Professional Documents
Culture Documents
TET-DG-5001 - Basic Design Criteria v1.1
TET-DG-5001 - Basic Design Criteria v1.1
Date: 14/05/2015
BASIC DESIGN CRITERIA Issue: 1.1
Electronic Document, only the original archived in Quality Department is signed / Printed copies uncontrolled
Revision Date Details
1.1 14/05/2015 - Page 3 section 1.1 last paragraph’’ Future population and
Growth rates’’ updated after publication of Population Projection
Sultanate of Oman (2015-2040) by National centre for Statistics
and Information (NCSI)
- Section 1.3 LPCD table updated.
Contents
Introduction............................................................................................................................................................. 2
1. WATER DEMAND FORECAST ................................................................................................................ 3
1.1 Population forecast ................................................................................................................................... 3
1.2 Categories of Water Demand ................................................................................................................... 4
1.3 Domestic Consumption / Pipe Supply...................................................................................................... 4
1.4 Domestic Consumption / Tankers Supply................................................................................................ 5
1.5 Non Domestic Consumption .................................................................................................................... 5
1.6 Leakage and other technical losses........................................................................................................... 6
1.7 Water Used by PAEW in its Normal Operations (after leakage) ............................................................ 6
1.8 Fire Fighting.............................................................................................................................................. 6
1.9 Commercial Losses ................................................................................................................................... 7
1.10 Peak Factors .............................................................................................................................................. 8
2. DISTRIBUTION SYSTEMS ........................................................................................................................ 9
2.1 Future Water demand – Design horizon and phasing of Assets .............................................................. 9
2.1.1 General ...................................................................................................................................................... 9
2.1.2 Water Demand .......................................................................................................................................... 9
2.1.3 An `` All-In`` figure for preliminary estimating ...................................................................................... 9
2.2 Pressure in the network ............................................................................................................................. 9
3. TRANSMISSION AND TRUNK MAIN DESIGN ................................................................................... 10
3.1 Headroom ................................................................................................................................................ 10
3.2 Route and elevation ................................................................................................................................ 10
3.3 Desired pressure ...................................................................................................................................... 11
3.4 Velocity ................................................................................................................................................... 11
3.5 Surge ....................................................................................................................................................... 11
3.6 Valves ...................................................................................................................................................... 11
3.7 Air valves ................................................................................................................................................ 12
3.8 Pipe materials .......................................................................................................................................... 12
3.9 Thrust blocks ........................................................................................................................................... 13
3.10 Energy considerations ............................................................................................................................. 13
4. WATER QUALITY .................................................................................................................................... 13
5. CONTROL PHILOSOPHY ........................................................................................................................ 14
6. SECURITY OF SUPPLY – RISK MANAGEMENT ............................................................................... 15
1/15
Design Guidelines TET/SS/5501
Date: 14/05/2015
BASIC DESIGN CRITERIA Issue: 1.1
INTRODUCTION
This document has been prepared as a Guide to PAEW engineers and their consultants for the
planning of water transmission and distribution systems.
It is not intended as a complete Manual for pipe design, but is intended to:
In the event of any doubt concerning the use of this Guide, the advice of the General Manager:
Planning and Asset Management Department should be sought.
Wherever possible, the water demand of an area should be based upon researched data
relating to the specific area under study. Only where such data is not available, should the data
in this Guide be used.
The Guide provides the minimum requirements/standards to be met and the data
provided is to be used as the minimum acceptable.
2/15
Design Guidelines TET/SS/5501
Date: 14/05/2015
BASIC DESIGN CRITERIA Issue: 1.1
Population
Future water domestic demand depends upon the future population and future per capita
consumption.
Population in an area can be determined in number of ways:
Domestic Occupancy
Domestic occupancy rates are difficult to ascertain due to lack of appropriate data.
Computations are complicated by the large number of empty houses1, holiday homes and for
other reasons.
From the 2010 Population Census and the 2010 water demand study, the following have been
deduced for 2010 and can be used for future developments unless more explicit data is
available.
As assessed
Parameter Governorate for 2010
1
According to the 2010 Population Census of the total 551,058 housing units only 396,421 were occupied
2
From Population Projection Sultanate of Oman (2015‐2040) issued by NCSI in September 2014.
3/15
Design Guidelines TET/SS/5501
Date: 14/05/2015
BASIC DESIGN CRITERIA Issue: 1.1
Unless more specific information is available, for the foreseeable future the following growth
rates can be assumed2 and applied. The following table contains the average population
growth rate deducted from the Population Projection Sultanate of Oman (2015-2040) issued by
the National Centre for Statistics and Information (NCSI) published in September 2014.
For local evolutions and detailed estimates data published by NCSI can be referred. NCSI is
updating this information regularly, for detailed information the designer should refer to the latest
data published.
There is a distinct difference between water demand, which is the quantity of water required
within an area to satisfy all the water needs of the area, and water consumption, which is the
actual quantity of water drawn by customers through their service pipes.
In some cases due to inadequacies in the water supply system, customers demand may not be
met. In which case, their consumption is referred to as “restrained demand”. However water
systems shall be designed for unrestrained water demand.
The required water demand of customers to be met by the PAEW for their domestic use, i.e.
within their residences, varies depending on several considerations such as socio-economic,
cultural and climatic.
Water consumption is expressed as “per capita consumption”, and is the average quantity of
water used per person per day and is generally termed as “lpcd”.
Wherever data is available, domestic per capita demand should be based upon the
consumption at the time of the design, increased appropriately over the project design horizon,
which is usually 25yrs.
4/15
Design Guidelines TET/SS/5501
Date: 14/05/2015
BASIC DESIGN CRITERIA Issue: 1.1
2010
from
Parameter Governorate Water
2015 2020 2025 2030 2035 2040
Balance
Domestic Muscat 175 180 185 190 195 200 200
consumption as Batinah North 167 175 180 185 190 195 195
drawn at tap in
litres/head/day Batinah South 156 165 170 175 180 185 185
Buraymi 180 180 180 180 185 190 190
Dakhliyah 150 158 165 170 175 180 180
Dhahirah 148 154 160 165 170 175 175
Sharqiyah (North and
South)
134 152 160 165 170 175 175
Wusta 130 135 140 145 155 160 160
Musandam 191 191 191 191 191 191 191
These are indicative figures only that apply across a Region. It can be expected that there will
be variations within a Region.
Where water is being distributed by the tankers, the consumption of 22 gallons /capita/day is to
be used.
Where there is not expected to be any specific non-domestic high-usage, there are different
methods to calculate the water consumption, such as:
Commercial user can be converted into the equivalent number of domestic user,
Number of employees at the commercial site divided by the population density per
house in the region to get the equivalent number of properties,
Hotels, clinics and hospitals can be converted into domestic properties by considering
the number of employees so that in turn the usage can be calculated.
Generally the domestic usage uses the greatest volume of water per square meter of any other
type of user.
The following table shows some values of non-domestic consumption for special uses:
5/15
Design Guidelines TET/SS/5501
Date: 14/05/2015
BASIC DESIGN CRITERIA Issue: 1.1
A general “rule of thumb” is to allow 20% of the domestic consumption for non-domestic usage
(including government).
Where there are known to be industrial premises that will have a high water consumption or
other developments such as tourist complexes, shopping malls and industrial parks, it is
essential that the anticipated water demand is discussed with the appropriate industrialists,
developers and planning authorities.
Beware that there is a tendency for planners to over-estimate water needs in order to ensure
the adequacy of the water supply to a development.
1. Leakage – slow continual loss of water through small holes in the mains, poor joints and
the like;
2. Bursts, where the volume lost can be large but are generally of short duration;
3. Water lost when a mains system has to be drained down in order to repair a leak or
burst, including water used to flush the main and take water quality samples after the
burst;
4. Water lost from reservoirs and other storage facilities due to non-closing inlet valves,
wash-out valves not fully closed, incorrectly set water level recorders when a reservoir is
filled by pumps controlled by the reservoir level and from leakage through the structure,
and
5. Water lost from leaking pump glands, inadequately maintained sluice valves, hydrants
etc.
For a new distribution system that has been correctly designed, installed and commissioned,
losses should be negligible within the early years of the pipe system. In order to allow for some
leakage, especially during the later life of the system, an allowance needs to be made.
The PAEW will use water during its normal day-to-day operations for such activities as mains
cleansing and running hydrants for water quality sample analysis.
Normally, the water used is minimal and can be considered as included within the technical
losses. If there is known to be specific problems in the area, for example with debris settling in
the mains due to the condition of the mains or as sand “carried over” from the treatment/source
works, an allowance of 2% of customer demand can be assumed.
In Oman the Directorate General of Civil Defence set the requirements for fire fighting.
6/15
Design Guidelines TET/SS/5501
Date: 14/05/2015
BASIC DESIGN CRITERIA Issue: 1.1
The design of new distribution network should incorporate fire hydrants in accordance with the
Directorate General of Civil Defence requirements. Each project must get their approval for the
location of fire hydrants.
The additional ground service reservoir capacity for fire fighting is as follows:
3
Population (Capita) Capacity (m )
Less than 5,000 50
Less than 10,000 100
Less than 20,000 200
Less than 30,000 300
Less than 40,000 350
Less than 50,000 400
Less than 60,000 450
Less than 70,000 500
When designing the flow capacity of a distribution system, the following fire flows shall be
incorporated, depending on the population of the area served.
Commercial losses are generally included at design stage within domestic and non-domestic
consumptions.
In addition to the recorded flow of water to a customer, there might be an additional flow not
recorded by the meter due to wear of the meter; the meter being incorrectly installed or, in
extreme, the meter has become blocked or has stopped recording for some other reason.
A key consideration can be the type of meter installed being one that is not capable of recording
very low flows that can occur when a customer’s inlet valve to a cistern is not closing off.
7/15
Design Guidelines TET/SS/5501
Date: 14/05/2015
BASIC DESIGN CRITERIA Issue: 1.1
It should be noted that the meter error is included within the above per capita consumption
rates. Thus, meter error normally affects the income received by the PAEW and the historical
records of consumption in a given supply area, not the quantity of water that it has to supply.
These are obviously not known as they would be stopped, disconnected or converted into a
legitimate connection. As such no specific allowance need to be made, unless it is known that
the mains are to be laid in an area where illegal connections may be made.
Water demand of customers can vary by the hour, by the day and seasonally.
The total quantity of water supplied or drawn for 365 days, divided by 365 is the average daily
demand. This is the normal reference flow.
Domestic per capita figures quoted relate to the annual average demand.
At various times of the year and as a result of seasonal needs, people will use more water in
some days. A similar higher demand can occur at weekends when customers are at home. This
is known as the peak day demand. The peak can vary from one area to another. Past records
of the study area, or a similar one, should be consulted to determine the historic peak day factor
to be used in the design.
People draw water according to the needs. The PAEW has to meet the instantaneous water
demand when many people wish to draw water at the same time e.g. in the morning before
going to work. This is known as the peak hour demand. The peak hour demand can be
extremely variable, depending as it does on the actions of people in an area. Within a
predominantly residential area where all the customers leave at around the same time each day
to go to work, take children to school, the peak hour factor can be as much as 5 times the
annual average. The peak hour demand can be significantly reduced where water goes first into
a storage tank, and people draw from the storage. The flow to a property is then limited by the
capacity of the service pipe; not the quantity of water used instantaneously.
The amount by which a peak demand exceeds the annual average demand is known as the
peak day or peak hour factor. The peak factors do not apply to all categories of demand. For
example, leakage will not vary. Industrial demand is usually more consistent – indeed the
PAEW can ensure a consistent draw-off by requiring the industrial premise to have storage and
by limiting the size of the service pipe to the premise.
Where there is no historic data available, the following can be used as a guide:
Peak day flow = 1.3 × annual average demand (based on the average day demand in the peak
week) excluding leakage or 1.24 times water in to supply i.e. inclusive of leakage
Peak hour flow = 2.5 × peak day flow.
8/15
Design Guidelines TET/SS/5501
Date: 14/05/2015
BASIC DESIGN CRITERIA Issue: 1.1
2. DISTRIBUTION SYSTEMS
2.1.1 General
Any design must take into account the likely growth in demand in the areas that will be fed from
the new main(s).
Whilst it is normally not desirable to lay a second pipe in the future to allow for future growth,
there can sometimes be an advantage. For example, if the development is to be staged it might
be cost beneficial, if space permits, to lay one main for the immediate development and to
follow this with a duplication when subsequent development takes place. An alternative would
be to convert a gravity main to a pumped main to “force through” more water.
Such phasing is only likely to be cost effective for large diameter mains and when there will be a
significant time difference between the development phases. The justification can only be after
a cost benefit analysis is made.
A more likely, and advantageous, scenario would be to lay one main along one route and then
duplicate the main along a second, separate route.
In some instances, short sections of main across roads have been installed and left blanked off
allowing an additional main to be laid in the future picking up these blanked off mains. This
allows an extra parallel main to be laid at minimal cost as the difficult sections have been
installed at the time of the original main being laid.
The design horizon for PAEW projects is 25 years. However for consistency issues, horizon
currently used is year 2040.
See above.
Surprisingly and consistently, a “rule of thumb” all-in peak day design flow that can be used for
preliminary estimating within an area, is found to be between 300 and 350litres/head/day.
In a distribution system water should be supplied with adequate pressure and flow. However,
pressure is lost by the action of friction at the pipe wall and in pipe line components such as
valves. The amount of pressure loss is also dependant on the water demand from customers,
pipe material, length, gradient and diameter.
To deliver sufficient quantities of water the pressure head in the network should, wherever
possible, be at least 1.5 bar (15 m.w.c., worst point peak day, peak hour) in all parts of the
network, including the remotest and highest points. The maximum pressure should not exceed
6 bar (60 m.w.c.).
In case of fire fighting flows, pressure in the network shall be maintained as minimum positive
value i.e. negative pressure should not be developed in the network.
9/15
Design Guidelines TET/SS/5501
Date: 14/05/2015
BASIC DESIGN CRITERIA Issue: 1.1
3.1 Headroom
Not used in the design of distribution mains, but used for source/treatment works, pumping
stations and transmission mains, is the concept of “headroom”.
Following a major incident, the PAEW’s reservoirs and mains will be depleted. The quantity of
water to be supplied by the PAEW in these conditions must be such as to not only meet
demand, but also to refill the reservoirs and re-charge the mains.
Customers may have been without water for a considerable time. They will want to use water
for a backlog of purposes, and their storage will need to be re-filled.
In order to provide for this addition demand, a treatment works etc. is designed to meet the
average daily flow not over 24 hours, but over 21 hours i.e. the works are designed to supply
24/21 (1.14) times the annual daily flow or, put another way, with 15% extra capacity than would
otherwise be provided. This ratio can be refined for large systems where several sources of
water or pumping stations may be used concurrently to supply the demand.
Sometimes it will be necessary to consider alternative routes and also intermediate boosters to
re-lift the pressure.
Sometimes it is necessary to tunnel under obstacles with a relatively short section of smaller
diameter main. Directional boring of large diameter pipes can be a major cost and so reducing
the size of the main at such crossing points is often desirable. Often for security of supply such
crossings are duplicated. For example a 400mm main could cross a major road with 2 parallel
300mm diameter mains. If this action is taken, the twin bores should be suitably distanced apart
so that an incident to the first bore does not affect the second. The water carrier pipe should be
laid within a sleeve to enable a failed pipe to be readily removed and replaced. For the same
reason, two adjustable couplings with a connecting piece should be provided.
All crossings of major obstacles should be guarded by in-line valves either side of the obstacle.
All branches off a transmission and trunk mains should be metered, as required by the PAEW
Non-Revenue Water Manager, within the Planning and Asset Management Department.
10/15
Design Guidelines TET/SS/5501
Date: 14/05/2015
BASIC DESIGN CRITERIA Issue: 1.1
No service connection should be taken directly off a transmission or trunk main. A fault with the
connection may require the main to be shut down, with possible consequences on maintaining
supplies. If a connection is required, it should be taken from a tapping drilled into a blank flange
on a branch tee, “guarded” by a valve.
The pressure within a pipeline is determined by the pressure at the start of the pipeline and at
the terminal point. Pressure at various points along the pipeline is shown on the hydraulic
gradient that must be prepared for all transmission or trunk mains during preliminary design at
the latest.
The hydraulic gradient can be used to determine the pressure rating of the pipe to be used.
It is important to ensure that:
To avoid the above happening, a break pressure tank may be required, or an elaborate control
system installed at the terminal reservoir.
If branches are to be taken off the main under design, the adequacy of the pressure at the take-
off must be determined and, if necessary, a booster pump(s) or a pressure reducing valve
installed.
Normally the aim of the design is to transfer a desired flow down the main whilst achieving a
minimum pressure at the far end. This minimum pressure could be the top water level of a
service reservoir or water tower. The pressure could be a service level required to feed
properties or the desired suction pressure of a transfer pump at the end of the main being
designed.
3.4 Velocity
Normal design velocity is 1 m/s. This figure is the point at which particles in the main will be
picked up. This helps to ensure that the main is self-cleaning and reduces long term build up
inside the main.
A peak velocity as high as 2.5 m/s is possible but is seldom considered due to the high stresses
this can cause and high pressure loss than can be generated over short distances. A peak
velocity of 2 m/s is more common but will depend on pipe diameter (more acceptable for large
pipes than small diameters).
3.5 Surge
All transmission and trunk mains, pumped or gravity, should be evaluated for the risk of
excessive surge pressures developing. If required, anti-surge measures should be adopted and
necessary protection provided to the pipeline.
3.6 Valves
11/15
Design Guidelines TET/SS/5501
Date: 14/05/2015
BASIC DESIGN CRITERIA Issue: 1.1
Valves should be installed so that, where possible, all parts of the network can be controlled
without adversely affecting another part. As a minimum valve shall be installed:
On all branch connections,
On all branches from feeder mains,
Between feeder pipes and hydrants;
Not more than 2 valves at a tee,
Preferably at a uniform distance from pipe intersections;
Not more than 3 valves at a cross,
Washouts at all valley points.
The frequency of in-line isolation valves should be determined for each pipeline and shall be
located strategically. A maximum spacing of line valves for transmission main should not
exceed 5km and 2 km for primary trunk mains and maximum 1 km for distribution lines.
Gate valves with flange joints shall be used on pipelines ≤ DN 400. For pipelines > DN 400
butterfly valves shall be used.
All valves must be located with due concern for the safety of the PAEW staff/contractor during
their operation.
Valves can be buried or installed in a chamber. The criteria for chambers are given in the
Design Guidelines for Transmission and distribution pipelines TET/DG/5005.
The chambers should be constructed to take the end thrust of the pipe against the closed valve.
Some in-line valves may be electrically operated and some provided with a by-pass
(systematically above DN 400).
In order to prevent an air lock in the pipeline, an adequate number of suitably designed air
valves need to be incorporated into the pipeline design.
Air valve design is a special subject but generally air valves require to be located:
12/15
Design Guidelines TET/SS/5501
Date: 14/05/2015
BASIC DESIGN CRITERIA Issue: 1.1
Transmission Lines
o Ductile Iron up to 600 mm diameter;
o Above 600 mm dia comparison should be made with MS pipes (generally
epoxy coated in and out or 3 layers PPE);
o In special cases like high pressure, small diameter pipes MS pipes may also
be used.
Where a pipeline contains flexible joints, concrete thrust blocks must be designed and
constructed at all changes in pipe direction horizontal and vertical. The thrust block must be
capable of resisting the pipe test pressure; not the operating pressure which will be lower.
Sometimes along long sections of trunk main it is necessary to re-lift the pressure.
For a pumping main, there is normally a choice between a large pipe diameter with a
corresponding low pumping head – a high CAPEX/low OPEX option - or a smaller pipe
diameter with a larger pumping requirement – a low CAPEX/high OPEX option.
In order to evaluate the options and determine the most suitable, a cost benefit analysis is
required considering both OPEX and CAPEX, over the whole life of the assets. The cost of the
booster maintenance, replacement and running costs should be considered.
