Professional Documents
Culture Documents
Qaqcsuk Latest
Qaqcsuk Latest
Qaqcsuk Latest
JALAN RAYA
1
Constructing a flexible pavement involves four general focal points:
construction of sub grade, sub base, road base and asphalt pavement.
• This is true not only for individual consumers but also for
large corporations, government organizations and the
taxpaying public as a group.
2
Quality assurance. All those planned and systematic actions necessary to provide
confidence that a product or facility will perform satisfactorily in service. Quality assurance
addresses the overall problem of obtaining the quality of a service, product, or facility in the
most efficient, economical, and satisfactory manner possible. Within this broad context,
quality assurance involves continued evaluation of the activities of planning, design,
development of plans and specifications, advertising and awarding of contracts,
construction, and maintenance, and the interactions of these activities.
Acceptance. Sampling, testing, and the assessment of test results to determine whether
or not the quality of produced material or construction is acceptable in terms of the
specifications.
Independent assurance. A management tool that requires a third party, not directly
responsible for process control or acceptance, to provide an independent assessment of the
product and/or the reliability of test results obtained from process control and acceptance
testing. The results of independent assurance tests should not be used as a basis of
product acceptance.
3
3 Phases of Contractor Quality Control – What is Involved?
•Preparatory Phase
•Review Plan & Specification.
•Verify submittal approval
•Check preliminary work
1 •Examine materials
•Discuss construction methods
•Review safety.
•Start-up Phase
•Establish quality required
•Resolve conflicts
•Production Phase
•Ensure contract compliance
•Conduct intermittent or continuous inspections to identify and correct
deficiencies.
4
Quality Assurance (QA)
Adalah program pemeriksaan dan ujian pengesahan
tambahan dan berasingan. Meliputi ujian dan analisis
yang dijalankan oleh JKR atau PBT. Program QA
semestinya dijalankan ke atas sampel yang berasingan
dari QC dan menggunakan peralatan ujian dan
kakitangan yang tidak bersangkut-paut dengan aktiviti
QC. Sijil pengesahan memenuhi spesifikasi dan
penerimaan ke atas sebarang bahagian kerja yang
telah disiapkan semestinya berdasarkan pada QA, dan
bukan QC.
QC/QA Specification
5
QA/QC BUKAN PERCUMA…
Ia melibatkan kos..
RULE OF THUMB…..
6
ANDA DIMANA……
PLUS –5%
JKR – 1-3%
7
WHAT IS PAVEMENT SUPERVISION WORK?
8
WHY EFFECTIVE PAVEMENT SUPERVISION ACTIVITIES
ARE CRUCIAL?.....(CONT)
9
JIKA TIADA KAWALAN…...
10
JIKA TIADA KAWALAN…...
11
ADA KAWALAN…...TETAPI…
12
KESANNYA…..JALAN CEPAT ROSAK…
Rugi
Money !
RM
KESANNYA….. …
13
TIPAH TERTIPU……
1.Ketebalan (Thickness)
10mm…
Contoh : 1 km panjang dan 7m lebar.
