges to made-to-measure on the spot.
oceangoing vessels in New Orleans. Over the course of several weeks,
the assigned Marine Warranty
The loading operation onto the Surveyor and dteq’s team of
barges took place at the fabricator’s engineers went through seven
yard. While the first barge was revisions of the method statement
released on and towed for transportation. Details like
towards New Orleans, the the grade of steel and type of
second barge was receiving cargo. wood used had to be agreed
upon before dteq could produce
The transshipment required 11 days detailed fabrication drawings. Only
to complete, and than the Industrial then could the manufacturing
Kelly started her six-week voyage to of the tailor-made construction
Pasir Gudang. Upon arrival at commence.
MMHE’s yard in Pasir Gudang, the
discharging operation commenced
and took 10 days to complete.

4 5
Excellence and experience
are what have been
making deugro’s services
unique for nearly
100 years.

Discharging operation at MMHE’s


jetty in Pasir Gudang, Johor, Malaysia

6 7