Having a transfer booster mid-point along a transmission main can have a dramatic impact on
pressures along the length of the main. It is possible to use mains with lower pressure rating
and background leakage may also be reduced. Additionally future mains breaks should be
reduced as a result of operating at a lower average operating pressure along the length of the
main.
4. WATER QUALITY
Consideration to water age should be made at design stage. Increased residence may lead the
deterioration in water quality e.g. reduce chlorine content, taste ,odour and microbiological
growth.
Hydraulic modelling should be used to assess age and potential water quality impact.
Designing pipeline`s future growth should consider range of flows (retention time) over the life
time of the pipe e.g. initially residence time may be significant due to low demand.
13/15
Design Guidelines TET/SS/5501
Date: 14/05/2015
BASIC DESIGN CRITERIA Issue: 1.1
5. CONTROL PHILOSOPHY
In this instance the demand from the customers determines how much water will flow down the
main. There is little control that can be used on such a system other than pressure control.
The main will have been sized to meet peak demand usage however at night demand is much
lower. Therefore the pressure loss across the main will be lower and the pressure on the main
and within the demand area will increase.
It is possible to install a pressure reducing valve at a point along the new main that will reduce
pressures at night to minimize leakage and burst rate.
In most PAEW systems, transmission main do not feed directly distribution zones.
Within PAEW the water is generally not directly sent to distribution mains in demand areas.
Generally all the water reaches the storage service reservoir and is distributed by gravity.
In this case the normal method of control is to install a control valve on the inlet to the reservoir.
This can be controlled in three ways:
1. A valve – When water level in the reservoir falls below certain level the valve opens
automatically and allowing unrestricted flow into the reservoir. If the level exceeds an
upper control point the inlet valve shuts. This can be a Floating valve. However this
system is not desired as it often generate overflow if the valve is not closing properly. An
electrical valve controlled by the level in the reservoir is therefore preferred.
2. Flow Control – A modulating control valve on the inlet to the reservoir operates such that
a set flow is allowed into this reservoir. This control can be adjusted remotely from an
operational control room.
3. Pressure Sustaining Valve – A modulating control valve on the inlet to the reservoir that
maintains a set pressure upstream on the transmission main. This form of control is
most common where there is a high point on the transmission main that prevents
unrestricted flow from going into the reservoir. A PSV will ensure that positive pressure
always exists on the transmission main.
This can occur if there is a high point at the end of the transmission route which requires a
booster to lift the water or if the transmission main is of such a long length that a simple
transmission system with realistic mains diameters is not possible.
It is possible that an economic assessment of mains capacity vs. boosting energy indicates that
this is the preferred solution.
The size of the transmission main will influence the suction and delivery at the transfer booster.
14/15
Design Guidelines TET/SS/5501
Date: 14/05/2015
BASIC DESIGN CRITERIA Issue: 1.1
It is possible to combine all these elements and controls to ensure that it is possible to transfer a
given amount of water along any feasible construction route.
Wherever possible, risk should be designed out of the water supply system.
Reservoir provides adequate security of supply to a network allowing enough time for a
transmission repair to take place, or a treatment works failure rectified. All supply areas should
have a minimum of 48 hours storage located after the transmission system and as close as
possible to the area of supply.
Whenever possible and providing a significant risk reduction effect compared with additional
costs the design of the system will take into account the following considerations:
Alternative supply routes;
Limiting repair time through the use of standard pipe diameters and adequate provision
of inline valves and corresponding fittings (washout and air valves);
Parallel pipes or ring main arrangements.
15/15
Design Guidelines TET/DG/5002
Date: 14/05/2015
WELLS AND ACCESSORIES Issue: 1.1
Electronic Document, only the original archived in Quality Department is signed / Printed copies uncontrolled
Revision Date Details
1.0 03/12/12 First Issue
1.1 14/05/15 Few typo errors corrected
Contents
1. GENERAL .................................................................................................................................................... 2
2. WATER SOURCES .................................................................................................................................... 2
3. GROUNDWATER IDENTIFICATION ..................................................................................................... 2
3.1 Hydrogeology ........................................................................................................................................... 2
3.2 Surface Geophysics .................................................................................................................................. 3
3.3 Subsurface Geophysics ............................................................................................................................ 3
3.4 Well site location ...................................................................................................................................... 3
3.4.1 Desk study ................................................................................................................................................ 3
3.4.2 Site survey ................................................................................................................................................ 4
4. WELL DRILLING ....................................................................................................................................... 6
4.1 Drilling Techniques .................................................................................................................................. 6
4.2 Drilling Procedure .................................................................................................................................... 6
4.2.1 Core Drilling for Surface Casing ............................................................................................................. 6
4.2.2 Installation of Surface Casing and Concrete Protection.......................................................................... 6
4.2.3 Well Core Drilling .................................................................................................................................... 6
5. WELL CASING AND SCREEN ................................................................................................................. 7
5.1 Physical and Chemical Qualities of Casing and Screen Materials ........................................................ 7
5.1.1 Physical..................................................................................................................................................... 7
5.1.2 Chemical ................................................................................................................................................... 8
5.1.3 Joints ......................................................................................................................................................... 8
5.1.4 Screen ....................................................................................................................................................... 8
5.1.5 Dip Tube ................................................................................................................................................... 9
5.1.6 Gravel Pack .............................................................................................................................................. 9
6. WELL DEVELOPMENT .......................................................................................................................... 11
7. PUMPING TEST ........................................................................................................................................ 11
7.1 Step-Drawdwn Test ................................................................................................................................ 11
7.2 Constant Discharge Test ........................................................................................................................ 13
8. GENERAL PROTOCOL TO MAINTAIN DURING MONITORING PUMP TESTS .......................... 13
9. METHODS TO MEASURE DISCHARGE .............................................................................................. 14
10. DTH VIDEO LOGGING ....................................................................................................................... 15
11. WELL HEAD FACILITIES .................................................................................................................. 15
12. WELL DISINFECTION ........................................................................................................................ 15
13. WELL HEAD PLATFORM AND ACCESSORIES ............................................................................ 16
14. PUMPING SYSTEM ............................................................................................................................. 16
15. WELL COMPLETION REPORT ......................................................................................................... 17
16. REGULATION FOR THE PROTECTION OF THE GROUND WATER ......................................... 17
1. GENERAL
This document in general, is a Guideline detailing the standards and specifications that are
recommended to be followed for ''Bore Well Drilling'' in the works related to Public Authority for
Electricity and Water.
This document includes overall information, criteria and practices for construction of wells in
different aquifers (formations).
2. WATER SOURCES
Though ground water is one of the major sources of water in Sultanate of Oman, due to the
poor quality and quantity of available ground water in certain areas, sea water desalination is
carried out to meet the potable demands of the citizens. But as a reserve, ground water is used
as and when needed on emergencies and hence this exercises to standardise the abstraction
techniques of the ground water.
a. Open Wells
b. Bore Wells
Of the above, Open wells are not much suitable for bulk abstraction due to the limitation in
depth. Instead, deep drilled Bore wells are widely used by Water Supply Agencies and hence
this document focuses mainly on the Bore Well construction and its related Techniques.
3. GROUNDWATER IDENTIFICATION
Be it open well or bore well, the well location is a prime factor which would very much influence
the performance of the well. Selection of the aquifer/well location depends upon the following
aspects:
1. Hydrogeology
2. Surface Geophysics
3. Subsurface Geophysics
3.1 Hydrogeology
In groundwater resource identification, the objective is to locate deposits of ''water bearing sub-
strata'' with relatively high permeability. Such a water bearing sub-strata is called ''aquifer''. The
potential of an aquifer is mainly determined by:
In order to classify them as potential aquifers such deposits should meet the following
requirements.
A thorough analysis of the underground stratification, buried topography, inflow and outflow,
rainfall, evaporation etc. of the related area needs to be carried out to determine the quality and
quantity of water that can be abstracted for a considerably a long time from any aquifer. The
performance and the available data from the nearby wells in operation could also provide
information on the aquifer under study.
Surface Geophysical surveys are of major importance to assess the status of underlying water
aquifer. The survey is carried out on the ground surface prior to reconnaissance drilling in order
to define areas with greatest potential and to find the best locations for water abstraction. Two
types of geophysical surveys are widely in use:
Subsurface Geophysics study requires drilling of Pilot Bore hole to conduct certain studies at
the depths of the aquifer. This operation consists of running special probes upward/downward
in the borehole in order to identify water bearing strata. A 100 mm reconnaissance borehole
down to the bedrock is drilled to make sure the entire thickness of the aquifer and its
characteristics. Two types of Subsurface geophysical surveys are widely in use :
From the borehole observation the geological strata, ground permeability and water salinity can
be assessed. Figure No: 1 shows samples of boring logs.
With the acquired data and information from the above, the suitable well location shall be
identified following the sequences of activities as below:
Anyhow, in the Sultanate, most of these exercises are done by Ministry of Regional
Municipalities and Water Resources and the final recommendation on the well location and the
depth to drill are provided along with the ''Well Drilling Permit'' which is mandatory before
commencing the works.
Fig 1. Drilling
Logs
4. WELL DRILLING
As a general rule, after finalising the well location and the parameters, the production bore well
shall be drilled around 50 m away from the pilot bore well to avoid interferences. The choice of
method of drilling depends primarily upon the geological strata and the depth to drill.
1. Rotary Percussion drilling used for aquifers with consolidated hard strata such as
limestone, sandstone, plutonic or volcanic rocks. This technique would involve using
foam to remove the drill cut materials.
2. Rotary drilling adapted to drill through unconsolidated loose strata. This technique
would involve using ''Bentonite'' mud to stabilize the loose wall while drilling and to flush
out the drill cut materials.
3. Percussion Drilling with bailer is suitable for both but not used generally by PAEW.
For the finished bore well diameter of 6 inch (150 mm) the drilling shall be 225 mm.
For the finished bore well diameter of 8 inch (200 mm) the drilling shall be 325 mm.
Following data shall be recorded as a must while carrying out drilling operation to the full depth:
At this stage, with the available data on quality and quantity of water the suitability of the well to
continue further shall be decided. If found suitable further steps in well construction shall be
continued or else in the unfortunate event of poor quality and or poor yield the well construction
shall be discontinued and filled back as instructed by the Site Engineer.
Well casing and screen go together in a well construction. Well casing is basically a solid
impermeable lining for the drilled hole to act as a wall to maintain the open hole from collapsing.
The material of the casing shall be as per the design and the commonly used are Mild Steel,
Stainless Steel (type 304, 316, duplex), High Density uPVC etc., In certain hard rock formation
well is left without casing but it is preferable to have well casing. This casing shall run through
the entire depth of the well excepting for the places of the screen.
Well Screen shall be made of similar material as the casing but shall have permeability in the
form of slots to allow water from the aquifer to enter into the well chamber with a minimum of
resistance and without letting the passage of sand during pumping. Casing and Screen shall
run through the entire well depth alternatively or in sections as per the well design based on
water bearing strata.
5.1.1 Physical
Material should be in compliance with International Standard Specifications
Shall have greater strength to weight ratio
Uniform wall thickness
Uniform ND and OD
Shall be straight without buckling and bending
Shall be unruffled with the inner and outer diameter
Shall with-stand a maximum ambient temperature of 80 deg C
Shall have homogeneous texture and have smooth finish in and out to avoid hydraulic
friction
Shall be Fire Resistant
5.1.2 Chemical
Withstand pH range 2-12
Chemically Resistant
Acid and Alkali Resistant
Oil and Fat Resistant
Anti Bacterial
5.1.3 Joints
Casing and Screen shall have threaded joints preferably with ''Trapezoidal'' threads as per BS
Standards. Joint length shall be a minimum of 200 mm.
5.1.4 Screen
Selection of Screen depends upon the ground strata, soil type, grain size, available water
quantity, rate of abstraction etc., Salient Parameters of Screen Slots:
rounded slots vertical slots bridged slots wire-wound PVC screen with
slots horizontal slots
The installed Casing and Screen shall be straight and truly vertical in status and any deviated
casing shall result in disapproval of the well.
Diameter
Slot Size
8'' 10'' 12'' 8'' 10'' 12'' 8'' 10'' 12''
Slot No. MM
20 0.5 4 18 18 14
30 0.8 3 2 3 8 6 25 25 16
40 1.0 8 8 30 30 21
50 1.3 10 35 35 24
60 1.5 6 5 6 14 11 11 41 33 28
90 2.3 48 43 37
100 2.5 21 16 16 52 46 39
125 3.2 13 12 13 51 51 45
Gravel pack around the casing and screen is necessary in all cased wells. It shall be of broken
stone – preferably rounded - of nominal size 25 mm. Not lesser than that and not greater than
that. To have optimum performance of the well the gravel pack shall not be lesser than 75 mm
thick around the casing and screen.
Gravel shall be homogenously filled along and around the casing/screen. Packing shall be from
the bottom to the top without any gaps. Verticality of the casing and screen should be
maintained and ensured all along while gravel packing. While doing the gravel packing ''Well
Centralizer Rings'' shall be installed at a minimum of 10 m centre to centre or as frequently as
it may be required for the full depth of the well to maintain the verticality of the well. Top of the
gravel pack shall be concrete sealed at the level of surface casing.
A finished cross section Well shall have the following features as shown in the Sketch below:
6. WELL DEVELOPMENT
After installation of the casing, screen, gravel pack, centralisers and dip tube, the well shall be
developed in order to:
air-lifting
pumping from low to high discharge rate (over pumping)
pumping by steps
jetting and swabbing
Chemical cleaning - adding acids, polyphosphates
air-flushing -injecting pressurized air in to the well
Two main parameters shall be monitored to assess the efficiency of the well development:
Upon completion of well development, pumping tests shall be can be carried out to assess the
recommended yield of the well.
7. PUMPING TEST
Pumping tests are usually performed once the well is completed and properly developed so as
to get a clear concept of how the well would behave and it's performance and efficiency. It also
helps in arriving at the recommended pumping rate and pumping pattern of the well.
Two types of Pumping Tests which are in vogue and shall be used:
Step-Drawdown Test
Constant Discharge Test
A step draw-down test shall involve pumping at different steps - a minimum of 3 steps - for a
duration of 60 to 120 minutes each. It shall be performed at increasing discharge rates as
detailed in the following indicative sketch. Before commencing the test it is mandatory to
observe and record the Static Water Level with reference to a fixed datum and with date and
time stamp. The same reference point shall be used in all the tests at any time.
Temperature, Electrical Conductivity, Salinity and pH of the water shall be measured and
recorded during each step with time stamps
The ''Critical Flow Rate'' is defined as that particular pumping rate beyond which the turbulent
flow tends to increase the drawdown of the well in a geometric progression.
All the findings and observations of the tests shall be clearly recorded figuratively and
graphically for future reference and as a permanent history record of the well. These data shall
be stored in hard copy and as well as in soft copies.
After completion of step draw-down test enough time shall be allowed for the well to regain its
original status before starting subsequent test. and prior to starting the constant discharge test
the water level must be allowed to return to its original level which is recorded prior to
commencing of the Step Drawdown Test.
This test will enable determine the ''Hydrodynamic characteristics'' of the aquifer in general and
well in specific.
During the test pumping rate shall be kept constant. The rate at which Constant Discharge Test
needs to be conducted shall be arrived at from the observed data from the Step-Drawdown test
conducted earlier. The constant discharge test must be continued without any interruption for a
minimum of 72 hours – draw down permitting.
The recovery must be measured at pre-fixed smaller frequencies for at least 12 hours as soon
as the pump stops and at the same time intervals as when pumping.
The water level must be taken with an accuracy of a centimetre from a fixed reference
point whose reduced level is known.
Water levels shall be measured before pumping starts - Static Water Level - SWL
Water levels shall be measured during pumping - Dynamic Water Level - DWL,
according to the following frequency :
From 1 to 2 h 15 min
From 2 to 4 h 30 min
From 4 to 8 h 1h
>8h 2h
Following methods are widely in use for measuring the discharge rate while performing a
pumping test.
Items 1 and 2 are direct reading equipments and the measurement of flow in a 'V-notch' is done
as below.
H = head in m.
Down The Hole Video logging shall be carried out to confirm interior of the well. This operation
allows to check if the inner structure of the well is in conformation to the design and
expectations. Problems like bad position of the screen, deformation of the structure, or
defective screwing, premature clogging or sanding can be detected at this stage. Very
importantly verticality of the well can be confirmed.
Concrete Well head shall be constructed to prevent polluting intrusions from the surface in to
the well. The different elements constituting a typical well head shall be as below:
The most commonly used disinfectants are Sodium hypochlorite and Calcium hypochlorite.
The outline disinfection procedure shall be carried out as described briefly below:
Calculate the volumes
Add chlorine + contact time
Check residual of chlorine
Flush and take sample
The Well head platform and the fencing/compound protection shall be as below:
The plot limits of the well site shall be at least 10 m x 10 m for 150 mm dia wells and
15m x 15 m for 200 mm and above dia wells
Concrete slab 150 mm thick around the well casing over a minimum surface of 5 m²
with a 45 degree slope with a platform height of 100 cm above ground level
Top of casing extending 30 cm above finished well platform level with drilled flanged
end.
Cover designed to prevent all kind of intrusion into the well
Lockable Fencing/Compound to prevent unauthorised access and equipped with a
proper security device.
A PVC coated chain linked fence of 2000 mm high with 3’’ GI tubes shall be installed
with fence holding concrete base of 400 mm deep all around (200 mm above and 200
mm below ground) with a width of 200 mm
Fence top shall have a single armed barbed wire
A Block work compound wall with similar dimensions and safety features
Around the wall water weep holes of 2 inch PVC pipe at 3 meter intervals shall be
provided
In case of compound wall a grilled window shall be provided near the well head to
facilitate crane operation during maintenance works.
Well head platform shall be placed towards one side of the fence/compound to facilitate
crane operation during maintenance works.
After calculating the Specific yield of the well from pumping tests, pump and control system can
be designed. In Oman submersible pumps are mostly in use. Submersible pumps are quicker
and easier to install and are more efficient for deep wells as mechanical losses are limited.
The standard installation of well pumping installation is given in the standard drawings.
In general the Well Completion Report Shall have the following Documents in detail.
In the Sultanate of Oman water resources are limited and groundwater resources are subject to
over exploitation due to growing needs. The protection of the ground water became a major
stake.
In 2000, Water Wealth Protection Law was issued by the Royal Decree no 29/2000 (replaced
the Royal Decree No 82/88) which declares water resources to be part of the national wealth
and contains a specific article dealing with protection of groundwater resources.
Furthermore, the law on Conservation of the Environment and Prevention of Pollution is the key
law on environmental protection and the prevention of pollution in Oman issued by the Royal
Decree No 114/2001 (replaced the original Royal Decree No 10/82).
The pollution protection of the wellfields is under the responsibility of the Ministry of
Environment and Climate Affairs (MECA).
The law on Protection of sources of potable water from pollution is issued by the Royal Decree
No 115/2001 which addresses the protection of drinking water resources from pollution and
empowers the Ministry of Environment and Climate Affairs (MECA) to identify drinking water
protection zones. Activities likely to pollute drinking water will be prohibited in these zones.
The overall objectives of wellfield protection are to safeguard and protect the existing
groundwater reservoir against over extraction, pollution, and to prohibit and eliminate
unauthorised land and water uses that might adversely affect the wellfield.
Wellfield Protection Zones are designated by the Ministerial Decisions. Initially three Ministerial
Decisions were published in 1988/89. These regulations were modified, updated and amended
in 2003.
The well fields are drilled and operated by the Public Authority of Electricity and Water (PAEW).