Subbase: 147 ton x15 =2610
Roadbase: 147 ton x15 = 2610 RM 101,505…
ACBC: 161 ton x 180 = 28980
ACWC: 161 ton.x 185 = 29785
2. Pemadatan.
Subbase - Density diperlukan, 2.1 – 2940 ton, tertipu..density 1.95 –
2730 ton, 210 ton.x 15 = 3150
Roadbase – 2.3 – 4830, tertipu..2.1 – 4410, 420 ton.x15=6300
ACBC – 2.2 – 924 ton, tertipu.. 2.0 – 840 ton, 84 ton.x180=15120
ACWC – 2.2 – 770 ton, tertipu..2.0 – 700 ton, 70 ton.x185=12950
2.3 Thickness Qty (ton) 200 195 190 185 180 175 170 165 160
0.050 0.1150 23.00 22.43 21.85 21.28 20.70 20.13 19.55 18.98 18.40
0.045 0.1035 20.70 20.18 19.67 19.15 18.63 18.11 17.60 17.08 16.56
0.040 0.0920 18.40 17.94 17.48 17.02 16.56 16.10 15.64 15.18 14.72
0.035 0.0805 16.10 15.70 15.30 14.89 14.49 14.09 13.69 13.28 12.88
0.030 0.0690 13.80 13.46 13.11 12.77 12.42 12.08 11.73 11.39 11.04
0.025 0.0575 11.50 11.21 10.93 10.64 10.35 10.06 9.78 9.49 9.20
0.020 0.0460 9.20 8.97 8.74 8.51 8.28 8.05 7.82 7.59 7.36
2.25 Thickness Qty (ton) 200 195 190 185 180 175 170 165 160
0.050 0.1125 22.50 21.94 21.38 20.81 20.25 19.69 19.13 18.56 18.00
0.045 0.1013 20.25 19.74 19.24 18.73 18.23 17.72 17.21 16.71 16.20
0.040 0.0900 18.00 17.55 17.10 16.65 16.20 15.75 15.30 14.85 14.40
0.035 0.0788 15.75 15.36 14.96 14.57 14.18 13.78 13.39 12.99 12.60
0.030 0.0675 13.50 13.16 12.83 12.49 12.15 11.81 11.48 11.14 10.80
0.025 0.0563 11.25 10.97 10.69 10.41 10.13 9.84 9.56 9.28 9.00
0.020 0.0450 9.00 8.78 8.55 8.33 8.10 7.88 7.65 7.43 7.20
2.2 Thickness Qty (ton) 200 195 190 185 180 175 170 165 160
0.050 0.1100 22.00 21.45 20.90 20.35 19.80 19.25 18.70 18.15 17.60
0.045 0.0990 19.80 19.31 18.81 18.32 17.82 17.33 16.83 16.34 15.84
0.040 0.0880 17.60 17.16 16.72 16.28 15.84 15.40 14.96 14.52 14.08
0.035 0.0770 15.40 15.02 14.63 14.25 13.86 13.48 13.09 12.71 12.32
0.030 0.0660 13.20 12.87 12.54 12.21 11.88 11.55 11.22 10.89 10.56
0.025 0.0550 11.00 10.73 10.45 10.18 9.90 9.63 9.35 9.08 8.80
0.020 0.0440 8.80 8.58 8.36 8.14 7.92 7.70 7.48 7.26 7.04
14
2.15 Thickness Qty (ton) 200 195 190 185 180 175 170 165 160
0.050 0.1075 21.50 20.96 20.43 19.89 19.35 18.81 18.28 17.74 17.20
0.045 0.0968 19.35 18.87 18.38 17.90 17.42 16.93 16.45 15.96 15.48
0.040 0.0860 17.20 16.77 16.34 15.91 15.48 15.05 14.62 14.19 13.76
0.035 0.0753 15.05 14.67 14.30 13.92 13.55 13.17 12.79 12.42 12.04
0.030 0.0645 12.90 12.58 12.26 11.93 11.61 11.29 10.97 10.64 10.32
0.025 0.0538 10.75 10.48 10.21 9.94 9.68 9.41 9.14 8.87 8.60
0.020 0.0430 8.60 8.39 8.17 7.96 7.74 7.53 7.31 7.10 6.88
2.1 Thickness Qty (ton) 200 195 190 185 180 175 170 165 160
0.050 0.1050 21.00 20.48 19.95 19.43 18.90 18.38 17.85 17.33 16.80
0.045 0.0945 18.90 18.43 17.96 17.48 17.01 16.54 16.07 15.59 15.12
0.040 0.0840 16.80 16.38 15.96 15.54 15.12 14.70 14.28 13.86 13.44
0.035 0.0735 14.70 14.33 13.97 13.60 13.23 12.86 12.50 12.13 11.76
0.030 0.0630 12.60 12.29 11.97 11.66 11.34 11.03 10.71 10.40 10.08
0.025 0.0525 10.50 10.24 9.98 9.71 9.45 9.19 8.93 8.66 8.40
0.020 0.0420 8.40 8.19 7.98 7.77 7.56 7.35 7.14 6.93 6.72
2.05 Thickness Qty (ton) 200 195 190 185 180 175 170 165 160
0.050 0.1025 20.50 19.99 19.48 18.96 18.45 17.94 17.43 16.91 16.40
0.045 0.0923 18.45 17.99 17.53 17.07 16.61 16.14 15.68 15.22 14.76
0.040 0.0820 16.40 15.99 15.58 15.17 14.76 14.35 13.94 13.53 13.12
0.035 0.0718 14.35 13.99 13.63 13.27 12.92 12.56 12.20 11.84 11.48
0.030 0.0615 12.30 11.99 11.69 11.38 11.07 10.76 10.46 10.15 9.84
0.025 0.0513 10.25 9.99 9.74 9.48 9.23 8.97 8.71 8.46 8.20
0.020 0.0410 8.20 8.00 7.79 7.59 7.38 7.18 6.97 6.77 6.56
SPESIFIKASI.
JKR/SPJ/1988.
JKR/SPJ/2008.
15
STRUKTUR LAPISAN JALANRAYA.
PLUS
JKR/PBT
1 PBT/J.KAMPUNG
2
1
3 2 1
4 4
4
5 5 5
6 6 6
16
STRUKTUR JALANRAYA.