The list of Ministerial Decisions for wellfield protection zones are following:
Electronic Document, only the original archived in Quality Department is signed / Printed copies uncontrolled
1.1 03/12/12 The word ‘’ REVERSE’’ added in the title of the document
Contents
1. GENERAL.................................................................................................................................................. 2
1.1 Principle of Reverse Osmosis ............................................................................................................... 2
1.2 Field of application ............................................................................................................................... 3
1.3 Different Stages in RO Treatment System … ....................................................................................... 5
2. RAW WATER SOURCE AND QUALITIES ............................................................................................ 6
3. PRE-TREATMENT DESIGN .................................................................................................................... 7
3.1 Pre-treatment performance .................................................................................................................... 7
3.2 Pre-treatment processes ......................................................................................................................... 7
3.3 Chemical conditioning before RO ......................................................................................................... 8
4. RO STAGE DESIGN ............................................................................................................................... 10
4.1 General lay-out .................................................................................................................................... 10
4.2 Main process parameters ..................................................................................................................... 11
4.3 Energy recovery device ....................................................................................................................... 13
4.4 Cleaning in place (CIP) ....................................................................................................................... 14
5. POST TREATMENT DESIGN ................................................................................................................ 14
5.1 Final disinfection................................................................................................................................. 14
5.2 Remineralisation and Correction of pH............................................................................................... 15
6. CHEMICALS HANDLING, STORAGE, PREPARATION AND DOSING .......................................... 16
6.1 Chemical waste disposal ..................................................................................................................... 17
7. INSTRUMENTATION AND CONTROL ............................................................................................... 17
1. GENERAL
Osmosis is a natural process involving fluid flows across a semipermeable membrane barrier. It
is selective in the sense that the solvent passes through the membrane at a faster rate than the
dissolved solid. When two solutions with different concentrations of dissolved salts are
separated by a semi permeable membrane, a flow of solvent from the less concentrated
compartment to the other one occurs, tending to balance the concentration gap. This flow
creates a differential pressure between the two compartments, called “osmotic pressure” –
which depends mainly on the salinity gradient and on the temperature (for a given type of
membrane).
If a pressure higher than that of the osmotic pressure is applied on the compartment filled with
the saline (high TDS) solution, the direction of the flow of solvent will change: solvent (pure
water) will flow from the high TDS compartment to the low TDS side . This phenomenon is
called “reverse osmosis” and may be used to produce soft water from salty water.
Note : Horizontal arrow lines show the direction of solvent molecules flow
Net applied in the Reverse Osmosis shall be higher than the normal Osmotic Pressure.
From a pure hydraulic point of view, a reverse osmosis is similar to a tangential filtration: a flow
of pressurized feed water is divided into a part of permeate (recovered on the other side of the
membrane, at low pressure) and a part of concentrate (flowing out of the system from the same
side of the membrane, as the feed water, and still at high pressure).
The flux through the membrane: flow of water through the membrane, expressed in
cubic meter per square meter of membrane per hour. ( m3/m2/hour or m/h)
The salt rejection: is a measure of salt or TDS that is rejected by the membrane (not
allowed to go with the permeate) and is expressed in terms of percentage:
The higher the feed pressure, the higher will be the recovery rate.
The higher the temperature, the lower will be the osmotic pressure.
The higher the temperature, the lower will be the salt rejection rate.
The higher the flux, the higher will be the salt rejection at constant temperature.
There are numerous types of membranes available in the market differentiated by the material
composition. These all have different properties.
RO plants are meant to produce potable quality water either from sea or brackish water.
It is a reliable process, suitable for a wide range of production capacities, well adapted to
modular design; it can be supplied in containerised skids and quickly.
Distillation process can cope with significant variations in raw water quality without major
operational issues. But the RO membranes are sensitive to water quality parameters, for which
excess values may affect the performances of the treatment or even damage the membranes.
The design of the pre-treatment is therefore the most critical part of a RO plant design.
Membrane failures or bad performances result from a lack of accurate knowledge of the raw
water quality and poor or inappropriate design of the pre-treatment.
The RO performance and energy consumption are directly linked to the salinity of the feed
water. Lower salinity levels require less energy than high salinity levels i.e. brackish water is
more energy efficient per cubic meter of potable water production than sea water.
Energy consumption
Feed Water consumption
Concentrate disposal
Permeate salinity and
Consumption of chemicals.
Problems which arise in the Reverse Osmosis manifest themselves in two ways:
1. Compaction;
2. Degradation;
3. Fouling/ Scaling.
Select system parameters resulting in the most cost effective design and economical
operation.
Select the design which will produce the required quantity and quality of permeate at
the highest possible recovery rate.
A reverse osmosis water treatment plant typically consists of five major process stages as
below :
1. pre-treatment,
2. pressurization,
3. membrane filtration,
4. disinfection
5. remineralisation and pH correction.
Pre-treatment:
The incoming feed water is pre-treated to be compatible with the membranes by removing
suspended solids, adjusting the pH, pre-chlorination, De-chlorination and adding a threshold
inhibitor to control scaling resulting from precipitation of various salts (calcium sulfate, barium
sulfate, calcium carbonate).
Pressurization:
The high-pressure pump raises the pressure of the pre-treated feed water to an operating
pressure appropriate for the membrane and the salinity of the feed water (in practice, this
pressure is higher than the osmotic pressure). The pressurization system may also include the
energy recovery device - transferring the energy from the brine concentrate to the feed water.
Filtration :
Two types of membranes are currently used for RO Systems.
They are generally made of cellulose acetate, aromatic polyamides, or thin film polymer
composites. Both types are used for brackish water and seawater desalination,
although the specific membrane and the construction of the pressure vessel vary
according to the different operating pressures used for the two types of feed water and
the product water quality requirement.
Outlet of permeate
Outlet of reject
There are basically three types of raw water used for drinking water production through RO in
Oman:
Note - TDS can range from 2000 to 45 000 mg/l in the above waters influenced by either costal
salinity or local geology.
For the design of a RO plant, it is of high importance to have an accurate knowledge of raw
water quality and its variability. Full water quality analysis should be done for the following:
Microbiological parameters
Physical parameters
Organic and inorganic parameters
Ionic balance
For design considerations, percentiles are typically used and depends on the water quality data
set. Now in Oman particular attention must be given to new sources as geology has a
significant impact in certain areas.
In addition to the water quality data an environmental / catchment survey should be carried out
to identify all potential point and non-point, pollution sources .Mitigation of these issues should
be included in the proposed design. Earlier experience has shown that use of beach wells
provides significant protection against marine algae blooms (red or green tide), jelly fish. The
use of water safety plan methodology should be followed.
3. PRE-TREATMENT DESIGN
Typical feed water quality after pre-treatment should be within the following ranges:
SDI < 3
Organic matter < 1 mg/L
Turbidity < 0.2 NTU in average, and always less than 0.5 NTU.
The design of the pre-treatment depends on the source or raw water characteristics and
variability.
A Water Safety Plan study for identifying the risks & mitigation should be carried out when
selecting the preferred option to ensure whether any loss of production capacity is acceptable.
Cost benefits of the various options may also be studied:
Screening;
Continuous / Shock pre-chlorination (to avoid bio fouling). Please note continuous
chlorination is discouraged other than in MSF;
Flash mixing and coagulation with ferric chloride;
First stage dual media (sand and anthracite) filtration;
Second stage dual media filtration.
The two stages of filtration may be replaced by Micro Filtration or Ultra Filtration; coagulation is
always necessary.
Option 2 - For sea water, with open intake, subject to green or red tides:
If algae blooms present a risk to production (as is the case of the coasts of Oman
occasionally), dissolved air floatation facility may be included before the filtration stage as it is
easier to ‘float’ algae than to settle flocs and particulates ( as opposed to option 1).
This option starts to mitigate the impact of algae, oils, jelly fish etc., as raw water would typically
be drawn from a depth at which impact would be marginal. Care must be taken on depth, a
figure of 10 to 15 meters (draw off 2 to 5 meters above sea bed) at low tide may be a safe
depth at which Algal blooms will not affect the intake. It must be noted that at the end of a
bloom, the dead algae (or mass jelly fish death) may present an issue if they accumulate of the
sea bed around an intake structure. Environmental considerations and law may prevent this
option.
Option 4 - For sea water from submerged sea wells or beach wells and (brackish)
ground water:
The raw water coming from submerged sea wells, beach wells and brackish ground water may
mitigate many risks and provide a more secure raw water supply from both a quality & quantity
perspective. Environmental constraints may present limitations. Submerged sea wells, although
not currently in practice in Oman, may be a possible option.
For these options pre-treatment requirements may be much simpler compared to other intake
systems . A simple mechanical filtration with MMF may be enough to reach the required SDI
(< 3) for the RO feed. Best practice is to include a single or multimedia filtration to protect the
membranes.
Hydrogen Sulphide is sometimes present in well water (costal or other locations), or even in
sea water, with much decomposing weed in it, if it becomes oxidized it can produce colloidal
sulphur, which can have disastrous effect on membranes.
H2S may be dealt by one or two methods; the feed can be degassed, and then treated with
chlorine, if the feed is hard it may require acid dosing before the degasser.
In many locations odour control is used to get rid of the gas by air strippers, typical techniques
included counter current scrubbing with sodium hypochlorite or caustic soda.
fouling (e.g. by carbonates) and organic / bio-fouling (e.g. bacteria, algae, jellyfish) must be
addressed to protect the membranes and as well as from chemical damage (e.g. by chlorine).
The combination of the targeted pH and the anti-scalant requirement is a key parameter of the
design, as it impacts the operational costs. The lower the required feed water pH, the less anti-
scalant will be required. Although it will increase in the amount of acid required. The choice of
the most suitable anti-scalant depends on the chemical composition of the water, on the brine
concentration rate and on the water temperature. A cost comparison needs to be done
between acid (including caustic soda for pH correction on the permeate) and anti scalant uses.
Pre-treatment process
Coagulation / Floculation
Ultra filtration
One or Two stage dual media DAF
filtration
Dechlorination
Chemical
pH adjustment
Conditioning
Anti scalant
Pre-treatment for bore holes, wells (Brackish water) may include aeration, before Coagulation
and Flocculation to get rid of dissolved gases.
4. RO STAGE DESIGN
Cartridge filters;
Pressure pumps;
RO membranes;
Energy recovery devices;
Booster pumps;
A number of pressures vessels / tubes are installed on skids. One skid can be considered as an
operational unit: all the pressure vessels / tubes of one skid are operated as a single unit i.e.
run together, or washed together.
The number of parallel skids or units is determined as a trade-off between investment costs and
operational flexibility. A plant may be designed such that a capacity upgrade in future can be
achieved by adding an additional skid or unit to a parallel process train.
Each skid or unit is fitted with its own pressure pump and its own energy recovery device.
All the above mostly depend upon the recommendations of the membrane supplier.
Number of passes:
To filter out certain special elements such as Boron it may be necessary to implement two
successive passes. In this case, the partial/ full permeate of the first pass is pumped to a
second pass on order to increase the total salt rejection rate.
In the case of boron treatment, the pH is often adjusted between the first and the second
passes, as boron rejection rate is higher at high pH.
The second pass can be designed for a part only of the permeate flow of the first pass,
depending on the expected efficiency of both passes. In this case, the permeate of the second
pass is blended with the by-pass first pass permeate.
The concentrate of the second pass has generally a low salinity compared to raw water; then, it
can be recycled in the feed of the first pass. This must be taken into account in the general salt
balance, when designing the first pass.
Figure 3 Configuration of two passes RO unit. Figures represent recovery rate at each step
Number of stages:
In brackish water, the TDS content of the concentrate may be relatively low. In such a
condition it can be economical to implement a second stage of reverse osmosis; it consists in
sending the concentrate of the first stage to a second stage of RO membrane, to increase the
total recovery rate. (Unlike the two passes configuration, the two stages design does not
improve the salt rejection rate, but only the recovery rate).
Figure 4 Configuration of two stages RO unit. Figures represent recovery rate at each step
The choice of the membrane type and design of the RO skids are based on the following
parameters:
Feed pressure;
Flux through the membranes;
Average age of the membrane;
Yearly performance decaying rate of the membranes;
Longitudinal pressure drop;
Chemical and biological resistance;
Membrane cleanability.
The choice of the optimum salt rejection rate depends on the quality of the raw water and on
the targeted standard for the permeate. Drinking water is never “salt free” water: hence, a very
high salt rejection is not always necessary.
The higher is the feed temperature; the lower is the salt rejection rate. For each project, the
required minimum rejection rate must be specified at the higher possible temperature.
For brackish water ( TDS is feed water < 3 000 mg/l) : > 90 % Rejection rate;
For low TDS sea water (mix of brackish and sea water, with TDS around 25 000 mg/l) :
> 98 % Rejection rate;
For sea water ( TDS > 35 000 mg/l) : > 99 % rejection rate.
The membranes are designed for different feed (raw) water characteristics and permeate
characteristics depending on the application. Three different membranes are available for
Brackish water, sea water, boron rejection, as well as other applications.
Feed pressure:
The feed pressure is directly linked to the type of membranes (permeability), and to the
targeted recovery rate, feed TDS and target TDS. Typical figures are:
The feed pressure changes with the temperature and salinity. High pressure pumps are fitted
with VFD to control within to set pressure limits to protect the membranes.
With the ageing of the membranes, their performances decreases and the required feed
pressure for a steady recovery rate tends to increase. Salt rejection rates tend to decrease.
The actual feed pressure can be assessed against the design feed pressure to give an
indication of deterioration. The expected life span and performance guarantees should be
clearly documented so that on-going performance measurements and assessments can be
made so that an early indication of quantity or quality deterioration can be identified.
The pressure drop across the membranes is dependent on type and on the number of
membranes per pressure vessel. A standard figure of 1 bar of pressure drop along the entire
length of the membrane is common and acceptable. An increase in the longitudinal pressure
drop may be the clue of abnormal membrane fouling; Cleaning in Place (CIP) is then required
to recover the membranes performances.
The pressure of the concentrate at the outlet of the membranes is equal to the feed pressure
minus the longitudinal pressure drop. This represents a considerable amount of hydraulic
energy, which must not be wasted.
Turbo-pumps,
Pelton turbines
Work-exchanger.
The best recovery efficiency is achieved with work exchangers. A design efficiency of more
than 95 % may be achieved. Typical energy savings from 7.5 kW/Hr/m3 to 3kW/Hr/m3 have
been observed on small scale plants.
The benefits of Energy recovery devices are less on low TDS brackish (10,000 mg/l) water RO
plant; it would be theoretically possible to recover a significant amount of energy on the
concentrate of these plants, but, given the current economic conditions (cost of recovered
energy, cost of the Energy recovery system), it is generally not considered beneficial
Even with a correct pre-treatment and anti-scalant injection, the performances of the
membranes tend to decrease, due to the fouling and scaling mechanisms. Recovery back to
design membrane performances by chemical cleaning (without dismantling the membranes)
should be carried out in accordance with manufactures recommendations. It is not good
practice to skip cleans which are typically required on a three month basis. Although marginal
deterioration in performance may be seen over a short time period, the rate of fouling becomes
exponential. There is a point of no return, at which the membranes cannot be recovered,
leading to premature replacement of membranes. Failure to recover membranes to an
acceptable level can also indicate changes in raw water quality, which can, in some instances,
mean that the anti-scalant being used is no longer effective and needs changing.
Citric acid;
Caustic soda;
NaDDS ( Sodium dodecyl sulfate);
Hydrochloric acid;
Ammonia;
EDTA.
The waste solution from CIP must be neutralized before disposal. Disposal requirements in
Oman are legislated under various environmental laws and Royal Decrees.
Final disinfection;
Correcting the pH and mineralisation of the RO permeate.
Final disinfection can be achieved by injecting gaseous chlorine or solutions from On Site
Electrolytic Chlorine (OSEC) generation system, sodium hypochlorite liquid or calcium
hypochlorite (powdered made up into a solution)
Each type of chlorination system has pros and cons. A significant concern is for safety of the
operator and local community. Prime importance is ensuring that the water is successfully
disinfected, and free form disease causing organisms. It is equally important to maintain a free
chlorine residual into the water supply system to maintain a healthy water to the customer tap.
After the Reverse Osmosis process, the pH of the permeate is acid – because of the initial
acidification to prevent scaling, and because of the retention of the HCO3- and CO3 ions by the
membrane. The pH must be corrected.
Ideally, the goal of remineralisation and pH correction is to reach the calco-carbonic equilibrium
(Langellier saturation Index equal to 0, or slightly positive 0 to 0.2.
Depending upon the characteristics of the raw water, there may be an excess or deficit of CO2
content in the permeate water.
In the case of brackish water with low salinity it is recommended to carry out :
If there is a deficit of CO2 in the permeate (which is generally the case with sea water), the
chemical post treatment would comprises the following:
CO2 injection;
Final pH correction, by injection of lime water or caustic soda.
Lime should be injected as lime water form (maximum concentration: 1.5 to 2.0 g/L) and never
under lime slurry form, as slurry can significantly raise the turbidity of the produced water. i.e a
settling and decanting stage is required.
The types and quantities of chemicals used within an RO plant depends on the characteristics
of the raw water and on the design of the plant.
The reliability of the operation, the consistency of the treated water quality and the life of the
membranes are directly linked to the accuracy of the chemicals dosage, which depends on a
proper monitoring of the injection pumps, a precise preparation of the solutions, and a good
management of the chemicals stock.
Health, Safety and environmental laws, royal decrees and international best practice MUST be
followed. A HAZOPS (Hazard identification and mitigation) review should be carried out as a
part of the design process.
Examples include:
The condition of chemicals storage: easiness of access for delivery, sufficient handling
equipment (cranes, monorail, forklift, etc.) for heavy bags and drums, safety provisions
(retention bunds) in case of leakage of spillage;
Chemical solution preparation; Transfer, make up, transfer, storage volumes and
containment;
Chemical dosing; Duty / standby dosing pumps (rotational operation), secondary
containment of dosing lines, catch pots and calibration pots.
In Oman there are environmental laws and Royal Decrees covering the management and
disposal of such chemicals.
Typically lined evaporation ponds, deep well injection, and disposal to Sea are practiced in
Oman.
The level of instrumentation and automation will depend on the size of the plant.
The minimum of on-line instrumentation must be implemented, for a correct and steady
operation of the plant. This should include:
Raw Water
Chlorine Dosage
Pre-Filtration.
RO Feed ORP
RO Feed Residual Cl2
RO Feed pH
RO Feed water temperature
RO Feed pressure
RO Feed water conductivity
RO Feed water Flow
Permeate
RO Concentrate Pressure
RO Permeate Conductivity
RO Permeate pH
RO Permeate Turbidity
Permeate Flow
Treated Water.
Treated Water pH
Treated Water Residual Free Chlorine
Final Water Flow
Discharge Flow & applicable quality instruments.
All instrumentation must be fitted with data logging and out of range alarm management
systems for local operational control & management.
The requirements for Instrumentation, Control and Automation will be detailed in a separate
document.
All instruments should have a digital output, with sufficient de-bounce for manual logging
purposes.
Process flow diagrams must be provided with full detail of process stage conditions and criteria.
LIST OF REFERENCES.
Electronic Document, only the original archived in Quality Department is signed / Printed copies uncontrolled
Revision Date Details
- Page 12/24 : Section 2.5 : Last formula corrected
1.1 05/05/2013 - Page 13/24: Section 2.7 Pump performance testing added.