17
PRE CONSTRUCTION
SUBGRADE
Unbound Material
Subgrade Performance
A subgrade’s performance generally depends on two interrelated
characteristics:
• Load bearing capacity. The subgrade must be able to support loads
transmitted from the pavement structure. This load bearing capacity is often
affected by degree of compaction, moisture content, and soil type. A
subgrade that can support a high amount of loading without excessive
deformation is considered good.
• Volume changes. Most soils undergo some amount of volume change
when exposed to excessive moisture or freezing conditions. Some clay
soils shrink and swell depending upon their moisture content
18
Volume changes. Most soils undergo some amount of volume change
when exposed to excessive moisture or freezing conditions. Some clay
soils shrink and swell depending upon their moisture content
For the designs recommended in this manual all soils are divided into three classes: Good,
Medium and Poor. California Bearing Ratio (CBR) design values are assigned for each class. It
is desirable to use laboratory tests to evaluate the load supporting characteristics of subgrade
soils. However, if laboratory test equipment is not available, designs may be made on the basis
of a careful field evaluation by an engineer who can assign the subgrade soils to one of the
following categories:
GOOD SUBGRADE SOILS—Good subgrade soils retain a substantial amount of their load
bearing capacity when wet. Included are the clean sands and sandy gravels and soils free of
detrimental amounts of plastic materials. A good subgrade will have a CBR value of 20 or
higher.
POOR SUBGRADE SOILS—These soils become quite soft and plastic when wet. Included are
those soils having appreciable amounts of clay and fine silt. The coarser silts and sandy loams
also may exhibit poor bearing properties in areas where frost penetration into the subgrade is a
factor. A poor classification will have a CBR value of 5 or less. Soils with a CBR value of less
than 5 should be stabilized or removed and replaced using suitable material. A stable subgrade
is always required.
19
WHY SOIL STABILIZER?
20
CRUSHED AGGREGATE
21
Jaw Crusher
22
Schematic Diagram of Cone Crusher
23
SUBBASE
Test parameter Quality Requirement Remark
CBR Not less than 30% compacted to 95% of
MDD, soaked for 4
days.
Plasticity Index Not more than 12
10% Fines Value Not less than 30 KN
Sand Equivalent Not less than 45% aggregate fraction
passing the No. 4 (4.75
mm) sieve
If more than 10% of the material is retained on the BS 20.0 mm sieve,
the whole material can be assumed without test to have a CBR value
of 30% or more.
JKR/SPJ/2008
24
CRUSHED AGGREGATE ROADBASE
JKR/SPJ/2008
25
MAXIMUM DRY DENSITY(MDD) AND
OPTIMUM MOISTURE CONTENT(OMC)
2.100
2.071
2.050
Dry Density (Mg/cm 3)
2.000
1.950 1.954
1.948
1.900
1.885
1.850
1.839
1.800
2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5
Moisture Content (%)
An in-situ CBR test can also be carried out in the field, using a suitably-
rigged vehicle. In-situ CBR results can be significantly different from
laboratory-derived results. The in-situ CBR test is not normally used as
quality assurance measure to ensure specification implementation.
26
California Bearing Ratio (CBR) Test.
(Keupayaan Galas Tanah)
2,055 kgf (20.15 kN) at 2.5 mm and 5.0 mm p = measured pressure for site soils [N/mm2]
p s = pressure to achieve equal penetration on
penetrations respectively. standard soil [N/mm2]
27
Aggregate Crushing Value (ACV)
28
GRADING/SIEVE ANALYSIS
Maximum aggregate size can affect HMA, and base/subbase courses in several ways. In HMA,
instability may result from excessively small maximum sizes; and poor workability and/or
segregation may result from excessively large maximum sizes (Roberts et al., 1996) . ASTM C
125 defines the maximum aggregate size in one of two ways:
• Maximum size. The smallest sieve through which 100 percent of the aggregate
sample particles pass.
• Nominal maximum size. The largest sieve that retains some of the aggregate particles
but generally not more than 10 percent by weight.
Thus, it is important to specify whether “maximum size” or “nominal maximum size” is being
referenced.
29
NOMINAL MAXIMUM SIZE AGGREGATE/MAXIMUM SIZE AGGREGATE.
FLAKINESS
30
SOUNDNESS TEST
Before After
Premix,
AGGREGATE Tack/Prime Coat
31
JKR/SPJ/2008
TABLE 4.3.3– GRADATION LIMITS FOR ASPHALTIC CONCRETE.
BITUMINOUS MATERIAL
Bituminous binder for asphaltic concrete shall
be pen.grade bitumen of 60- 70 conforming to
M.S 124.