Contents
1. Introduction ............................................................................................................................................... 3
1.1 Pump Station Types .............................................................................................................................. 4
1.2 Site Infrastructure .................................................................................................................................. 5
1.2.1 Location ................................................................................................................................................ 5
1.3 Access Road .......................................................................................................................................... 7
1.4 Materials Of Construction ..................................................................................................................... 7
1.4.1 Pump Station Building .......................................................................................................................... 7
1.4.2 Pumps .................................................................................................................................................... 7
1.5 Pump Selection ..................................................................................................................................... 7
1.6 Pipework arrangement and valving ....................................................................................................... 8
1.7 Future Expansion/Up-gradation .......................................................................................................... 10
2. Pump Design ........................................................................................................................................... 11
2.1 Field of use .......................................................................................................................................... 11
2.2 Number of impeller (s) ........................................................................................................................ 11
2.3 Shaft position ...................................................................................................................................... 12
2.3.1 Surface / Immersed / Submersible / Line Shafting .............................................................................. 12
2.4 Type of impeller .................................................................................................................................. 12
2.5 Type of Casing .................................................................................................................................... 12
2.6 Number of Entrances........................................................................................................................... 13
2.7 Specific speed ..................................................................................................................................... 13
3. Components of pump .............................................................................................................................. 13
3.1 Impeller ............................................................................................................................................... 13
3.2 Casing ................................................................................................................................................. 13
3.3 Seals .................................................................................................................................................... 14
3.4 Coupling .............................................................................................................................................. 14
3.5 Bearings .............................................................................................................................................. 14
3.6 Suction pipe......................................................................................................................................... 15
3.7 Foot valve with strainer ....................................................................................................................... 15
3.8 Delivery pipe and delivery valve ........................................................................................................ 15
4. Motors ..................................................................................................................................................... 15
5. Hydraulic calculations for pump ............................................................................................................. 16
5.1 Specific speed ..................................................................................................................................... 16
5.2 Pump design parameters ..................................................................................................................... 16
5.3 Operating point ................................................................................................................................... 18
5.4 NPSH and cavitation ........................................................................................................................... 20
5.5 Motor drive ......................................................................................................................................... 22
5.6 Points to note ....................................................................................................................................... 22
5.7 Pump Performance testing .................................................................................................................. 23
5.7.1 Factory Test......................................................................................................................................... 24
5.8 On site Testing .................................................................................................................................... 25
6. Design of pumping station ....................................................................................................................... 25
6.1 General Recommendations ................................................................................................................. 25
6.2 Access and maintenance ..................................................................................................................... 26
1. INTRODUCTION
The purpose of this document is to provide a brief guideline for the design of small to large
sized pumping stations for the Public Authority for Electricity and Water (PAEW). The
secondary objective is to provide a standardised guide containing requirements relating to the
design of potable water pumping stations and reduce the variability in designs and improve
overall the efficiency.
The principle function of pump station is to transfer water from lower elevation to higher level; in
some instance it is required to boost the flow/pressure or even both.
The principle goals of the design are to ensure that the water pumping station is functional,
reliable, fit for purpose, cost effective, able to be maintained and complies with the
requirements of PAEW.
The complete system should be well planned and designed with particular reference to the
following:
Where technical constraints allow a choice in the type of pumping station arrangement or type
of pumping equipment, the final choice will normally be determined as the most cost-effective
method. Cost effectiveness should be determined by a net present value analysis.
Factors to be considered are:
The net present value analysis shall allow for the different efficiencies for each suitable pump,
the variation in pump duty required for different pipe materials and class of pipe and the
economic life of different pipe materials
PAEW operates a wide range of pumping stations of different configurations and capacities. A
number of these are major pumping stations, most of which draw potable water from reservoir
and pump to service reservoirs/elevated tanks. Most pumping stations are located strategically
within the distribution system.
All stations shall contain at least two pumps (one duty and standby). Duty pump(s) shall be
sized to deliver up to the maximum design demand. The standby pump is programmed to
operate in the event that the duty pump fails or unavailable. Major pumping stations may have
more than two pumps but will always incorporate a standby pump(s). The standby pump(s)
must have at least the same capacity as the largest duty pump(s).
The design of pump station depends on techno economical and geographical considerations.
A pumping station that supplies water to the distribution system is ideally located near to a
water treatment or water storage facility. Booster pumps are required to increase the pressure
within the distribution network. The pumping stations can either be required for full time
operation or only to operate during periods of high demand or low system pressure.
Dimensioning the pump Pump selection is a key factor; the information on pumps (design, type,
size etc...) is detailed in the document below.
This document is a guide only and sound engineering judgement must be applied at all times. It
remains the designer’s responsibility for all aspects of the design and the designer must justify
any variation from these guidelines.
Typical layout of pump building (small and big pump stations) are annexed at the end of the
document. The drawings show typical building layouts, along with pump, pipework and other
electro mechanical arrangements. These layouts are for the information as a guidance, the
design consultant/contractor shall develop in detail to suit design and site requirements.
The choice of site is usually determined by the system requirements, land availability,
availability of electrical infrastructures and aesthetic conditions, but the location should allow for
a suitable layout for the incoming and outgoing water-mains. There should also be sufficient
clearance from surface and subsurface obstructions to allow for construction. Sites located
under electrical power lines should be avoided. Consideration should also be given to the
potential likelihood of future development.
To ensure that the proposed pumping station location and layout are acceptable, the proposed
site shall be approved in advance by PAEW during concept/preliminary design stage. Pump
pedestal level or building floor is to be located above maximum flood level, with the floors being
a minimum of 300mm above the 1:50 year flood level. And the electrical transformers/ pad
mounted substation or emergency generator on the site must also be located at least 300mm
above 1:50 year flood level. The design consultant should fully acquire the site info and
meterological data during the preliminary/detailed design stage; properly design the
surface/stormwater management considering the 1: 50 ARI.
The size of a pumping station site is primarily depending upon the number of pumps
(present+future) and site pipe works. In most cases, pumping station is associated within the
reservoir compound which is located adjacent to road or at Jabel. If the pumping station is to be
located adjacent to road, its entry and exit position should be determined in conjunction with the
Ministry of Transport & Communication and ROP. As much as possible, it shall be located
away or far apart from the residential area and sensitive areas like hospitals, Mosques etc.,
If the pump station is situated adjoined to the jabel (mountain), suitable protection measures to
be considered to protect the pump station from unstable boulders / loose soil that may fall often
from jabel.
During preliminary design stage, the design Consultant should consult with the various regional
stakeholders like MoH, power distribution company (MEDC, Mazoon, Majan, RAECO),
Municipality, MoTC, Ooredoo, Omantel, PDO/OGC, OBC, ROP, Falaj crossings etc.,. This
should be commended early stage of project as getting approvals/NOC can become prolonged
that directly affects/delay the commencement of project execution unintentionally.
Consideration must be given to key issues associated with the project and relevant
stakeholders associated with these issues and bring to the notice of PAEW as and when
required.
Copies of relevant approvals from authorities/stake holders shall be included in the detailed
design report shall be annexed with the Tender Documents.
The following factors shall be considered during the site selection process:
Location Factors Requirements
Site selection Must be located within the plot, ownership of which is dedicated
to PAEW including the easements
Provide all weather access road to pumping station for routine,
emergency operation and normal maintenance activities
Power facilities should be available or able to be economically
provided to the site
Site should have safe access and consideration should also be
given to construction requirements.
If it is located within the reservoir compound, the external pipe
works should not affect/hurdle the future compound expansion
and its pipe works.
Amenity and environment Provision of sufficient buffer from nearby existing built-up areas
and future developments
Adequate entry and exit shall be provided with ascending and
descending bay in consult with MoTC and ROP
Design Proximity to pipeline and reservoirs
Accessibility
Site slope and soil conditions
Flooding Ensure that adequate storm water management drainage from
the pumping station and site including access roads is designed
so that flooding of the facility is avoided
The pumping station site, electrical infrastructures, access road
shall not be liable to flooding during a 1 in 50 year ARI
Supporting Systems In conjunction with determining the requirements for the site
infra-structure, the designer shall consider the requirements for
supporting systems to enable efficient and safe operation of the
pumping station, as
Requirements follows:
− Electrical power and on site generator (if required)
− security
− fire alarm with fire-fighting facilities
− SCADA
− Adequate Turning radius for maneuvering of maintenance
vehicle
− Access road and compound lighting
The surfacing of the pumping station site and access road is site specific.
Preferably approved products and suppliers registered with PAEW shall be used.
1.4.2 Pumps
There is a choice of materials depending on the environment the pump will be working in. The
principal materials are ductile iron, stainless steel, bronze, nickel, titanium alloy and plastics.
Material selection shall vary based on the below major parameters in water (salinity, total
dissolved solids, conductivity, pH and temperature).
A pump is required to provide a range of flows over a range of system pressures in order to
satisfy system demand criteria. The main criteria when selecting a pump is operating
efficiency.
The design consultant is to ensure that there is a commercially available pump which
satisfies the required duty with high efficiency from at least three well reputed suppliers.
Selection of a pump suited to the application, requiring an acceptable level of maintenance and
efficient in operation is critical to achieving minimum whole-of-life costs.
Each pump and drive unit is to be suitable for pumping water and for performing the duty
throughout the specified range. The operating (flow and head) requirements are to be
determined by the design consultant and should be approved by PAEW.
• System flow and head for initial and ultimate requirements (where applicable)
• Pump efficiency within the normal duty range
• Pump speed
• Standby capacity required
• Best efficiency point to be as close as practical or within the normal operating range.
• Availability of spare parts, supported by adequate local service agent
At the pump station the following pipe arrangement and valving are common
a) Suction pipework
b) Delivery pipework
c) Miscellaneous fittings
d) Pipework for surge suppression devices
Suction Pipework
The suction manifold should be sized according to the maximum flow demand, including future
flow demands, if any with a velocity limit of 1.0m/s. The branches from this manifold to the
individual pumps are to be similarly sized according to the range of flows for the pumps.
Flow is to be directed into the suction of the pumps in a uniform manner without turbulence.
Valves, tapers and changes of direction or pipe section are to be no closer than three times
of pipe diameters upstream of the pump suction intake.
Inlet tapers (reducers) are to be eccentric, with the obvert horizontal in order to prevent an
air pocket developing. The sides of all tapers are to be straight and the taper is to be gradual
with an included angle not greater than 15 degrees (ie butt weld tapers are not to be used on
the suction).
The inlet pipe which connects directly to the pump is to be horizontal, straight and of the
same internal diameter as the pump inlet and of three pipe diameters in length. Puddle
flanges are to be incorporated to take thrust on suction pipework when passing through a
wall.
Delivery Pipework
The delivery pipework is to be sized in order to allow for the maximum flow (i.e, future
demand flows, if any) through the pipeline within a velocity limit 2.0 m/s.
Tapers used on the pump delivery may be concentric or eccentric but are to be straight
sided.
Delivery pipe work is to be restrained so that there is no loading back onto the pump flange.
Puddle flanges are to be incorporated to take thrust on delivery pipework when passing
through a wall.
Miscellaneous fittings
Dismantling joint
A dismantling joint is to be provided adjacent to at least one pump flange to allow removal
and re-installation of the pump without significantly disturbing the pipework. As a minimum
the Dismantling joint is to connect the straight section of inlet pipe to the inlet flange of the
pump. Flange thicknesses are to be rated for the test pressure of the system.
Thrust restraint for pipework can also be achieved by the use of thrust restrained type
dismantling joints. The use of adapter type flange is not permitted. Within the pumping
station particular care is to be taken to ensure that there is no loading onto the pump flanges
caused by poor installation or pressure generated forces as this can cause distortion of the
pump body and lead to premature failure of components such as mechanical shaft seals.
The pump is not to be used to support the pipework. Flexible jointed pipes and fittings are to
be adequately restrained. Flange thicknesses are to be rated for the test pressure of the
system.
Where an existing pumping station is being upgraded, pipe pressure class, thrust restraint
and possible fatigue of existing reticulation pipes due to cyclic loading must be checked.
Pressure Gauges
Pressure gauges are required to measure the pipeline suction and delivery pressures.
Tapping points complete with ball type isolation valves are to be located on the
common/individual suction pipe and common/individual delivery pipe.
Flow meter
The flow meter is to record all pumped flows, an electromagnetic flow meter is to be installed
at the common delivery pipework only; flow meter is not required at delivery of each pumps.
The flow meter is to be located so that there is ideally 10 and 5 but no less than 5 clear pipe
diameters upstream and a minimum of 3 clear pipe diameters downstream of the flow meter
from any disturbance (for example, valve, tee, bend, change of direction etc.) in the
pipework. The flow meter is to be flanged and sized as per the manufacturer’s
recommendation (i.e. no tapers are to be used) so that the inside diameter of the flow meter
matches that of the pipework. At least one of the pipe flanges joining the flow meter must be
a dismantling joint to the flow meter to allow removal of the flow meter.
The signal converter and LCD display unit is to be located above the flow meter and
readings displayed in flow rate (m3/h) and cumulative total flow (m3/h). Where the flow meter
is used for control purposes, it is important to specify the required flow range. The flow rate
reading shall be sent to local control room as well as regional SCADA control station.
Testing of Pipework
All pipework within the pump station is to be tested to the design test pressure. Design test
pressure is to be nominated by the design consultant and is to consider operating conditions
(present/future), surge and shut off head.
In general, pumping station is planned to be expandable in the future. The design consultant
ensures that adequate space is provided to accommodate the installation of future pump(s)
and allied equipment (including surge suppression) for smooth expandability. The suction
and discharge pipework is sized and arranged to accommodate future flows without having
to take the pumping station out of service when expansion is required. If it appears to be
impractical or uneconomical to construction the pumping station building to house future
pump(s), the design consultant shall submit a comparative evaluation of cost, operability and
constructability issues at appropriate design stage. This evaluation address alternative
means of providing the desired capacity to meet future capacity requirements. Based on this
analysis, PAEW may direct the design consultant before proceeding with final design of
pumping station relative to future expansion.
2. PUMP DESIGN
In a water supply system centrifugal pump is most commonly used. A pump is a hydraulic
machine which converts mechanical energy into hydraulic energy or pressure energy. A
centrifugal pump is also known as Rotodynamic pump or dynamic pressure pump. It works on
the principle of centrifugal force. In this type of pump the liquid is subjected to whirling motion by
the rotating impeller which is made of a number of backward curved vanes which cause partial
vacuum to suck the water from pump suction. The liquid enters this impeller at its centre or the
eye and gets discharged into the casing enclosing the outer edge of the impeller. The rise in the
pressure head at any point / outlet of the impeller is proportional to the square of the tangential
velocity of the liquid at that point. Hence, at outlet of the impeller where the radius is more the
rise in pressure head will be more and the liquid will be discharged at the outlet with a high
pressure head. Due to this high pressure head, the liquid can be lifted to a higher level.
A centrifugal force is defined as the action that causes something to move away from its
access of rotation.
A centrifugal pump uses an impeller and volute (or casing) to create the partial vacuum to suck
water in and discharge pressure necessary to move water through the pump casing. The
impeller and volute are the essential parts of the pump and help determine its flow, delivery
pressure and suction capability.
There are four main major characteristics to describe a centrifugal pump are as below:
Field of use (type selection);
number of Impellers or stages (single stage pump or multistage or multi impeller pump);
Shaft orientation (vertical shaft or horizontal shaft) orientation;
Type of impeller (closed ,semi open or open impeller);
type of Casing (Volute or Diffuser);
number of entrances (Single suction pump or Double suction pump);
specific speed (Low specific speed or radial flow impeller pump, Medium specific speed
or mixed flow impeller pump, High specific speed or axial flow type or propeller pump)
It is important to know the type of water (raw sea water or potable water). The choice of the
pump also requires knowledge of characteristics of the pumped water (hardness, pH,,
conductivity, sand content etc.).
Horizontal pump: The shaft of the pump is horizontal or parallel to the ground. Entire
pump unit would be installed on the ground level;
Vertical pump: The shaft of the pump is vertical or perpendicular to the ground. Motor is
located above the pump head or at a higher level with an extended shaft.
Surface pump : The pumping unit (motor + pump) is situated outside of the liquid to be
pumped, both motor and pump are above ground level;
Immersed pump: Pump unit is in liquid but motor is above the liquid;
Submersible pump: The pumping unit is immersed in the liquid to be pumped. Both
pump and motor are inside the liquid and they can work only in the liquid medium for
the sake of cooling and cannot work outside;
Pump with line shafting: The motor is situated outside of the liquid to be pumped and
the pump is immersed and they are connected by a shaft.
The type of impeller depends on the type of water to be pumped, the total head and the
discharge.
There are different types of impellers.
Open;
Semi open;
Closed.
Suction can be either single suction or double suction. A single suction impeller allows liquid to
enter the centre of the blades from only one direction. A double suction impeller allows liquid to
enter the centre of the impeller blades from both sides simultaneously.
Pumps can be classified according to the suction and delivery of the liquid with reference to the
position of the access of the impeller.
In case of a volute pump a spiral casing is provided around the impeller. The water which
leaves the vanes is directed to flow in the volute chamber circumferentially. The area of volute
chamber gradually increases in the direction flow. Thereby velocity reduces and hence
pressure increases. As the water reaches delivery pipe a considerable part of kinetic energy is
converted into pressure energy. However, eddies are not completely avoided, therefore some
loss of energy takes place due to continually increasing quantity of water through volute
chamber.
In case of a diffuser pump a guide wheel containing a series of guide vanes or diffuser is the
additional component. The diffuser blades which provides gradually enlarging passages
surround the impeller periphery. They serve to augment the process of pressure built up that is
normally achieved in volute casing.
Normally all centrifugal pumps will have single suction entry for water inlet. In case of double
suction, two impellers are set back to back. The two suction eyes together reduce the intake.
The two suction eyes together reduce the intake velocity reduce the risk of cavitation. Mixed
flow type double suction axial flow pumps besides are capable of developing higher heads
A radial flow impeller has small specific speeds (300 to 1000) & is suitable for discharging
relatively small quantities of flow against high heads. The direction of flow at exit of the impeller
is radial. The mixed flow type of impellers has a high specific speed (2500 to 5000), has large
inlet diameter D and impeller width B to handle relatively large discharges against medium
heads. The axial flow type or propeller impellers have the highest speed range (5000 to
10,000).
3. COMPONENTS OF PUMP
Impeller
Casing
Seals
Coupling
Bearings
Suction pipe
Foot valve with strainer
Delivery pipe and delivery valve
3.1 Impeller
Impeller is the rotating component of the pump. It is made up of a series of curved vanes. The
impeller is mounted on the shaft connecting an electric motor
3.2 Casing
Casing is an air tight chamber surrounding the impeller. The shape of the casing is designed in
such a way that the kinetic energy of the impeller is gradually changed to potential energy. This
is achieved by gradually increasing the area of cross section in the direction of flow.
3.3 Seals
Seals are leakage control devices. Seals are basically meant to control escape of liquid from
the volute along the shaft. The seals are designed to ensure that the point where shaft passes
from the inside to the outside of the pump does not leak.
Packings are made of woven fabrics impregnated with various lubricating substances in order
to lower friction. It is packed within a gland housing that needs manual adjustment to prevent
leakage but still ensure lubrication by the liquid to be pumped.
Mechanical seals are another key component of pumps. They consist of two faces, one
stationary on the outer side and the other rotating inner side and are located on the shaft
between the impeller and the rear casing.
3.4 Coupling
It is a device used to connect pump and motor shafts together for the purpose of transmitting
torque. The coupling is a unit which connects the motor shaft and the pump shaft enabling the
transfer of torque energy from water to pump.
3.5 Bearings
Bearings are intended to provide smooth friction free rotation of the shaft of motor and pump.
A wide variety of bearings is available.
Rolling body: Balls or rollers ensure proper contacts between the rotating and the
stationary rings.
It is the pipe connecting the pump to the sump, from where the liquid has to be lifted up.
The foot valve is a non-return valve which permits the flow of the liquid from the sump towards
the pump. In other words, the foot valve opens only in the upward direction. The strainer is a
mesh surrounding the valve, it prevents the entry of debris and silt into the pump.
It is pipe connected to the pump to the outlet delivery connection and delivery valve is fitted on
the discharge line to regulate the flow of liquid from the pump.
4. MOTORS
The selection of the motor is done according to the capacity of the pump. Motor selection shall
be based on the impeller size, maximum capacity, specific gravity of the fluid, and service
application. The selected motor shall be capable of operating the pump in any range on
selected pump curve. Motor capacity shall have sufficient margin min 10% over the maximum
operating point. Motor shall be designed with proper overloading service factor minimum of
1.15%.