Penetration – 60/70 dmm @( x 0.1mm )
Softening point – 48 – 56 deg.celcius.
Ductility - > 100cm.
Solubility – 99%
Flash point - > 250 deg.celcius.
Loss on Heating – 0.5%
Drop in penetration – 20 %.
32
TYPICAL COMPOSITION OF SOME CRUDE OILS
33
SIRIM Specification for Penetration Grade Bitumen (MS 124)
Penetration Grade
40 - 50 60 - 70 80 - 100 120 - 150 200 - 300
min max min max min max min max min max
Penetration@77°F 25°C,
100g, 5 s , dmm
40 50 60 70 80 100 120 150 200 300
Softening Point, ° C 52 60 48 56 45 52 40 46 33 43
Flash Point, ° C 250 - 250 - 225 - 225 - 200 -
Ductility @ 25°C,
5 cm/minute, cm
100 - 100 - 100 - 100 - 100 -
Solubility in
trichloroethylene, % 99 - 99 - 99 - 99 - 99 -
Retained penetration
after TFOT, %
55 - 52 - 47 - 42 - 37 -
34
Prediction of PG grades for different crude oil blends.
Bitumen Emulsion
TACK COAT & PRIME COAT
35
WHAT IS BITUMEN EMULSION..
36
SIRIM Specification of Emulsion MS 161- Tack/Prime Coat
Properties RS- RS- MS- MS- SS-
Units Methods RS-1K RS-2K
0K 3K 1K 2K 1K
Saybolt Furol Viscosity
At 25°C min 20 20
sec D 244
max 25 50 70 100
At 50°C min 100 50 50
sec D 244
max 400 450 450
Storage
% D 244 1 1 1 1 1 1 1
Stability,24hrs,max
Sieve Test,max % D 244 0.1 0.1 0.1 0.1 0.1 0.1 0.1
Cement mixing,max % D 244 2 2 2 2 2 2 2
Particle Charge D 244 +ve +ve +ve +ve +ve +ve +ve
Bitumen
% D 244 38 50 60 65 60 65 57
Residual,min
Oil Distillate, max % D 244 3 3 3 3 20 12
Test on Residue
Pen @ 25°C, min 60 60 60 60 60 60 60
dmm D5
max 200 200 200 200 200 200 200
Solubility in TCE, min % D2042 97.5 97.5 97.5 97.5 97.5 97.5 97.5
Classification of BS
37
Classification of SIRIM
RS-1K
RS – Rapid Setting
MS – Medium Setting
MS-1K SS – Slow Setting
1 – Breaking Rate
K - Cationic
SS-1K
38
TABLE 4.3.3 – GRADATION LIMITS FOR ASPHALTIC CONCRETE.
Aggregate Grading
100
90
80
70
Percentage Passing
60
50
40
30
20
10
0
0.01 0.1 1 10 100
Sieve Size (m m )
Cement
Establish Aggregate
Proportion/Blend
39
AGGREGATE PROPORTION - CALCULATOR
Bin Proportion %
Sieve B1 B2 B3 B4 B5 35 10 53 2 Specification
Combined C/L
Size(mm) 20mm 10mm Q/D Filler 20mm 10 mm Q/D Filler Upper Lower
25 100 100 100 100 35 10 53 2 100 100 100 100
20 91.3 100 100 100 31.955 10 53 2 96.96 88 100 76
14 42.5 100 100 100 14.875 10 53 2 79.875 76 89 64
10 19.8 96.3 99.6 100 6.93 9.63 52.79 2 71.35 68 81 56
5 0.1 3.6 94.8 100 0.04 0.36 50.24 2 52.64 58 71 46
3.35 0.09 0.5 79.4 100 0.03 0.05 42.08 2 44.16 45 58 32
1.18 0 0.2 43.1 100 0 0.02 22.84 2 24.86 31 42 20
0.425 0 21.3 100 0 0 11.289 2 13.289 20 28 12
0.15 0 8.6 100 0 0 4.558 2 6.558 11 16 6
0.075 0 4.6 96 0 0 2.438 1.92 4.358 6 8 4
100
Aggregate Grading
100
90
80
70
Percentage Passing
60
50
40
30
20
10
0
0.01 0.1 1 10 100
Sieve Size (mm)
40
Mixing temperature - 160ºC - 170ºC
41
Marshall Compacter – 75 blows per side.
42
Marshall Stability & Flow
43
TABULATING AND PLOTTING TEST RESULTS
• Tabulate the results from testing, correct the stability values for specimen height.
• Prepare the following plots:
– Asphalt content vs density
– Asphalt content vs Marshall stability
– Asphalt content vs flow
– Asphalt content vs air voids
– Asphalt content vs VMA
– Asphalt content vs VFA
• Review the plots for the following trends:
– Stability vs asphalt content can follow two trends:
• Stability increases with increasing asphalt content, reaches a peak, and
then decreases.
• Stability decreases with increasing asphalt content and does not show
a peak (recycled HMA mixtures)
– Flow should increase with increasing asphalt content.
– Density increases with increasing asphalt content, reaches a peak, and then
decreases. Peak density usually occurs at a higher asphalt content than
peak stability.
– Percent air voids should decrease with increasing asphalt content.
– Percent VMA decreases with increasing asphalt content, reaches a
minimum, and then increases.
– Percent VFA increases with increasing asphalt content.
After the completion of the stability and flow test, specific gravity and voids analysis shall be carried out for
each test specimen to determine the percentage air voids in the compacted aggregate filled with bitumen
(VFB) and the percentage air voids in the compacted mix (VIM).
44
AGGREGATE PROPORTION
100
90
80
70
Percentage Passing
60
50
40
30
20
10
0
0.01 0.1 1 10 100
Sieve Size (m m )
Aggregate + Bitumen
45
Asphalt Production
46
Batch Plant Layout
COVERED STOCKPILES
47
Asphalt Batch Mix Plant and its Components
48
PUGMILL MIXER
49
HOW CAN YOU TELL THAT A MIX IS PROPERLY
MIXED?
When all the aggregate particles are coated with asphalt. The large
aggregate particles are always the last to be coated. If the large
aggregate particles are completely coated, the mix is properly mixed.
Generally we see mixing problems only with batch plants. The producer is
trying to mix each batch as quickly as possible (probably in about 30
seconds) which may or may not be adequate mixing time. Typical
specifications set minimum coated particle percentages at 90 to 95
percent. Minimum mixing times to meet the specified requirement should
carefully adhered to in order to avoid excess oxidation of the asphalt films
on the aggregate particles as it is exposed to air (oxygen) during the
mixing process.
As a general rule we do not see this problem with drum mixes. The mix
remains in the mixing portion of the drum for much longer periods of time
(maybe 2 to 3 minutes) than in the pugmill of a batch plant, so the
aggregate particles get very well coated. Keep in mind that we are not as
concerned about oxidation in drum mixes as the mixing portion of the
drum mixer is essentially an oxygen-free atmosphere.
50
Load front first, back second and middle third
51
PLANT TRIAL
Contractor shall arrange to mix the
asphaltic concrete conforming to the
proposed formula.
Comprehensive sampling and testing.
Gradation
Bitumen Content
Marshall Properties.
Plant trial results
Bitumen ± 0.2 %
Fraction of combined ± 5.0 %
aggregate passing 5.0 mm
and larger sieves
Fraction of combined ± 4.0 %
aggregate passing 3.35 mm
and 1.18mm sieves
Fraction of combined
aggregate passing 425 µm ± 3.0 %
and 150µm sieves
Fraction of combined ± 2.0 %
aggregate passing 75 µm
sieves
52
TRIAL LAY
Contractor shall arrange, lay and
compact asphaltic concrete conforming
to the proposed formula.
A minimum 10 tonnes shall be placed in
trial area;
Thetrial areas shall not be part of the
contract works – contractor expense.
Comprehensive sampling and testing.
Trial Sections
• The construction of trial sections is very valuable, and
allows any problems to be sorted out in advance of the
permanent construction.
• The trial section is generally part of the main construction,
done at the beginning of the section.
• A trial section is recommended for all pavement layers
constructed with problem or sensitive materials.
• A successful trial is the reference against which the
permanent works are compared, and ultimately accepted.
53
• A trial section is usually constructed to enable the assessment and verification of
the proposed construction procedures for the particular construction process.
• A trial section is recommended for all pavement layers constructed with problem
or sensitive materials.
• Trial sections should be constructed using the same materials, plant, equipment
and procedures as will be used in the permanent works. Trial sections form a very
important part of a proactive approach to quality control.
• Any problems with mix sensitivity, constructability, uniformity of product properties
as well as surface and smoothness can be identified timeously, and corrected
prior to commencement of the permanent works.
• The successful trial is the reference against which the permanent works are
compared, and ultimately accepted. It is, therefore, important that a high level of
monitoring, including careful visual assessment, data recording and testing, is
carried out.
• It is vitally important that the design engineer is present at the trial section. Each
specific product type and/or layer has its own unique requirements for trial section
procedures and information.
• It is important to ensure that the condition and settings of equipment, as well as
construction procedure and techniques utilised for the construction of the
approved trial section, remain constant throughout construction of the permanent
works.