When determining a motors size, safety margins should be considered. Safety margins
normally vary between 10 and 15 %.
For large motors, soft-starters should be used in order to reduce the electrical current intake.
Variable frequency drivers (VFD) may be used to adapt the pumping regime to output
parameters (pressure, flow rate…). VFD should be limited to the range of 50% to 120% of the
nominal frequency of the motor.
Specific speed is a number characterizing the type of impeller in a unique and coherent manner
and is determined independent of pump size. This factor can be useful when comparing
different pump designs.
A wide variety of impeller types are available. Depending on the quality of the fluid and the Q/H
desired a choice must be made.
Specific Speed or Suction specific speed indicated by Ns and it’s a dimensionless quantity,
Specific speed is a number which indicated whether the suction condition of pump are sufficient
to prevent cavitation.
For the selection of pump size the flow rate or capacity Q (m3/h) and pump head H (m.w.c) are
needed at the required duty point.
The capacity of a pump is the amount of water pumped per unit time. Capacity is also called
discharge or flow rate (Q). In metric units it is expressed as litres per minute (l/min) or cubic
meters per second (m3/sec).
Head is the net work done on a unit weight of water by the pump impeller. It is the amount of
energy added to the water between the suction and discharge sides of the pump. Pump head is
measured as pressure difference between the discharge and suction sides of the pump.
Expressed in feet (ft) or meters (m) of the liquid. Pressure and head are two different ways of
expressing the same value. Usually, when the term "pressure" is used it refers to units in
kilopascals (kPa), whereas "head" refers to meter’s (m). A column of water that is 2.31 ft high
will exert a pressure of 1 psi.
These variables are determined for the pumping regime that occurs the most frequently. The
correct pump size and speed can then be selected from pumping group (pump + motor)
performance curves. Other parameters such as efficiency η, input power P and N.P.S.H. of the
selected pump can be found from its individual curves.
The main pump curve of a pump gives the relationship between the two variables Q and H. A
typical pump curve of a constant speed centrifugal pump is given below.
A characteristic feature of the curve of a centrifugal pump is the increase of the flow rate Q
while decreasing head H.
The selection of the appropriate pump curve depends on the specific duty point requirements.
For the same value of (ΔH) the value of (ΔQ) changes considerably between flat and steep
curves of the pump.
To assess the necessary pump head H, the system head, Hs, must be determined.
Hs = hsta + Ʃ hf
Where
hsta = static head: height difference between the suction and the discharge fluid levels.
Ʃ hf = The sum of all pressure head losses caused by friction in pump and pipeline systems, for
a given flow rate.
The system characteristics, i.e. the Q – H relationship of the pipe system have a form as can be
seen below (fig 2).
The point of intersection between system curve and the pump curve is the operating point.
The operating point changes based on the arrangement of the pumps (individually or
combinedly).
One way is to change the pump curve. This can be achieved by:
Parallel operation of more pumps (more discharge );
Serial operation of more pumps (higher. head).
Centrifugal pumps will only operate satisfactorily if there is no build-up of vapour within the
pump.
The required net positive suction head (NPSHr) is the amount of energy required to prevent the
formation of vapour-filled cavities of fluid within the eye of impeller. The formation and
subsequent collapse of these vapour-filled cavities is called cavitation and is destructive to the
impeller. The NPSHr to prevent cavitation is a function of pump design and is usually
determined experimentally for each pump. The head within the eye of the impeller, also called
net positive suction head available (NPSHa), should exceed the NPSHr to avoid cavitation.
Cavitation on the impeller blades should always be avoided. This phenomena is caused by
carried air or water vapour being released from the water. The developed bubbles (of a very
small size) move inside the pump and collapse when entering a higher pressure zone. The
continuous collapsing of bubbles on the tip of an impeller blade causes the metal to be eroded.
The lifting of water by suction should be avoided as far as possible. The pump parameter
N.P.S.H. (Net Positive Suction Head) must be evaluated. The N.P.S.H. can be roughly defined
as the static head above vapour pressure.
Where
p0 = pressure at the water surface;
pv = vapour pressure for the fluid at the temperature T1 at 1;
∆z = difference in height (z1-z0) from the water surface to the location;
ρ = fluid density;
g = gravitational acceleration
Electric motors operate at their peak power factor and efficiency when fully loaded.
The power delivered to the pump shaft is known as brake horsepower (BHP)
The pump power input P of the pump is the mechanical energy at the pump coupling or pump
shaft absorbed from the drive. P can be calculated using the following formula:
P=
Where
P = power (kW),
= mass density of the fluid (kg/m3)
= gravitational constant (m/s2)
Q = pump capacity (m3/s),
H = pump head (m)
= pump efficiency
When determining the required power of the motor drive an overall efficiency must be used:
Never oversize a pump but select with the required duty point considering limited
margin;
Selected motor shall be capable of running the pump in any point on the pump curve.
Choose a motor with sufficient power reserve but not too oversized;
Respect the maximum number of starts per hour depending on motor power:
P < 4 kW 15 starts / hour
P from 5 to 11 kW 12 starts / hour
P from 15 to 30 kW 10 starts / hour
P > 30 kW 6 starts / hour
Prefer a motor running 1500 rpm rather than 3000 rpm to maximise longevity and
reliability;
Power on the motor plate is the nominal power delivered by this motor;
Minimize head loss at the suction side, prevent the possibility of air intake to avoid
cavitation;
Never control the pump from the suction side;
The discharge flow should be a straight as possible (avoid Tee and 900 elbow);
For the installation of pressure gauges and flow meters comply with manufacturers
recommendations.
A pump test is performed to measure various aspects of the pump's operation. The end result
of a pump test is an estimate of the overall efficiency of pump and to authenticate the
manufacturer design guarantee are attaining at rated parameters.
The pumps shall be designed, manufactured and tested in accordance with the last edition of
one of the following appropriate standards:
ISO
BS EN
DIN
API
Hydraulic Institute Standards (HIS)
The pumps and associated equipment shall be designed and suitable for the climatic conditions
in the Sultanate of Oman.
The pumps shall be of a type as indicated in the particular requirements of the specifications.
The pumps shall be designed for continuous duty at rated parameters and should be capable of
pumping the flow ranges specified in the specifications.
The pumps and associated equipment shall include all necessary provisions to prevent
contamination of the drinking water being pumped.
The Contractor/Manufacturer shall produce material test certificates for all components making
up the pump in accordance with ISO 10474 3.1B certificate.
PAEW reserve the right for shop inspection / stage inspection by their authorised
representatives. The Manufacturer / Contractor shall provide full assistance and co-operation
for such inspections. Transport conditions to safeguard all parts of the pump, motor including
the bearings and seals should be clearly defined.
The Contractor / Manufacturer shall make suitable provisions for detailed shop testing of the
pump and inform PAEW sufficiently in advance to enable their representatives to witness the
tests.
The pumps shall be tested in accordance with the ISO 9906 or relevant equivalent standard to
be approved by PAEW or their representative, at the Manufacturer premises to witness the
pump performance as per the designed guarantee points as detailed in the specifications
/contract.
The factory test for each variable speed pump shall include, but shall not be limited to the
below:
The above tests shall be conducted at minimum, maximum and average speed.
Motors
All motors shall be given a standard commercial test as defined by IEEE and the all tests shall
confirm the followings:
Temperature
Efficiency
Torque
No load, full voltage vibration level
Noise test
Power consumption
All listed tests shall be detailed and procedures shall be included for every test along with the
acceptable tolerances according to international standards.
All instruments used during shop tests at Manufacturer’s premises shall be duly calibrated by
recognised laboratories and the calibration certificates shall be inspected and certified by
PAEW’s representatives prior to starting the shop tests. The equipment for testing pump
performance corresponds to the most common pump test standards ISO, HIS and DIN.
The calibration certificates should not be more than six months old. (required to be calibrated
periodically).
After installation and before commissioning, the Contractor shall be carry out site test to be
witnessed by PAEW, their representative (Consultant), contractor and manufacturer’s
representative.
The site tests for individual and parallel pump operation shall include but not be limited to the
following measured over the entire specified range:
Discharge characteristics
Head measurement
Water leakage measurements
Vibration measurements
Bearing temperature measurements
Noise measurements
Any problem or defect detected during these tests shall be promptly rectified by the
Contractor/Manufacturer at no additional cost.
The Contractor shall include in his bid, as a minimum, consumables and spare parts for
commissioning and spare parts for guarantee period operation. The Manufacturer/Contractor
shall guarantee the availability of spare parts for a minimum duration of 10 years.
The required capacity of pumping station and its location is determined from hydraulic network
analysis.
A pumping station should have at least shall have minimum but not limited to below:
Pump hall room ;
Overhead cranes / hoist / monorails
Control room (optional);
Electrical room;
Automation room;
Office (Optional);
Maintenance and workshop facilities (Optional);
Storage for spare parts and equipment (Optional);
Storage for chemical and substances (Optional);
Welfare facilities (including PPE changing area).
The architectural design should harmonize with the surrounding environment and respect the
natural landscape as far as reasonably practicable.
The foundations of structures depend on the results of geotechnical investigation. Usually, the
structure is of reinforced concrete, steel and masonry construction.
The building should be designed considering both the initial requirement and the potential need
for space to accommodate future equipment for expansion.
The impact of noise on houses or other buildings near the station must be considered.
Windows should not be included in unattended locations or chemical storage including chlorine
gas.
All equipment must be installed or built in such a way that flooding or other spillages cannot
jeopardise the operation or running of such equipment. All electrical panels must also meet
these requirements so as to prevent failure or electrocution.
Floors should slope to a sump fitted with a pump. The floor should be non-slippery to avoid
accidents.
In line with MD 286 the Design team must carry out an assessment of all potential Hazards
during construction and operation phases. This must include a risk assessment detailing the
future requirements for fire fighting, manual handling, electrics, lone working, confined spaces,
chemical control etc. PAEW HSE is to be consulted at all stages of the design.
A paved road access for maintenance vehicles should be provided. All equipment should have
horizontal and vertical clearances to allow for repairs and maintenance to be carried out
efficiently and safely. Pumps, motors and equipment should be installed after finishing civil
works.
If the pumping station has different floor levels, stairs and safety railings should be installed.
To avoid the need to climb over pumps, motors or pipes, stairway shall be provided to provide
access to all sides of pump and motor. Where required lifting equipment specific to fitting new
parts i.e. A frames or block and tackle must meet all HSE requirements
If temporary or portable hoisting is not practical, crane rails and electrical hoists should be
installed for maintenance or repair works. These should cover all heavy equipment and allow
for offloading of Trucks etc.
Hoists should be designed so that the equipment located inside can easily be taken outside for
heavy maintenance or replacement. Hoists must be marked and included in routine inspections
by the relevant competent authority at least annually for the hoist and every 6 months for hoist
equipment i.e. chains, straps, strop, hooks, shackles and D rings.
The protection of access to water facilities is important. Metal fences must be provided to
prevent trespassing, theft and from act of domestic and non-domestic aggression.
Pumping stations are normally completely enclosed by high fences. These could be of the
chain-link or iron railings type, depending on architectural requirements and risk level.
Alternatively a masonry wall could be constructed to meet architectural requirements.
The security fence is generally adjacent to the property line. Each site should have a boundary/
perimeter fence which should comply with regulations and PAEW’s security and HSE Policy.
Emergency equipment must be set on the risk of the hazards on the site. The following are
some mandatory emergency equipment:
Alarms;
Signage;
Lighting/Emergency lighting (powered through UPS);
Exits / Emergency exit ;
Fire extinguishers;
Confined spaces;
Welfare facilities.
Emergency alarms must meet the requirements governing the hazards and the risk. As a
minimum all sites including pumping station must have a fire alarm system capable of
evacuating the site safely in a minimum of time, be it electrical or mechanical.
Other alarms to consider in pump room and treatment works would be:
Pump alarm normally blue flashing;
Telephone alarm normally white flashing;
Chlorine alarm normally orange flashing;
Fire alarm normally red flashing.
All alarms are normally backed up with audible high pitched sound. Staff must be trained and
aware of what to do in the event of any alarm.
Interior and exterior lighting facilities must be provided where necessary and automatically
operate emergency lighting system must be installed as part of the normal lighting and must
last for a minimum of 30 minutes on automatic action during an emergency. It must also
illuminate the safe route to a final exit from any part of the building structure.
Where exterior lighting is requited it shall be equipped with an automatic presence detector
lasting not less than 5 minutes.
Emergency exists must be provided so that staff can evacuate the building during an
emergency by the fastest safe route and all final exits must have push/paddle bar release.
Where required, dependent on volume of staff these may need to be double doors.
All emergency exits, walkways, staircases, hall ways must have emergency signage dictating
the direction of travel to the emergency exits including pictograms on what actions to carry out
on route or at the exit i.e. push bar release.
Other signage required on the site should follow best international practice and the following
categories must be observed:
Mandatory;
Prohibition;
Emergency and warning;
Danger;
Information.
All signage will be worked out on the hazard identified risk assessment and may change with
further building design or alteration. For example see followings chart.
Fire fighting equipment can only be decided on the recommendations from a fire risk
assessment in line with the completed design from the designer and further improved during
the course of construction. Only with this information and in line with Oman HSE regulations
and guidance by external authorities i.e. ROP, municipality can the right equipment per location
be decided upon. This may include but not be limited to fire extinguishers, suppression
systems, fire blankets etc.
In a pumping station confined spaces are normally found where chemicals are stored or dosing
i.e. chlorine or in an area with limited access and egress, or where there is a risk from flooding,
free flowing solids or the design of the building or structure dictates.
Mandatory equipment requirements should be used in these areas and the following list should
be included but is not exhaustive:
Gas monitors;
Tripod and Winch;
Harness;
Breathing apparatus;
PPE.
This would be decided on a thorough and comprehensive confined space risk assessment.
Welfare facilities must be included in all pumping stations for the benefit of staff and operational
requirements. They should include the following as a minimum but this may change on the use
of the site or risks that develop:
Toilets and washing facilities;
Changing areas;
Pantry/Canteen facilities (depending on size of site);
First aid facilities including a minimum of a 10 man first aid kit with 2 eye wash bottles;
On all sites where chemicals or substances are to be used a safety shower (s) must be
fitted (see requirements in Other facilities).
Doors giving access to the facilities and equipment must be equipped with anti-intrusion system
providing access only through use of a code or badge. The doors must opened in an outward
direction.
A chain must be installed across access ladders as a means of preventing further entry and as
a visible sign unless authorised not to go beyond. In this instance, the chain must be replaced
after the entry and exit.
Sump covers should be installed and be of the gridded type each grid not exceeding 30 x 30
mm.
The sump shall be equipped with float level controllers '' Pear shape type '' and a drainage
pump that initiates automatically when the sump is full.
For the security of the pumping station an independent flood alarm system shall also be
installed. This system shall consist of a level controller '' Pear shape type '' positioned 20 cm
above the floor which will inform the Control room.
A telephone booth shall be provided inside the building adjacent to the pump room with a vision
panel in to the pump room. A flashing white light shall be installed to indicate the phone is
ringing in the pump room. The operator must go into the telephone booth to operate the phone.
6.7 Ventilation
Ventilation will be provided to protect against over heating equipment, and will be either air
conditioning, heat extraction or a mixture of both and shall be designed for internal (motor,
lighting etc...) and external loads (structure, climatic conditions). A specific ventilation study is
required for each installation.
7. HYDRAULIC EQUIPMENT
Manometer
Pressure
sonde
Anti-ram
PI Sondes
temperature & Meter
Suction vibration Discharge
WM
Sonde
temperature &
vibration
7.2 Pipes
The type of pipe depends on the fluid being transported and the environment in which it is
installed. Usually, suction and discharge pipes are made of steel (cast or carbon steel).
7.3 Valves
Isolation valves are installed on suction and discharge pipes, and, by-pass pipelines.
The discharge valve(s) should be modulating type and motorized.
Pump controls must have an emergency shutdown power check feature for surge
protection when power fails.
Air release, air vacuum release or combination of air release and vacuum valves are to
be provided at critical locations in the pumping station piping.
Unless otherwise required, the discharge side of all pumps is to be provided with flow control
valves as well as check valves
Drain valves should be also installed on the suction and discharge pipes of each pump.
Tapping points for pressure monitoring should be installed at the suction and delivery sides of
each pump as well as on the common header of suction and discharge.
In order to measure the flow at outlet of pumping station, an electromagnetic or ultrasonic flow
meter shall be installed at the discharge line
7.5 Disinfection
Water quality studies are necessary to choose the type of disinfection, its installation, control,
storage, handling and transport requirements.
For the disinfection see TET/DG/5007 design guidelines for Disinfection and Secondary
Chlorination.
All electrical panels, switchgear and electrical control equipment should be located in the
electrical room. Good visibility of panels is necessary as is proper warning and danger signage
on the equipment. The electrical panels should have at least 30% extra capacity for extension.
Every electrical panel shall be equipped with command buttons with three positions (Manual,
Automatic and stop).
The main parameters (power, power factor, power totalizer, voltage, current, temperature, hour
running meter etc.) should be displayed.
The electrical equipment room shall be separated from pump room. It could be either in a
separate building or physically separated from the pump room by a structurally sound dividing
wall with a viewing pane. Normally the second internal door to the room should have no
windows. This room should be air conditioned.
The general electric supply must be dual and able to take a permanent or temporary stand by
generator. Switch over arrangements, automatic or manual, need to be decided.
The medium/high voltage electrical cells should be equipped with an automatic restart system.
The power supplied to the Pumping station should have the capacity to run all the pumps
including stand-by pump if needed.
Pumping stations should be equipped with an emergency un-interrupted power supply with
sufficient capacity to provide electric output in case of main power failure.
After checking the fire protection regulations authority, the following fire detection/suppression
systems should be installed: Heat/ smoke detection in all rooms. Suitable Fire extinguishing /
suppression appropriate to the installed equipment and size of the site. For example CO2 for all
electrical equipment, dry powder for generators and foam for fires on liquid fuels and oils. This
will be established by a risk assessment of the blue print by HSE Department PAEW. Alarm
should be both, audible on site and relay back to the operations centre.
Safety showers must be available in all areas where there is a high concentration of chemicals
or substances with the potential to harm. This could be one or more on larger sites. The shower
must be constructed of steel and rise from the floor at least 2.5 metres with a shower arm at
right angle to the main body “length of 0.5 metres” and a shower head 20 cm wide. It must
have a pull handle activation that will release abundant amounts of water from a free flowing
main or tank that is at normal body temperature between 16 and 26 ° C. The water must run for
a minimum of 30 minutes. Around the base of the shower must be an interceptor that can take
the residue chemical or substance away to safe storage (Remember that this storage must be
emptied after emergency use). The shower must be green with white striping and must be
signed above and from any substance source it must be a maximum of 10 meters from any
substance.
Attached to the safety shower fitted to the main stem at about 1.2 metres should be an eye
wash which is activated on opening allowing the injured person to places eyes in the flow of
water which must be controlled a reasonable speed so as not to cause further damage. This
should also empty to the interceptor.
8. SCADA
The Supervisory Control and Data Acquisition (SCADA) and Programmable Logic Controller
(PLC) shall supervise, monitor and control the pumping station. For more detailed information
of control and automation refer latest version of TET/DG/5009.
All the data shall be collected from the different units and transferred to the Regional Control
Room.
The following represents the basic minimum which should be monitored in the SCADA system.
Electrical actuated valves: Open, intermediate, Closed, % opening;
Pump: Start, Stop, running, trip;
Pressure alarm: low , high, normal;
Pump Temperature control;
Pump discharge control;
Pump operation mode (automatic/manual)
Vibration sensors;
Pressure control;
Level: Low , high, normal;
Water quality parameters;
Energy consumption for each pump;
Number of hours in operation (for maintenance );
Flood alarm;
Doors access control;
Situation of electrical power;
Historic.
PIPELINES
Electronic Document, only the original archived in Quality Department is signed / Printed copies uncontrolled
Revision Date Details
- Page 8 : 1.9: last point corrected ‘’risk of water hammer
1.3 26/03/14 (surge’’ removed and integrated by-pass allowed also.