54
Important aspects to note during asphalt trial sections are:
55
JOB MIX FORMULA
Aggregate Grading
100
90
80
70
Percentage Passing
60
50
40
30
20
10
0
0.01 0.1 1 10 100
Sieve Size (m m )
DURING CONSTRUCTION
SUBGRADE/SUBBASE/ROADBASE
56
Road Formation
Compaction of Subgrade
Impact Roller
57
OMC/MDD
58
Compacted Subgrade
MOISTURE CONTENT
1. Speedy Meter
2. Oven Method
3. Frying Pan
59
FDT- SAND REPLACEMENT METHOD.
An in-situ CBR test can also be carried out in the field, using a suitably-
rigged vehicle. In-situ CBR results can be significantly different from
laboratory-derived results. The in-situ CBR test is not normally used as
quality assurance measure to ensure specification implementation.
60
CONSTRUCTION - SUBBASE/ROADBASE
Sub-base/Road-base material shall be transported, laid and
compacted at a moisture content within the range +1% to -2% of
the optimum moisture content without drying out or segregation.
Sub-base/Road-base material shall be placed over the full width
of the formation to the required thickness in one layer or more,
each layer not exceeding 200 mm compacted thickness. Where
two or more layers are required, they shall be of approximately
equal thickness and none shall be less than 100 mm compacted
thickness.
Compaction shall be carried out in a longitudinal direction along
the roadbed, and shall generally begin at the outer edge and
progress uniformly towards the crown on each side in such a
manner that each section receives equal compactive effort.
The sub-base/Road-base shall be finished in a neat and
workmanlike manner, and shall have an average thickness over
any 100 metre length not less than the required thickness. The top
surface of the sub-base shall have the required shape, super-
elevation, levels and grades.
Roadbase layer
61
Finished layer of Road Base
62
Well Knitted Crushed Stone Surface
After Completion..
After 6 Months…
Theme Park…free
ride Roller Coaster !!!
63
Prime Coat
The main function of a prime is to penetrate the
layer to which it is applied, while leaving a small
residual amount of binder on the surface to:
64
YES X NO
65
IS A PRIME COAT NECESSARY?
??????????
Tack Coat
The function of a tack coat is to ensure bonding between the new
asphalt layer and the primed surface or old asphalt layer. The
tack coat is applied in a thin coat and uniformly covers the entire
surface, including all vertical joint surfaces. Too little tack coat
causes debonding, and too much tack coat can cause slippage
between the layers.
66
BITUMINOUS TACK COAT
Materials
Emulsion grade RS-1 or RS-1k (MS 161)
Equipment
Power broom
Compressed Air Blower
Pressure Distributor for Bituminous Material
Spraying Rate
0.25 to 0.55 litre/sq.m
Curing ACWC
GLUE
45 minutes to one hours ACBC
YES X NO
67
Tack coat….?????
68
69
Tack coat…to much!
70
YES X NO
71
72
73
Not enough tack coat?
74
Example of Milling Machine
75
Mill and Pave.
Scabbing
76
DURING PRODUCTION AND LAYING
Flow
Air Void
Void Filled with Bitumen (VFB)
Density
Stiffness ( Stability/Flow)
Bitumen extraction
Aggregate grading
Before extraction
After extraction
77
CONSTRUCTION
Asphalt Paver
Must be Tip-TOP.
Rollers
Pneumatic tyre roller and two steel wheeled tandem rollers.
Laying Asphaltic Concrete
Temperature before unloading from the truck – 135 º C.
compaction temperature – 120 º C.
Tandem roller – 8 – 10 tonnes
Tyred roller – 15 tonnes.
Speed for tandem – 5 km/hr and tyred roller – 8 km/hr.
Compaction – wearing course 98 – 100 % and Binder
Course 95- 100 %.
78
HMA Paver
PAVING TRAIN
79
WHAT SHOULD BE USED AS A MIX RELEASE AGENT
FOR TRUCK BEDS AND ROLLERS?
Far too often we still see diesel fuel used as a mix
release agent. Diesel fuel is a solvent. Any excess
amount will dissolve the asphalt films on the
aggregate particles, thus contaminating the mix.
Commercial mix release agents are readily
available and should be used. They generally are
soap or emulsified wax or other stick-resistant
materials that do not contaminate the mix.
A couple of suggestions are a bag of hydrated lime
mixed with 1000 gallons of water or a bottle of dish
soap (Joy) mixed with water. The portions depend
on the water with which it is mixed.
80
Loose versus Compacted Mat Thickness
81
WHAT IS A MINIMUM TEMPERATURE FOR ASPHALT MIXES?
Mixes must be placed and compacted before they cool to 90o C, so the
minimum temperature will depend on the temperature of the layer upon
which it is being placed as well as ambient conditions. Generally, agency
specifications will spell out a minimum acceptable temperature for the mix.