- Page 40: 4.2.1: last point corrected ‘’risk of water hammer
(surge’’ removed and integrated by-pass allowed also.
Contents
1. GENERAL.................................................................................................................................................. 3
1.1 Sizing .................................................................................................................................................... 3
1.2 Location of pipe and equipment ............................................................................................................ 3
1.3 PAEW pipeline and OBC duct .............................................................................................................. 4
1.4 Identification ......................................................................................................................................... 5
1.4.1 Warning tape ......................................................................................................................................... 5
1.4.2 Marking ................................................................................................................................................. 5
1.5 Pipe laying Techniques ......................................................................................................................... 5
1.6 Accessibility .......................................................................................................................................... 6
1.7 Materials ............................................................................................................................................... 6
1.8 Pipeline connection ............................................................................................................................... 7
1.8.1 Self anchored joints ............................................................................................................................... 7
1.8.2 Anchor (Thrust) blocks ......................................................................................................................... 7
1.9 Joints ..................................................................................................................................................... 8
1.9.1 HDPE pipes ........................................................................................................................................... 8
1.10 Valves ................................................................................................................................................... 8
1.10.1 Isolating valve ................................................................................................................................... 9
1.10.2 Manual Valve.................................................................................................................................... 9
1.10.3 Motorised Valve ............................................................................................................................... 9
1.10.4 Equipment for operating valves ........................................................................................................ 9
1.10.5 Non-return valves .......................................................................................................................... 10
1.10.6 Air valves ........................................................................................................................................ 10
1.10.7 Washout valves ............................................................................................................................... 10
1.10.8 Pressure regulating valves .............................................................................................................. 10
1.10.9 Metering .......................................................................................................................................... 12
1.10.10 Fire hydrants ................................................................................................................................... 13
1.11 Network protection.............................................................................................................................. 13
1.11.1 Protection against corrosion for pipes ............................................................................................. 13
1.11.2 Cathodic protection for steel pipes ................................................................................................. 13
2. HYDRAULIC CALCULATION ............................................................................................................. 14
2.1 Basic equations ................................................................................................................................... 14
2.2 Darcy – Weisbach equation................................................................................................................. 16
2.3 Empirical formula ............................................................................................................................... 18
2.3.1 Hazen – Williams formula .................................................................................................................. 18
2.3.2 Manning formula ................................................................................................................................. 19
2.3.3 Head losses through fittings and valves .............................................................................................. 19
2.4 Hydraulic thrust ................................................................................................................................... 20
2.5 Self Anchoring Joints .......................................................................................................................... 21
2.5.1 Calculation of anchoring lengths ......................................................................................................... 21
2.6 Anchor (Thrust) blocks ....................................................................................................................... 23
1/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
2.6.1 Anchor (Thrust) block calculation ...................................................................................................... 23
2.7 Anchor (Thrust) Block Standards ....................................................................................................... 24
2.8 Water hammer (surge)......................................................................................................................... 24
2.8.1 Water hammer (surge) protection ....................................................................................................... 25
3. PIPE INSTALLATION ............................................................................................................................ 26
3.1 Excavation ........................................................................................................................................... 26
3.2 Trench width ....................................................................................................................................... 28
3.3 Trench depth ....................................................................................................................................... 29
3.4 Safety in excavations........................................................................................................................... 29
3.5 Trench Safety (Battering) .................................................................................................................... 29
3.6 Trench safety (Shoring) ....................................................................................................................... 30
3.7 Pipe bed ............................................................................................................................................... 30
3.8 Pipe laying........................................................................................................................................... 30
3.9 Nuts, bolts and washers ....................................................................................................................... 31
3.10 Gaskets and joint rings ........................................................................................................................ 32
3.11 Pipe storage ......................................................................................................................................... 32
3.12 Backfilling ........................................................................................................................................... 32
3.13 Road and wadi crossings ..................................................................................................................... 33
3.13.1 Road crossings ................................................................................................................................ 34
3.13.2 Crossing through existing ducts / culverts ...................................................................................... 34
3.13.3 Wadi crossings ................................................................................................................................ 35
3.14 Valve chambers and surface boxes ..................................................................................................... 35
3.15 Hydraulic testing ................................................................................................................................. 38
3.16 Disinfection and flushing .................................................................................................................... 39
4. DESIGN OF WATER TRANSMISSION PIPELINES ............................................................................ 39
4.1 Recommended materials ..................................................................................................................... 40
4.2 Valves on transmission systems .......................................................................................................... 40
4.2.1 Isolating valves ................................................................................................................................... 40
4.2.2 Air valves ............................................................................................................................................ 41
4.2.3 Washout valves ................................................................................................................................... 41
4.2.4 Pressure regulating valves ................................................................................................................... 41
5. DESIGN OF WATER DISTRIBUTION PIPELINES ............................................................................. 41
5.1 Pipe size .............................................................................................................................................. 44
5.2 Pressure ............................................................................................................................................... 44
5.3 Methods of supplying potable water ................................................................................................... 45
5.3.1 Metered House connections, ............................................................................................................... 45
5.3.2 Tanker distribution .............................................................................................................................. 46
5.3.3 TFS Location....................................................................................................................................... 46
5.3.3.1 Control Panel .................................................................................................................................. 47
5.3.3.2 Control Unit .................................................................................................................................... 48
5.3.3.3 Data Transmission .......................................................................................................................... 49
5.3.3.4 Water delivery point (bay) .............................................................................................................. 50
5.3.3.5 Data Report to Control Room ......................................................................................................... 51
5.4 Water meters ....................................................................................................................................... 52
5.5 Leakage and wastage control .............................................................................................................. 53
5.6 Recommended materials ..................................................................................................................... 54
6. SCADA..................................................................................................................................................... 55
2/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
1. GENERAL
1.1 Sizing
The design of a pipeline is to be validated systematically by a hydraulic study. The design will
be done taking into account:
Design criteria;
Pipeline material;
Meteorological conditions;
Location (geographical) / Purpose (transmission or distribution);
Soil conditions;
Operating conditions.
Appropriate consideration must be given to the pressure ratings of pipe materials however all
hydraulic calculations carried out during design shall be based upon nominal diameters.
The location of the pipeline and associated equipment must ensure that:
They are adequately protected (against outside attacks such as traffic, ground
contamination by chemical spillage, physical impact, weather conditions);
The pipe will not be exposed to ultra violet light during transport and storage where this
would impair its integrity and projected operating life;
Away from all existing and proposed utility infrastructures specially wastewater;
accessibility for the safe operation and maintenance of equipment;
accessibility for later maintenance and extension works without adverse impact on other
networks belonging to PAEW or others;
minimum impact on the operation and integrity of the existing network during
construction work;
In case of future mains failure the risk of flooding and third party damage is minimized.
Based on the direction of flow, pipeline profiles with gradual ascents and rapid descents
facilitate air collection at high spots, whilst preventing any air entrainment and the ready
evacuation of the pipe for maintenance. And also high points after pumps.
Washouts provide for the discharge of water from a pipeline to facilitate emergency repair /
maintenance works, periodical drain to clear deposits and stagnation.
These appurtenances must be sized to allow for the rapid evacuation of air / water. Air valves
are meant for both letting air in and out at the time of refilling and emptying.
Consequently the following precautions should be taken:
3/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Provide the main with a gradient to facilitate upward movement of the air (install with a
minimum gradient of 2 to 3 mm/m);
Avoid excessive gradient changes caused by following ground contours wherever
possible, particularly for large diameter pipes;
If the profile is flat, create as many artificial high and low spots as possible, to give
gradients of:
2 to 3 mm/m in ascending sections;
4 to 6 mm/m in descending sections.
Extreme care must be taken to ensure that air valve chambers are not flooded as this will
permit contaminated groundwater to enter a pipeline.
Pipes should be installed along a pre-arranged route. The preferred location for distribution
mains in urban areas is under the footpath. Transmission mains must be carefully sited to avoid
risk of damage to third party property in the event of pipe burst. If possible pipes should not be
installed under storm drains, sewers, major roads, vegetation or parking areas and minimum
5m away from the compound premises.
Sometimes mains will cross but in no case should they be installed in a way that makes future
intervention impossible.
The depth of pipeline should be chosen in such way that the slope of the pipeline is as constant
as possible. Unless it is unavoidable the cover over the crown on a pipe is to be as equal as or
greater than 1.0 m. A deeper profile is justified if the environment requires it so as to avoid
distortion of the pipe due to external stresses or the operating conditions is such that it may
cause the pipe to be lifted upwards if there is insufficient weight on it. And to provide the
required gradients referred to above.
Normally DI pipe is able to withstand normal ground pressures. If a HDPE pipe is being laid, the
design of the bedding and backfill is an essential element of the pipe design.
The OBC (Oman Broadband Company) is determined to provide broadband services all across
Oman. In order to expedite the implementation of duct and reduce the project managerial
process, OBC joined hands with PAEW. For OBC 110mm dia uPVC pipeline shall be laid
4/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
along with PAEW pipeline in the same trench (including transmission and distribution).
However, the requirements of OBC and its detail layout/requirements should be discussed with
PAEW/OBC during the commencement of each project.
1.4 Identification
Be immediately recognizable;
Be visible before excavation reach an area where there is a direct threat of exposing
the pipeline;
Be installed throughout the length of pipeline;
Be detectable by pipe locating equipment;
Have some identification / warning markings on it.
The warning grid should be detectable by a metal detector or pipe locating equipment.
1.4.2 Marking
Marking and numbering of valves and hydrants should be done in an acceptable level. The
marking should indicate all necessary information (such as distance and direction) to ensure
traceability.
This will help to identify ,hydrants and valves, during any subsequent maintenance intervention
and to assist the emergency services.
Pipe diameter;
Soil types ( mountain, gravel plain, tidal etc...);
Obstacles (highway, wadis etc...);
The length of underground structure requiring access;
Traffic constraints and traffic loads;
Proximity of other utility networks;
5/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Operating constraints of the network;
Cost.
Standard Open Cut Trenching : because of its simplicity and low cost this technique is
the most common;
Narrow trenching: A variation of the open cut technique but using specially designed
excavators to minimise the surface area disturbed;
Trenchless technologies such as micro-tunnelling, horizontal direct drilling, thrust boring
etc... and is especially useful in urban areas;
1.6 Accessibility
Every pipe and its associated valves, hydrants etc. should be accessible for maintenance. In
these latter circumstances consideration must be given and documented to the ability to
provide alternative supplies of water in the event of pipe failure. During the planning and design
stages of a project operations staff must be consulted to obtain local knowledge with respect to
this issue.
For large diameter pipes ( DN ≥ 1200mm) accessibility not only includes access to the outside
of pipeline but also the inside.
Pipes of diameter ≥ 1200 mm must be fitted with blanked off branch tees so that access to the
inside of the pipe is possible for a man and / or an automated machine carrying a camera
without the need to cut the pipe wall.
1.7 Materials
The pipe materials widely used in Oman are Ductile Iron and Mild Steel for transmission
pipelines, Ductile Iron and HDPE for distribution networks. In the past other materials such as
PVC, Asbestos Cement, Galvanised iron and MDPE were used but these are no longer in use.
6/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Each type of main has a pressure class also known as a pressure rating (normally measured in
bar). This is a measure of the maximum operating pressure that a pipe can withstand without
failing.
Mains can normally survive transient pressures in excess of this for short periods of time.
These higher pressures are normally the result of pressure surge caused by sudden changes
of rate of flows on the network associated with pumps switching on and off or valves suddenly
opening and closing.
If operating pressures, pumping conditions etc. are likely to cause surges of pressure in excess
of the pipe rating then surge protection facilities should be considered.
The connection between pipe elements must make a water-tight joint and, if a flexible pipe,
allow for movement between the pipes :
It is an attractive option when there are restrictions, notably in urban areas, when it is difficult to
obtain sufficient quantities of concrete. It is also time saving when pipe laying and allows pipes
to be tested immediately after being laid as there is no need to wait for concrete to set.
The block is to be designed for submerged ground conditions, if appropriate. For large diameter
pipes, thrust blocks are structural elements and should be designed as a structure.
7/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
1.9 Joints
Joints should be flexible when the pipe elements are installed in unstable soil.
1.10 Valves
Isolating valves (gate valves, butterfly valves) allow for the operation of the network, its
protection and its hydraulic isolation when necessary. Gate valves with flanged joints shall be
used on pipelines ≤ DN 400. For pipelines above DN 400 butterfly valves shall be used.
Valves should be installed so that, where possible, all parts of the network can be controlled
without adversely affecting another part. As a minimum requirement valves shall be installed:
Non-return valves;
Air release valves;
Pressure regulating valves;
Flow control valves;
Dismantling joints shall be used at each valve to facilitate the easy removal of a valve
from pipeline. This ensures consistency of equipment used on the network to facilitate
maintenance;
8/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Valves shall be operable from the surface using the means by which they were
designed to be operated and equipped with a protection tube / chamber and surface
box.
For DN > 400 the valve must have a smaller diameter by-pass valve. This allows ease
operating of the valve and the main to be filled with minimum risk after repair or
maintenance. Valves with integrated by-pass are also acceptable.
9/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
The valves could be also hand operated with manoeuvre wheel.
Air valves are located at high points of pipelines, and in long ascending stretches of moderate
slope at 500- 750 m intervals. Also where abrupt changes of slope exist an air valve is to be
installed.
1.10.7 Washout valves
Washout valves should be installed at all low points and at the termination point of dead-ends
to make water disposal easier and more convenient. (if flooding of the wash out / drain point is
possible mitigating action must be taken to ensure their ready availability for use).
10/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
11/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
1.10.9 Metering
Metering is essential if the performance of transmission and distribution of the networks are to
be calculated. The results of these calculations can then be used to prioritize where field
investigations need to be carried out based upon the performance level of the associated
networks.
Meters should be installed at the following locations in order that the performance of the
networks can be calculated.
Production sites;
Reservoir inlet and outlet;
Pumping station outlet;
Tanker Filling stations;
Bulk off takes;
District Metered Areas inlet.
12/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
1.10.10 Fire hydrants
Fire fighting demands should be taken into consideration in the design of water distribution
networks.
For each project, the location of a fire hydrant is determined in coordination with the Public
Authority for Civil Defence and Ambulance (PACDA).
After installation each fire hydrant shall be checked and approved by the competent authority
and certificate from PACDA to be obtained by the Contractor
Fire hydrant shall be on a pipe not less than 100 mm diameter. The operating pressure of the
nearby line should not go less than 1.5 bar when the fire hydrant is used at the rate of 60 m3/h.
Otherwise all pipes and other pipeline components susceptible to corrosion shall be provided
with adequate protection during manufacture. (For example coating or resin with PPE layers).
During installation great care must be taken to avoid damaging protective coatings.
If necessary a cathodic protection system shall be installed to protect and monitor the pipeline.
All work related to cathodic protection systems shall be designed and supervised by a
specialist. The work shall be based upon the guidelines for best practices as detailed in
International Standards.
13/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
2. HYDRAULIC CALCULATION
Where
P = pressure (N/m2 );
ρ = mass density of liquid (Kg/m3);
g = gravitational constant (m/s2);
z= height above datum line (m);
v= flow velocity (m/s).
In reality, however a certain energy loss due to friction, hf , will occur, and the equation now
becomes (see Figure 1):
14/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
p1 v12 p v2
Z1 2 2 Z 2 h f
g 2 g g 2 g
Where
z = the elevation head (the position energy above some given datum line in a gravitational
field),
The velocity of flow, v , is the average velocity. In a pipeline, which is not partially empty its
value equals , which is the discharge (m3/s) divided by the cross sectional area of the pipeline
bore (m2).
The modified equation of Bernoulli can be used for flow in pipelines which are not partially
empty. If the pipeline has a uniform diameter throughout the length considered, then v1 = v 2
and the kinetic energy term is constant.
If, furthermore, the pipeline has the same level at point 1 and at point 2 then:
p1 p 2
hf
g g
This means that the pressure lost in a straight pipe is equal to the energy lost through friction.
The total loss of head during transportation in a pipeline system is summation of the following
losses:
Friction losses ( h f );
Entrance losses (α 1);
Losses in bends and curves (α 2);
Losses resulting from diameter changes (α 3);
Losses in valves, elbows, union (α 4);
Exit losses (α 5).
H = ( f. + α1 + α2+ α3+ α4 + α5 ) .
15/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
2.2 Darcy – Weisbach equation
The Darcy – Weisbach equation is an expression for the head losses by friction when water
flows through a circular pipe. The expression is dimensionally correct as opposed to the
empirical formula which will be discussed in the paragraph 2.3. The latter type of formula has a
lesser accuracy.
f l v2
hf
2 g D
Where
The friction factor (f) is dependent on the type of pipe and flow, assessed by the Reynolds
number (Re), upon the roughness of the interior surface of the pipe or wall-roughness (k), and
upon the diameter of pipe (D).
One of the expressions for the determination of the friction factor is Colebrook expression:
Where
Re = Reynolds number
k = Wall roughness coefficient (mm),
The Reynolds number indicates the type of flow, which can be a laminar or smooth type of flow
(Re <2000 ), a turbulent flow (Re > 4000), or a transitional type of flow (Re = 2000 to 4000).
For circular pipes which are completely filled, the Reynolds number equals:
Where
Through the Kinematic viscosity the Reynolds number is dependent upon the temperature.
Figure 2 shows the friction factor being dependent upon the Reynolds number and the relative
wall-roughness.
16/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
The roughness coefficient of several pipe materials is shown in Table 1. When using a formula
the determination of the friction factor can only be done by iteration because of the Colebrook
expression being an implicit expression. As a first estimation of (f) a value of 0.025 is taken.
1.Smooth non-corroding piping with scaling unlikely, e.g. plastic, asbestos cement, centrifuged
cement: theoretical value for materials in new condition, k = 0.03 mm. In practice, k = 0.1 mm.
17/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
10 Ordinary concrete 1
11 Coarse concrete 5
A first estimation of the head loss by friction can be obtained using Table 2. In this table values
are given of the f/D ratio, being the friction factor divided by the pipe diameter. The values can
be substituted in the Darcy-Weisbach formula:
f l v2
hf
2 g D
Where
Several empirical expressions exists to determine the friction loss. This type of expression is
more convenient to handle, though less accurate.
hf = . ( )1.85
or
R0.63 . J 0.54
Where
= is the conversion factor for the unit system (k = 0.849 for SI units);
18/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
R = hydraulic radius;
C = roughness coefficient, which take in to account some increase in roughness as pipe ages
are as follows.
hf = . .
or
= . R2/3 . J ½
The Manning formula has the advantage that H is proportional to v2, the coefficient (n) being
constant for a given type of pipe.
Since the friction loss caused by fittings is usually expressed as α . v2. This formula is used for
lengths of pipelines involving many fittings.
The head losses due to the flow through bends, tees, entrances, sudden enlargements, sudden
contractions, valves etc are generally expressed as:
hf =α.
The factor is dependent on the Reynolds number and in case of turbulent flow also on the
roughness of the material. For smooth surfaces and a turbulent flow some theoretical values of
the friction factor are given in this table.
19/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
FRICTION LOSS FACTOR α
Theoretical value
1 Entrances / exits of α
Standard bellmouth pipe 0.050
Pipe protuding, Broad entrance 1.000
Ordinary entrance 0.500
Gradual exit 0.15 - 0.75
2 Bends
H = 0.051 (v1- v2 )2
D2/D1
4/3 0.20 (v1)
1.5 0.35 (v1)
2 0.60 (v1)
5 1.00 (v1)
5 Sudden contraction
D2/D1
2/3 0.30 (v1)
0.5 0.35 (v1)
0.2 0.50 (v1)
6 Valves
Gate valve fully open 0.17 - 0.25
Butterfly valve open 0.200
Swing check valve 0.80 - 2.5
Nozzle type check valve 0.16 - 0.23
Hydraulic thrust forces occur at changes in direction, reductions in diameter (bends, tees,
tapers) and at the end of pipelines carrying water under pressure. Thrust pressures can be high
and, to prevent failure of the pipeline, must be counterbalanced by appropriately anchored
jointing systems, or by anchor blocks.