Some specifications will use 110o C, and others may use 120o C.
1. rain will cool the asphalt mix and could make obtaining proper compaction more difficult
2. the asphalt lifts must be able to properly bond together and moisture can be a hindrance
to that bond
3. puddles overlaid with HMA turn to steam, which may cause stripping (separation of the
asphalt binder from the aggregate) – never pave over puddles whether it is raining or not
If you temporarily suspend paving operations due to rain, don’t forget to:
1. keep all trucks tarped
2. construct a vertical-faced construction joint
3. properly dispose of all material left in the hopper
4. be careful not to track mud and dirt onto the project
5. Asphalt pavements are designed to last for many years, so don’t let a sense of urgency to
get the job done quickly allow you to make decisions which could strip years away from
the pavement life.
82
No paving in the rain.
83
To minimize handwork/back casting….
84
Control Panel for Level Censor
YES X NO
85
86
Segregation
87
Excessive hand casting and manual addition or
removal of mix to correct levels will result in
poor surface texture and inadequate functional
performance of the layer.
88
89
ONE OF THE
ESSENTIALS
FOR A
CONSISTENT
AND HIGH
QUALITY HOT
MIX ASPHALT
PAVEMENT IS TO
PROVIDE FOR A
CONTINUOUS
OPERATION
90
Temperature at the start of rolling > 110 C.
Thickness
Control
91
Good Paving Practices
COMPACTION
GOOD
COMPACTION
LEADS TO GOOD
PERFORMANCE
92
How many roller required?
Wheel position of
PTR.
Both axles are
equipped with 4
compacter wheels
each. The wheel
overlap 40mm.
10 - 20 % air voids
behind paver
93
Top 3 factors in pavement
construction…
1. Compaction
2. Compaction
3. Compaction.
94
WHAT SHOULD COMPACTION REQUIREMENT BE?
95
WHAT IS THE RECOMMENDED AIR VOID CONTENT FOR
COMPACTION OF ASPHALT PAVEMENT
96
Factors Affecting Compaction
97
Good Rolling Practices
98
Effect of Air Voids on Life
Temperature is critical
99
Typical Rolling Pattern
Compaction Stages
i. Breakdown Rolling (150 °C – 120 °C range)
100
1. Breakdown Rolling
• This stage takes place immediately behind the paver
where the mat temperature is highest.
• Most of the compaction is achieved during this stage, e.g.,
an increase in density from about 84% of Maximum
Theoretic Relative Density (MTRD) behind the screed, to
about 91% of MTRD.
• Rollers with the highest compactive effort are used to
reach adequate density rapidly on mats where the
temperature is typically in excess of 135 °C for
continuously graded asphalt. This is best accomplished by
static steel wheel rollers, especially three-wheel rollers.
• Vibratory rollers have a wider compaction temperature
range than static rollers, and achieve density in fewer
passes.
• Pneumatic tyred rollers can achieve the required density,
but on a very hot mat may give rise to rideability problems.
8 or 10 or 12 passes
101
2. Intermediate Rolling
• This stage follows directly after breakdown rolling while the mat is still
plastic and at a temperature that permits further compaction. This stage
of compaction continues until the required compaction is achieved, and
the density is increased to the specified requirement, e.g., 93% to 95%
MTRD and the surface is well knit.
• This stage is best accomplished by rollers effective at lower
temperatures, i.e., generally in the range of 95 to 135 °C. Vibratory and
pneumatic tyred rollers are suitable for this stage, with pneumatic tyred
rollers effective at temperatures as low as 70 °C, and where knitting of
the surface is required.
• Heavy steel wheel static, or vibratory rollers at very low amplitude
vibration, are employed to iron out any roller marks. This stage should
be completed before the mat reaches a temperature of about 90 °C,
although evening out of the surface may be achieved at temperatures
as low as 70 °C, depending on the viscosity of the binder.
• Modified binders may have a marked influence on the compaction
temperatures. Workability of these mixes should be carefully
investigated during trial sections, and when any changes of binder and
additive sources occur, to set appropriate construction controls.