F = K.P.A.
20/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Where
F : thrust force (N);
P: maximum internal pressure (site test pressure) (Pa);
A: cross section (internal for flanged joints, external for all other types) (m2);
K: coefficient which is a function of the shape and dimensions of the pipeline component
concerned.
The utilisation of self-anchoring systems is growing all over the world. These solutions are
taking the place of concrete anchor (thrust) blocks.
The technique is based on the principle of anchoring joints over a sufficient length on both sides
of a region of hydraulic thrust, such as a bend, in order to harness soil/pipe friction forces to
counteract the thrust force.
The calculation of the length to be anchored does not depend on the anchoring system used. It
depends on the test pressure, the pipe diameter and the parameters shown in the two figures,
C & D.
21/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Situations requiring anchoring of pipelines
L= x x ) xc
Where
L : anchoring length (in m);
P : on-site test pressure (in Pa);
S : cross section (in m2);
n : bend angle (in radians)
c : safety coefficient (generally 1.5);
Fn = K. (2.We + Wp + Ww)
We = .HD 1
22/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
α1 = 2/3, for test with uncovered joints;
D : pipe outside diameter (in m);
H : covering height (in m).
Various types of concrete anchor blocks can be designed, depending on the configuration of
main, strength and type of soil, presence, or absence, of significant amounts of ground water.
The anchor blocks must be designed to withstand the thrust force, either by bearing on side of
the trench if the soil is sufficiently resistant or by their own weight.
Thrust T = 2 pS .sin
Where
U= .M
Where
= allowable horizontal soil pressure;
M = area of vertical contact surface of concrete block/soil.
23/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Friction concrete block / soil
V=βN
Where
For Bends:
T = 2 P .S .sin
Where
T=P.S
For Reducers:
T = P (S1 – S2)
The area of the thrust block (A) required to sustain the thrust force (T) is to be related to the
safe bearing capacity (ϕ) of the soil concerned.
When the pipeline lies in a horizontal plane the thrust force is sustained by the horizontal soil
pressure together with the friction between the concrete block and the soil.
Standards for anchors and thrust block are shown in the Standard Drawings.
If the flow rate of a liquid in a pipe is abruptly altered, there is a violent change in pressure. This
transient problem, known as water hammer or surge, generally occurs when ancillary
equipment is interrupted or operated (pumps, valves etc...). Waves of pressure surges and
pressure drops sweep through the main until an obstruction stops them. The pressure
generated is destructive and has to be released. If no protection systems are in place the surge
24/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
seeks out the weakest part of the pipeline and causes a catastrophic failure at that point. Water
hammer can occur equally well in gravity and pumping mains.
The velocity of the pressure wave can be determined from the formula:
0.5
c=
Where
Esteel = 2,1.1011 N/m2; EDuctile Iron = 1,05.10 11 N/m2; EPe = 1,2.10 8 N/m2; EPVC = 3,1.10 9 N/m2
These protective systems are installed to limit water hammer to an acceptable level. There is a
variety of systems and each must be adapted to suit a specific situation. They act by slowing
the change in fluid velocity or by limiting the pressure surge in relation to the pressure drop.
The user must determine the pressure surge and pressure drop envelope created by water
hammer and judge, according to the pipe profile, the type of protection to be installed:
The anti-water hammer bladders mostly frequently used. It has two functions:
25/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
In the event of a sudden pump shutdown, the pressure drop is offset by a flow rate provided by
draining the balloon.
When the direction of water flow reverses, the energy in the water mass is transformed into a
head loss by filling the bladder through a calibrated check valve.
Where surge vessels are used for surge protection, the pipeline pressures shall not fall below 5
m gauge at the pipe centreline level except at location closer than 20% of the total pipeline
length to a control such as a delivery reservoir or a surge feed tank where the pressures shall
not fall below 2 metres gauge.
The surge tank volume can be determined from the graphs or from computer programs.
The best protection against surge is the careful operation of pumps and valves to avoid the
creation of pressure surges in the first place.
VFD are also used to control the surge at the time of stopping of pumps.
3. PIPE INSTALLATION
Any project should be subject to geotechnical study prior to its commencement. This study
allows for difficulties to be anticipated and technical proposals to be submitted to counter them.
Pipeline route approval shall be obtained from the concerned authorities and land owners and
those who rent.
A survey shall be undertaken to show the locations, dimensions and level of all services and
obstructions in the pipeline route.
A resistivity survey (every 500 m) shall be undertaken along the pipeline route and at all wadi
crossings.
Representative soil surveys shall be carried out along the pipe route to identify contamination
that may cause undue deterioration to the pipeline or contamination of the water it transports.
3.1 Excavation
All required authorizations from local authorities or other utilities should be obtained before
starting excavation work. Based on information gathered from local authorities / utilities
exploration and excavations should be made to determine the precise location and scale of
obstructions and other utilities.
However before any excavation can be carried out the ground must be checked for the
possibility of other utilities, third party intrusions or other risks, soft ground, shingle, proximity of
structures etc., this is normally undertaken at the planning stage where necessary utility plans
and drawings must be obtained if this is impossible due to restrictions or lack of records the
following should be carried out.
26/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Visual Inspection of the Area to ensure that there are no drains, manholes, telegraph or
overhead cable poles, ditches, trees or other obstacles that can cause problems during
excavation. Move up to 100 meters away in a circular motion where practicable when
checking;
Cable location devices (cat and gen) should be used and any findings must be drawn
on the ground prior to excavation;
Trial Holes should be dug on the line of excavation by hand at intervals of 5 meters or
less if traversing major roads, junctions, paths etc;
Only when this is carried out should the ground be deemed safe to dig. Where obstacle
is found digging should be by hand only.
Bulk excavation is usually carried out by a machine. When this is not possible then hand
excavation must be used. PAEW’s Consultant shall decide whether and where hand
excavation is required in line with international guidelines set out in chapter 8 (NRSWA new
road and street works). Where utilities or other buried services are known then hand digging
should occur within the last 500 mm of the buried service ensuring that the service is dug
around and supported by straps or strops every 2 meters in an open excavation.
All required authorizations from local authorities or other utilities should be obtained before
starting the work. Based on information gathered from local authorities / utilities exploration and
excavations should be made to determine the precise location and scale of obstructions and
other utilities.
All the necessary precautions shall be taken not to disturb archaeological remains and historical
sites in the vicinity of the works. If any important and historical things are discovered, the
PAEW`s Engineer and the department of Archeology and Antiquities of the Ministry of National
heritage and Culture shall be informed.
If the installation is under the road, and in order not to extensively damage the road surface, the
trench edges shall be pre cut using abrasive wheels. The width of this is to be sufficiently
greater than the trench width to avoid disturbance to the remaining road surface during
excavation.
Trenches shall be excavated to the required line and level as shown on the approved drawings.
The contractor shall deploy appropriate dewatering equipment to keep the excavations free
from water from whatever source, so that the works shall be constructed in dry conditions. Only
under exceptional circumstances will approval be given to proceed with water within an
excavation.
In exceptional circumstances, the use of explosives will be permitted. The contractor shall
obtain all necessary authorisations from the relevant authorities and make himself familiar with
all current regulations of the Royal Oman Police. The explosives shall be stored in an
appropriate and secure magazine. The contractor shall employ staff who are qualified and
experienced in the use of explosives and who have all relevant approvals in writing from the
applicable authorities, for handling explosives and blasting.
Where excavated material does not meet the requirements of Grade A or Type 1 to be re-used
in the excavation, the contractor shall be responsible for the disposal of surplus excavated
material in an environmentally acceptable manner to an off-site location. The contractor shall
present his proposals for such disposal to PAEW for approval before commencing excavation
works. No excavated material suitable for reuse in the works shall be removed from the site
except on the direction, or with the permission, in writing of the engineer.
27/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
In all cases where there is a risk of subsidence from trench walls or other ground problems the
use of trench support systems must be used.
In all cases trenches of over 1.30 meters deep and with a width equal to or less than two-thirds
of the depth must, when their walls are vertical or substantially vertical be adequately
supported.
Width in m
Depends
on soil
Trench support
system Compulsory
Depth in m
The trench width depends on the diameter of the pipe, the type of connection, the type of soil,
the laying depth and the methods of shoring and compaction.
In all cases the trench shall be excavated with sufficient width to ensure that efficient laying and
jointing of the pipes and associated pipeline components is possible. The clear width of the
trench throughout its depth shall be as per PAEW/TET/SD/5019. To reduce the cost of
excavation, and backfill, narrow trench techniques can be used.
28/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Pipes shall be installed at 1,0 m cover from the top of the pipe to the finished ground level. In
certain cases, with the written permission of the engineer, pipes can be raised or lowered to
cross obstructions. In the case of reduced cover depth the pipe shall be encased in concrete
as specified by the PAEW engineer.
Where trenches are required to be deeper than the general depth, the trench shall be
excavated to the required depth with a gradual slope to permit the proper laying of the main.
Additional excavations will have to be carried out to provide extra space around joints when
necessary and to suit local circumstances.
The minimum horizontal distance between a water pipeline and other utilities shall be 0, 50 m
(except sewer). For more details see standard drawing Typical Pipe Laying TET/SD/5019.
At all times the safety of those working in trenches is paramount. Appropriate protection against
trench collapse must be used in cases prescribed in existing regulations, or, in general, when
demanded by the nature of the soil.
This method is most often used in soils prone to slippage and consists of giving the trench walls
an outward slope which must be close to the internal friction angle (angle of repose) of the soil.
This angle varies with the type of soil and will need to be determined on site through trials
before allowing staff to enter the trench. This solution is rarely used in urban areas because of
the space needed.
Battering of trench sides is an accepted method of protecting workers against the risk of trench
collapse. No excavation with battered sides shall be made in roads, footpaths, private gardens,
or within safe distance nearby buildings or structures.
29/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
3.6 Trench safety (Shoring)
There are numerous shoring techniques. It is important to study and adopt the best system for
the location before starting the work.
Whichever technique is used, the earth pressure has to be taken into consideration. The
shoring must be capable of resisting the full thrust of the ground over its full height.
For the installation of shoring permanent overload, vibrations from vehicles, excavation
machines and work equipment movements should be considered. The shoring must be
modified to suit the nature of soil. Sufficient drainage must be provided in case of infiltration and
runoff.
The Trench Support must be inspected prior, during and after use to ensure integrity.
If the material in the trench bottom is considered unsuitable as a bedding material, it shall be
removed and replaced to a depth of at least 0.15 m beneath the bottom of the pipe. A material
such as pea gravel shall be used for pipe bedding. Exceptionally sand may be used subject to
this being evenly spread across the bottom of the trench to provide full support along the full
length of the pipe. Depressions shall be formed at each joint to prevent these creating stresses
in the pipeline. Bedding materials must not be sourced from any location where they may have
been subject to salt water infiltration or contamination with chemicals or any other substance.
In all cases care must be taken to ensure that the external wall of the pipe is not in contact with
hard items such as rock, buried masonry, etc.
All the pipes should be laid according to International Standards and manufacturer’s
recommendations.
The trench bottom must be levelled to comply with the approved drawings. Ensuring that the
pipe rests on the uniformly distributed pipe bedding material as described above. The pipes
shall be laid accurately to the lines and levels shown on the drawings within a tolerance of ± 5
mm.
All the pipes shall be laid and maintained to the approved alignments and grades ensuring that
the pipe is properly bedded along its whole length. Pipe alignments shall be straight between
bends or curves. Deviation from this principle shall only be allowed, following approval of thrust
restraining proposals, where shown on drawings, to comply with detailed specifications to the
contrary, or with the written agreement of the project engineer.
30/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Pipes must be handled, stored and clad in conditions that will not allow deterioration of the pipe
material to the extent that it may adversely impact on its future operational life. Pipes must be
lifted and maneuvered using devices that will not cause any damage to the pipe itself or to its
protective coating / cladding. Particular attention is to be paid to maintaining the original
geometry of the pipe sockets and spigots.
When the requirements of the installation make this necessary it is allowable to make cuts of
pipes. Every precaution must be taken that this is done using approved tools / equipment for
the pipe material in question and is only done when necessary.
Cuts are to be made using equipment approved for use on water networks that do not
contaminate the internal surfaces of the pipe and do not reduce the physical strength of the
pipe. Cuts of appropriate geometry shall be made that are formed to fit with the adjacent
assembly and are of the same quality as the original spigot of the pipe.
Before installation, the pipes are to be checked both internally and externally for damage to
pipe coatings and linings. The interior of the pipe shall be cleared of all debris that could have
been introduced and the ends of the pipe cleaned.
During installation pipes and other pipeline components shall be aligned as per the
recommendations of the manufacturers and in all cases within the limits detailed in best
practice manuals.
During excavation, pipe laying, backfilling and reinstatement temporary support shall be
provided to all other utility infrastructure in consultation with the relevant utility managers.
Where installation of the pipe to the defined grade or alignment is obstructed by existing
utilities, (such as conduits, ducts, pipes, etc) the owners / managers of these utilities shall be
consulted to determine the most effective way of resolving such obstructions. If the obstructing
utilities are to be supported, removed or realigned this will be done to the specification of the
owner / manager of the utility in question.
At the end of each working day, the ends of the pipes being laid are to be sealed using water
tight caps to prevent ingress of water and animals.
Wherever pipe coatings, internal and external are damaged these shall be repaired to the
specification of the manufacturer. If this is not possible the pipe / pipeline component is to be
discarded and disposed of in a manner that prevents it inadvertently being used elsewhere.
Where manufactures specify that deviation at pipe joints is permissible the deflection at each
joint shall not exceed the manufacturer’s recommendation.
Unless otherwise specified, nuts, bolts and washers shall conform to the requirements of
International Standards. All nuts, bolts and washers shall be galvanised. Where it is necessary
due to ground conditions or the requirements of the pipeline specification the bolts and washers
shall be of stainless steel.
Bolts shall be of sufficient length that a minimum of one thread shall show through the nut when
in the fully tightened condition.
31/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
All nuts and bolts that will be directly buried in the ground shall be adequately protected with an
approved protection system applied in compliance with the manufacturers recommendations.
Any such system must protect the nuts and bolts for a period equivalent to the design life of the
pipe.
Until required for incorporation in a joint every joint ring, gasket etc., shall be stored in
accordance with the International standards and manufacturer’s recommendation. If there is
any contradiction in these the Project Engineer shall determine which is to be followed.
Generally joint rings, gaskets, lubricants and jointing compounds shall be stored in a cool, dry
place that is protected from adverse weather conditions.
Only lubricants and jointing compounds recommended by the manufacturer shall be used in
connection with the joint ring and these lubricants shall be approved by the PAEW laboratory
manager as suitable for use on drinking water pipelines.
Gasket and joint rings should be manufactured from EPDM rubber conforming to International
Standards.
Flange gaskets shall be manufactured from EPDM rubber conforming to International
Standards and shall be a minimum of 3 mm thick.
Prior to use pipes and fittings (valves, hydrants etc.) shall be stored in a safe, neat and tidy
manner and in conformance with the manufacturer’s recommendations. The open ends of all
pipes and fittings shall be covered in such a way as to prevent the ingress of water, animals,
insects and children.
3.12 Backfilling
When backfilling the trench the HAUC should be used for Guidance of the fill material and
required strengths of ground support, all materials must meet the requirements of Type A or 1
for the refill of the excavation.
As soon as practicable trench sections of installed pipes shall be partially backfilled to avoid
pipeline flotation whilst, where possible, leaving joints open. Completed sections of the pipe
shall be closed by blank flanges or cap ends that are restrained to resist test pressures.
1. Backfilling with pipe surround, leaving joints open for testing procedures where possible.
The pipe surround material shall be the same as that used for the pipe bed and shall
provide a minimum of 150mm protection to the at the sides and 300mm (after
compaction) above the pipe, the pipe surround shall be compacted in 150mm deep
layers to ensure uniform pipe support and protection;
2. Final backfilling of all sections still exposed after successful testing.
In cases such as where narrow trenching or trenchless installation techniques are used that
preclude the provision of the pipe surround as stipulated above the contractor shall formulate
32/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
proposals for the equivalent protection of the pipeline. These proposals are subject to approval
by PAEW before being implemented.
Appropriate backfill material that complies with the requirements of the relevant street
managers shall be imported and compacted in layers not exceeding 150mm.
Road surfaces shall then be replaced using materials and methods that comply with the
requirements of the street managers / land owners.
Example of trench
All material shall be of a consistency that permits its adequate compaction around and under
the pipes and fittings and to support the trench surface without subsequent subsidence. (For
further guidance see Road and Wadi crossing section below).
If the pipe is to be laid in open ground the compaction of backfilling material may not be
required.
In summary the balance of the backfill to the final ground level shall only be carried out using
approved fill. Backfill material shall not be unsuitable / unwanted excavated material. This
should be disposed of away from the site as described earlier.
The minimum and maximum depth of backfill depends on the pipe characteristics, laying
conditions, bed zone and surround zone conditions, pipe stability and/ or protection. It`s
execution must meet variable demands depending on the:
The main backfill zone varies according to the area involved (rural, semi-urban or urban), and
should take road stability into account.
If this section contradicts the Backfilling section above in any way then the requirements of this
section shall prevail.
The disruption to road traffic should be minimal and before starting all permissions from
authorities must be obtained.
33/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
3.13.1 Road crossings
Wherever possible trenchless techniques are to be used for pipelines crossing under existing
roads. In exceptional cases, the excavation of existing roads is allowed and for these cases the
following requirements shall be followed.
The road shall be reinstated using the form of construction and materials as per Oman Highway
Design Manual issued by MoTC and the Regional Municipality.
Bedding and jointing shall be as specified, but the trench re-filling shall be carried out using
granular bedding material and compacted at the sides of the pipes to not less than 95% of the
maximum dry density as specified by the compaction test.
Above this 250 mm layer concrete Class 20/20 shall be placed to bring the level of the backfill
up to 100 mm below the finished road surface. This method of back filling shall be applied to an
extent of at least 2 m either side of the surfaced road carriageway.
Immediately after the backfilling of trenches, roads, pavements and verges are restored
temporarily using the materials of the pavement stockpiled during the excavation if these are
suitable for reuse.
The replacement of the road structure shall be carried out as soon as practicable after
backfilling has been completed. Suitable excavated road pavement which complies with the
MoTC / Regional Municipality shall be used at the sub-base levels. Compaction shall be carried
out with approved mechanical compacting equipment.
Any part of the structure of the road which has been damaged beyond the width of the trench
must be cut out and made good to the same specification.
A vertical joint shall be formed between the new work and the existing road surface and shall
be painted with hot bitumen or as required by Authority and the base course and wearing
course stepped 75 mm.
Where the carriageway surface adjoining the trench is of rolled asphalt the contractor shall lay
an interim wearing course of Class 20/20 concrete 100 mm thick. At a later date (to be decided
by the Engineer) the temporary wearing course may be removed and replaced with 2 layers of
50 mm of rolled asphalt.
The finished levels of the completed reinstatement shall conform to the adjoining carriageway
surface.
Reinstatement of wearing courses shall match as nearly as practicable the colour and/or other
characteristics of the existing surface after making appropriate allowance for the effects of
weathering on existing surfaces.
Protection around the pipe should be provided to prevent damage to couplings whilst being
pulled. Also, (or in conjunction with,) special supports shall be provided to fix the pipe into the
34/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
duct as well as prevent the pipe from resting on the pipe joints and creating undue stress in the
pipe barrel. Details of the proposed arrangement including the pipeline support method shall be
submitted to PAEW for approval.
After finishing the pipe sections in the duct and thorough inspection / approval of the work, both
ends of the duct shall be sealed by casting lean concrete. Pipe ends protruding from the duct
ends shall rest on thoroughly compacted soil.