102
3. Finishing Rolling
103
Compacting seams and joints
104
Compaction effort
End of compaction
Favourable compaction
temperature
Start of
compaction
Mix temperature in °C
Effect of the compaction temperature on
the compaction effort
85ºC
32ºC
150ºC
105
85ºC 32ºC
135ºC
85ºC
32ºC
120ºC
106
T(°C) = (T(°F) - 32) / 1.8
85ºC
32ºC
107ºC
Low binder content High permeability enables ingress of water and air
Reduces durability
Increases chance of cracking and stripping
Void content High void content High permeability enables ingress of water and air
Reduces durability
Increasing chance of stripping
Compaction Low field compaction High permeability enables ingress of water and air
Reduces durability
Increasing chance of stripping
Filler content High filler content Low void content, stiff mix with reduced durability and
early flushing
Low filler content High void content, high permeability, reduction in rut
resistance
107
Tandem vibratory rollers should drive
the first two passes without vibration
Static compaction with tandem rollers Static compaction with pneumatic tired roller Contact pressure
0.20 - 0.80 MPa
108
109
110
YES X NO
111
112
113
Vertically cut joint faces shall be brushed or sprayed with
bitumen emulsion of grade RS-1K to ensure good bonding.
114
COMPACTED ASPHALTIC CONCRETE
A sample for every 500 m² of a.c. laid (obtained using
a core drill fitted with a diamond bit).
To determine the thickness and bulk S.G.
Extraction of bitumen and gradation if problems
occur during paving/material looks unsatisfactory or
perform poorly after paving.
Other quality test which are appropriate to spec,
should be carried out at recognized/accredited lab.
Other tests for unusually variable sources/quality:
Soundness
ACV
Polished Stone Value
Stripping test.
POST CONSTRUCTION
Core Samples
115
YES X NO
= 98% - 100%
116
Completed project…to check the roughness index (IRI) !!
POST CONSTRUCTION
ROLLING STRAIGHT EDGE
Transverse
Longitudinal
When ?
Before opening to
traffic.
117
JKR/SPJ/2008 – IRI = 2m/km
Tolerances for Surface Irregularity(RSE)-JKR/SPJ/1988
Transverse
Longitudinal Direction
Direction
Maximum Permissible Number of
Class of Surface Irregularities
Maximum
Surface Depth exceeding Depth exceeding
Permissible
Regularity 4 mm 7 mm
Depth of
Over Over Over Over Transverse
traverse traverse traverse traverse Irregularities
length length length length
of 300m of 75m of 300m of 75m
Class SR1 20 9 2 1 4 mm
Class SR2 40 18 4 2 8 mm
Class SR3 60 27 6 3 12 mm
15
10
Depth (mm)
0
0
0.03
0.04
0.08
0.1
0.13
0.13
0.16
0.16
0.18
0.19
0.2
0.2
0.2
0.22
0.23
0.26
0.29
0.3
0.31
0.32
0.34
0.37
0.4
0.41
0.43
0.43
0.45
0.46
0.48
0.49
0.5
0.5
0.59
0.59
0.59
0.6
0.61
0.66
0.66
0.7
0.74
-5
-10
Chainage
118
INTERNATIONAL ROUGHNESS INDEX (IRI)
Parameter/ Roughness,
Condition IRI (m/km)
criteria
119
Profiler Components
120
121
Minimum value of 55 ( 50m interval)
122
123
Road Marking Reflectometer.
Quick Facts
•Longest international highway: the Pan-American Highway, which connects many countries in the
Americas, is nearly 48,000 kilometres (29,826 mi) long as of 2005.
•Longest national highway: Australia's Highway 1 at over 20,000 km (12,427 mi). It runs almost the entire
way around the country’s coastline. With the exception of Canberra (which is inland) it links all the capital
cities, although Brisbane and Darwin are not directly connected. Also the route links all the major towns and
cities of the island state of Tasmania, Burnie, Devonport, Launceston and Hobart (the state’s capital).
•Longest national highway (Point to point): The Trans-Canada Highway (Known as TCH 1 in western
Canada) is 7,821 km (4,857 mi) long as of 2006. It runs across southern Canada and connects with several
major urban centres along its longitudinal route.[1]
•Largest national highway system: The United States of America has approximately 6,430,366 kilometres
(3,995,644 mi) of highway within its borders as of 2005.
•Busiest highway: Highway 401 in Ontario, Canada, has volumes surpassing an average of 500,000
vehicles per day in some sections of Toronto as of 2006.[2][3]
•Widest highway (maximum number of lanes): The Katy Freeway (part of Interstate 10) in Houston,
Texas, United States of America, has a total of 26 lanes in some sections as of 2007. However, they are
divided up into general use/frontage roads/HOV lanes, restricting traffic flow.
•Widest highway (number of maximum through lanes): Highway 401 through Mississauga, Ontario has
the most unrestricted free-flow lanes, at 18 (22 including restricted) as of 2006.
124
Quote of the day…..
Doing a good job cheaply implies the full and economic use of
the materials available. To use materials to the full it is
necessary to know as accurately as possible their properties.
To determine these properties tests must be performed.
Questions - ?
125
TERIMA KASIH…
126