A separate pressure test shall be carried out for the sections of pipe inside the duct to ensure
the integrity of the pipe and that correct installation has been achieved.
Valves shall be installed either side of major road crossings to permit the isolation of the
pipeline under the road.
Ductile Iron pipes and fittings shall be used over the length of wadi crossings plus 15 m
on either side. The use of mechanical or detachable joints are necessary;
Wadi protection is to be designed according to PAEW standard drawings TET/SD/5013;
Wadi protection shall de designed to prevent flotation of the pipeline in the event of
flooding while the pipe is empty;
Wadi crossings in soft soil will be constructed with a minimum cover of 2.00 metres;
Valves shall be installed either side of all Wadi crossings to permit the isolation of the
pipeline under the Wadi;
No valve chambers or marker posts shall be constructed in the wadi bed or on the
embankments of the Wadi;
All valves and marker posts must be visible and fully accessible when the Wadi is in
flood.
Valves shall be placed at the locations specified on the plans unless agreed in writing by the
project engineer in consultation with PAEW operations staff.
Buried valves shall be installed with an access tube and surface box. Only those valves
mentioned below shall be installed in a chamber:
35/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Valves on deep lines (> 2.50 m)where it is difficult to maintain access for operation
through surface box;
Valves located on unstable ground, embankments etc.;
PRVs.
For all Valves a metal surface box shall be installed that closely fits the tube / chamber and
restricts the ingress of dust, debris, insects and animals. Surface boxes shall be designed to be
height adjustable.
All surface boxes and chamber covers installed to provide access to valves shall be capable of
withstanding the anticipated traffic loading for the location.
Valves in chambers shall be installed using dismantling joints unless the design of the valve
allows replacement of internal parts without removing the valve from the pipeline. Dismantling
joints, if fitted, must be in the chamber.
GPS coordinates of each valve shall be shown on drawings and recorded in the GIS.
Surface box
36/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Operating cap
Operating Key
If the depth of the pipe is more than 1 m, telescopic operating unit could be used.
Operating unit
37/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Operating cap
Valve chambers shall be constructed with reinforced cement concrete or pre-casted RCC
components, and are based generally on the ground.
If man entry is required into valve chamber the chamber shall be of sufficient dimensions
depending upon the size of the valve/s, waterproof ,equipped with heavy duty D.I. cover and
frame, a aluminum ladder and a sump of 300 x 300 x 300mm dimensions.
Manhole covers shall be with Class D 400 in Ductile iron with round frame. The minimum
opening dimensions are 600 mm, 700 mm and 800 mm. The cover shall have lifting eyes, a
reliable locking system, sound proofing ring for stability and silence and optional anti-theft
system.
These tests are used to confirm the water tightness of pipes and fittings. A minimum of 48
hours notice must be provided to PAEW of the proposed date of a hydrostatic test. These tests
shall be carried out during normal working hours unless agreed in writing by PAEW.
After a new pipeline has been filled hydrostatic tests must be performed to ensure that the
pipeline is properly constructed before final acceptance. All hydrostatic tests must be witnessed
by PAEW.
Before any testing is commenced, pipelines to be tested shall be filled with water and left to
stand for at least 24 hours under a static pressure equivalent to the intended working pressure
in that section of the pipeline. After this, the line shall be subject to pressure and leakage tests.
38/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
2. Final test of the whole system on completion.
The test pressure is applied to the pipeline by means of a continuously operating pump,
equipped with a by-pass valve for regulating pressure. Attention must be given that the pipeline
is filled at a rate which will not cause any surges, and which will ensure a proper air release.
The section being tested is gradually filled with water from the lowest point to aid the release of
air.
All air must be released through hydrants and air valves installed for that purpose. Physical
inspection of wash outs and air valves must be made during pipe filling to confirm that all
entrained air is released.
After checking for visible leaks the full test pressure must be maintained for four continuous
hours. The recommended test pressure is Working pressure x 1.5 subject to a minimum of
10bar at the highest point of the pipeline.
The test shall be recorded using electronic pressure data loggers capable of operating within
the test pressure range.
The contractor shall design and document the testing procedure for approval by the Engineer at
least 7 working days before the proposed date for pressure testing. All the material for testing
shall be supplied by the contractor and submitted to the Engineer for approval.
Before takeover of a distribution network, hydraulic testing should be carried out either:
If the working pressure is less than 6 bar, the testing pressure should be 10 bar,
If the working pressure is more than 7 bars, the testing pressure should be working
pressure x 1.5.
After the hydraulic test and swabbing is completed and approved the pipes shall be disinfected,
flushed and sampled.
Any component used in the water system shall be fully disinfected and have the hygiene
clearance from PAEW.
Systems shall be admitted into service only once sampling results confirmed correct
disinfection. Procedure shall be repeated if sampling results show contamination.
The primary function of transmission pipelines is to transport large volumes of water between
sources and distribution systems possibly over significant distances. They normally have few
connections made from them.
Water transmission pipelines transport water from the source (water treatment plant, storage
reservoir) to the service / storage reservoir. Their operational functionality dictates that each
transmission pipeline is individually designed to meet the requirements of the storage systems
associated with it in balancing it.
39/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
The flow of water in transmission systems is normally more constant than that in distribution
systems in that they are used to fill reservoirs and when the reservoir is full the pumps that drive
the water through the transmission system are shut down. The effect is that the water is either
flowing through the transmission pipe at a consistent rate and pressure or there is no flow at all.
The design should be done taking into account pipe material, laying, maintenance costs and
energy costs (pumping).
For optimal size of pipe the parameters of length, static pump head and quantity of water being
transferred should be considered. Changes in elevation along the length of the transmission
main are critical in its design.
In a pipeline the velocity should be between 0.5 and 2 m/s (reaching a maximum of 2.5 m/s for
short sections of main in exceptional circumstances) with friction losses not be more than 0.5
bar over 1000 meters.
As mentioned in the basic design criteria, the choice of material depends on different factors.
The final choice of material is made during the engineering design process.
For DN ≥ 400 the valve must have a smaller diameter by-pass valve. This allows ease
operating of the valve and the main to be filled with minimum risk after repair or
maintenance. Valves with integrated by-pass are also acceptable. Bypass valves have
the following sizes:
40/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
4.2.2 Air valves
See section 1.10.6 above.
The distribution mains distribute water from storage reservoirs to the service lines for onward
distribution to consumer.
Pipe size,
Reservoir location,
Minimum and maximum pressure required,
Pressure variations.
A proper design involves minimizing investment and operating costs by optimizing these
factors. Due consideration should also be given to possible staged development of the network
to manage expenditure profiles.
Ideally the reservoir should be located on strategical point to equalize distribution flows and
pressures.
The flow of water in distribution systems can vary greatly from the peak hours, when a lot of
water is used for washing or drinking, to the minimum consumption hours, which are normally
at night.
Service reservoirs play an important role in the relationship between transmission and
distribution systems to balance the fluctuations of the water demand from customers that a
treatment plant may not be able to meet.
Reservoirs should be placed at a higher elevation than the distribution area, but as close as
possible to it to avoid unnecessary pumping and transmission line cost. If the area is flat
elevated tanks have to be used. Elevated tanks are generally smaller than ground reservoirs
and serve to balance demand variations in localized areas.
The pressure needed for the distribution system can be obtained using the following systems:
41/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
STATIC WATER
PRESSURE
Pumped system: these have a low level ground reservoir and the required pressure is
generated by pumps. Water only enters the storage vessel when the pressure in the
network increases above the height of the tank. When demand for water increases
water flows from the tank to supplement the volume supplied by the pump.
42/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Two main types of distribution networks are:
1. Branched distribution
Branched networks are predominantly used for small capacity water supplies delivering water
mostly through standpipes. Their drawbacks are lower reliability, (a single failure can cause an
interruption of supply to all customers), increased danger of contamination, possibility of
sediment accumulation in dead ends, larger pipes are often required than in looped systems to
overcome friction losses. Furthermore a fluctuation of water demand can cause large pressure
variations in the systems. Their advantages are that they are cheaper and easier to design and
install and flow direction and rates can be easily determined for all pipes.
2. Looped distribution
43/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Looped distribution networks allow for the supply of customers from more than one direction
making them less prone to overall failure of the supply. They have the advantage of better
hydraulic performance which leads to smaller pipe sizes and the reduced possibility of water
supply interruption during maintenance activities.
To determine the pipe size the Hardy Cross Method with empirical equations are used. For
quick and precise calculations software programmes are available.
Where
When designing a pipe system it should be ensured that there is sufficient pressure at the point
of supply to provide an adequate flow to all customers. If available, network models of the
system should be used to check that all pipes will be operating to the required standard.
To maintain water quality it is important to minimize transit times and avoid stagnation and low
flow rates. Therefore:
the system should not have excessive capacity unless this is required to meet a known
increase in future demand;
ideally low-flow dead-ends and loops should be avoided. Situations that may give rise to
negative pressures should always be avoided as in the event of a pipe failure
contaminated water can be sucked into the pipe.
The recommended diameters for distribution system are from DN 100 to DN 400 unless
otherwise specified.
5.2 Pressure
In a distribution system water should be supplied at adequate pressure and flow. However,
pressure is lost by the action of friction at the pipe wall and in pipe line components such as
valves. The amount of pressure loss is also dependant on the water demand from customers,
pipe material, length, gradient and diameter.
To deliver sufficient quantities of water the pressure head in the network should be at least 1.5
bar (15 m.w.c., worst point peak day, peak hour) in all parts of the network, including the
remotest and highest points. The maximum pressure should not exceed 6.0 bar (60 m.w.c.).
44/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
In high rise buildings a booster pump, supplied from a ground tank / reservoir, can be installed
by the consumer to ensure sufficient water pressure provided this pump is supplied from a
storage tank and not connected directly to the distribution main.
Pressure variations can be reduced by installing pipe of larger diameters although the cost of
doing this is higher.
There are 2 ways to deliver the potable water to the consumer in Oman:
The connection to the water distribution main is through a tapping saddle (electro-fusion
for HDPE pipes or mechanical for others) to a valve adjacent to a water meter generally
installed on the wall of each property. The material for house connections is HDPE
PE100 SDR 11 which has a pressure rating of 16 bars.
A water meter (see water meter section below) is installed together with a strainer on
the wall of each property. The meter should be installed at a sufficient height
(approximately 1.5m) to allow ease of reading and fitted with a ¼ turn lockable ball
valve installed before the strainer.
The approved meter is provided by PAEW.
Further information regarding the sizing of connections and meters are given in the
procedure TET/PRO/5000 and regarding a typical house connection in procedure
TET/MS/5001.
45/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Water is made available at tanker points from where it is distributed to the individual
customer using mobile tankers and pumped to the customers roof tanks.
Tanker Filling Station (TFS) is provided to supply potable water to remote dwelling
areas where water cannot be supplied through distribution network as laying of
distribution network is not feasible. Besides, TFS can be provided in addition to the
reticulated distribution network in order to distribute water during an emergency
situation like pipe burst or planned shutdown.
A tanker point shall have a sufficient filling capacity to fill at least 2 tankers at the same
time but as a minimum it should have a filling capacity of 40 m3 in 30 minutes. A two
bay tanker point serving 2 tankers at a time is usual. Multi bay tanker points are
installed in urban areas with high population density.
The following factors should be considered for the design of a tanker filling station:
Minimum filling capacity of 40 m3 in 30 minutes;
Minimum 2 bays serving each serving 1 tanker at a time;
During tanker filling, network pressure should not drop below 1.5 bar;
Number of bays shall be decided according to the requirement of the area;
Each filling station should have the capability to fill both small and big tankers;
A vending machine shall be installed on each bay to account for the water
taken;
For small regions individual tanker filling points shall have an individual storage
tank at a suitable height to comply with the above conditions;
If the flow is not sufficient to refill the tank quickly after emptying a booster pump
shall be installed to fill the storage tank within 1 hour.
Furthermore, each station is to be developed with adequate drainage, and paved entrance / ,
exit. Standing for tankers whilst filling or when parked shall be paved.
A flow meter shall be installed on the inlet of all tanker filling stations.
Valves are to be placed so that each filling bay is independent and can be isolated without
shutting down any other bays.
46/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Each station shall be equipped with an automatic prepaid card system for filling. The vending
machine will be equipped with a system to efficiently monitor all tankers. Each tanker will have
a smart card (electronic) to control his rotations and volume of water transported.
47/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
5.3.3.2 Control Unit
a) The unit will deliver only the allotted quantity of water authorized by the
system. After each filling the information (volumes) will be updated in the
control unit and in the regional SCADA.
b) Display access of the control unit can be secured by password for each
tanker, each contract.
c) The control panel shall be self-powered during 4 hours.
d) The control unit shall be able to send alarms by SMS to PAEW
technicians’ mobile phones.
e) The control units shall be the same for each TFS control panel, and shall
be in modular conception and upgradable.
f) Control units must be able to communicate with other devices: PLCs,
Controllers, smart sensors and other Units for the needs of process
controls.
g) The language program must be standard. The units shall be
parameterized with no specific language.
h) A connection on the local unit with a laptop must be anticipated and allow
an intervention in the program.
48/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
The following diagram Shows the general TFS schematic, the number of bays
depends upon the project requirements.
a) The data shall be sent to the Regional Control Room through GPRS or
GSM data, in accordance to available signal on site. As an option, optical
fiber medium could be proposed if available on site.
BOUSHER MUSCAT
AL KHOUD DHAKLIYAH
SUR AL SHARQHYIA
DUQUM AL WUSTA
49/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
b) In case of data transmission or SCADA breakout, the Control Unit shall be
able to store all data during 15 days.
50/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
5.3.3.5 Data Report to Control Room
a) The following data must be sent on daily basis (once in a day at 00.00
PM) to the main regional control room:
i. Total Volume delivered by Tankers per day
ii. Volume delivered by each tanker (name, tanker number
registration plate, contracted quantity, date)
c) Each filling station must have its SCADA backup (historics, curves), with a
local connection with a laptop.
d) The monthly reports must be automatically generated by the system last
day of the month at 00.00 AM.
51/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
h) The SCADA system must be able to print the report of all activated alarms
A water meter is a device that records the volume of water passing through a particular point in
the global water system.eg: pumping station, reservoir, consumer connection.
52/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Currently PAEW follows the below type of flow meter
Water meters are important for Utilities who need to bill their customers accurately for the water
used. Water meters shall conform to ISO 4064 standard and OIML R 49.
Domestic meters are to be installed vertically, on the outside of the property wall without any
protection installed at 1.5 m above ground level.
There is no water distribution network without leakage. Leakage is often the largest component
of difference between the total output of water and that consumed.
It is the difference between the total water input to the system and that is consumed.
District metering
Flow meters are installed at strategic points within the system compromising areas of
500 to 2500 connections.
There are different reasons for dividing network into zones. One is to have a greater control
over the distribution of water through monitoring the volume of water entering into an area. A
network can be divided in to District Metered Areas (DMA) for network assessment and control
proposes. Other benefits from Water Quality point of view are:
For the follow up of a network, a flow meter should be installed to measure the inlet and outlet
from a strategic point of the distribution network. This enables continuous network performance
assessment, which enables the identification of changes in network efficiency and thus
triggering field investigation exercises.
The following factors should be considered for the installation of a district meter:
53/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
Handover network pressure test if taking over a private network;
Maximum inlet diameter = 300 mm,
Electromagnetic flow meter + pressure linked via telemetry to access flow and pressure
data remotely,
Minimum cascading network,
Minimum number of boundary valves < 5.
Field Investigations
These are normally triggered by the network efficiency decreasing below the target
level. This decrease could be caused by opening of a boundary valve, new
connections, leaks or burst main.
Pressure control
Reducing the system pressures to the minimum level reduces the force behind leaks
and extends the working life of the network due to the reduced stress placed on the
network. Ways to accomplish pressure reduction are reducing pumping heads and the
use of pressure reducing valves.
In order to monitor the pressure in the network, pressure monitoring points should be located at
the following points within a DMA:
In order to asses and monitor the water quality, a sampling point should be installed at the inlet
of DMA. The sampling point should be installed as per the standard drawing TET/SD/5016.
HDPE
DI
54/55
Design Guidelines TET/DG/5005
Date: 14/05/2015
TRANSMISSION AND DISTRIBUTION Issue: 1.4
PIPELINES
6. SCADA
The following represents the basic minimum which should be monitored in the SCADA system.
All the data shall be collected and transferred to the Regional Control Room.
55/55
TET/DG/5006
Design Guidelines Date: 14/05/2015
Issue: 1.3
WATER RESERVOIRS
Electronic Document, only the original archived in Quality Department is signed / Printed copies uncontrolled
Contents
1. GENERALITIES ........................................................................................................................................ 2
1.1 Capacity ................................................................................................................................................. 2
1.2 Protection of water stored ...................................................................................................................... 3
1.3 Circulation of water ............................................................................................................................... 3
1.4 Cleaning and disinfection ...................................................................................................................... 3
2. DESIGN OF RESERVOIRS ....................................................................................................................... 3
2.1 Planning and Design Factors for Reservoirs .......................................................................................... 5
2.2 Location and Land Selection ................................................................................................................. 5
2.2.1 Location Factors .................................................................................................................................... 5
2.3 Schematic layout of a reservoir ............................................................................................................. 6
2.4 Provisional Arrangements ..................................................................................................................... 6
2.4.1 Ground level reservoir ........................................................................................................................... 6
2.4.2 Elevated tank ......................................................................................................................................... 7
2.4.3 Inlet pipe work ....................................................................................................................................... 7
2.4.4 Outlet pipe work .................................................................................................................................... 7
2.4.5 Overflow pipe work ............................................................................................................................... 7
2.4.6 Scour pipe work ..................................................................................................................................... 8
2.5 Testing of water retaining structures...................................................................................................... 8
2.6 Inspection and maintenance ................................................................................................................... 8
2.7 Access and protection ............................................................................................................................ 8
2.8 Security and access ................................................................................................................................ 9
2.8.1 Doors with direct access to water .......................................................................................................... 9
2.8.2 Secured hatch direct access to water .................................................................................................... 10
2.8.3 Ventilation Arrangement ..................................................................................................................... 12
2.8.4 Access ladder external ......................................................................................................................... 13
2.8.5 Access ladder internal .......................................................................................................................... 13
2.8.6 Lighting ............................................................................................................................................... 14
3. HYDRAULIC EQUIPMENT ................................................................................................................... 14
3.1 Pipes .................................................................................................................................................... 14
3.2 Valves .................................................................................................................................................. 14
3.3 Level detection .................................................................................................................................... 14
3.4 Meters .................................................................................................................................................. 15
3.5 Water quality monitoring ..................................................................................................................... 15
3.6 Access Road ........................................................................................................................................ 15
3.6.1 Approvals............................................................................................................................................. 16
3.6.2 Flooding ............................................................................................................................................... 16
3.6.3 Site Survey ........................................................................................................................................... 16
3.6.4 Geotechnical Investigation .................................................................................................................. 17
4. SCADA ..................................................................................................................................................... 17
1. GENERALITIES
The main purpose of the reservoir is to hold a strategic water reserve to meet the fluctuating
demands from the demand area and to maintain a desired and sustained residual pressure
head in the Distribution Network at all times.
Underground reservoir: entire structure is below ground level with partial reservoir top
above Ground Level. Such reservoirs are used in large storages in Desalination Plants.
These are invariably of RCC. These could be rectangular, square generally;
Ground level reservoir: entire structure sits on the ground level either on a mountain top
or at ground level and these tanks are mainly for Distribution systems. These are
invariably of RCC. These could be rectangular and or square;
Elevated reservoir: the water holding portion is located at a predetermined height called
“Straight Height” to support pressure head , supported either by a continuous structure
or by columns. These are invariably of RCC, MS Panelled and GRP are also used some
times elevated and supported by MS Frame Work. These could be rectangular, square,
inverted conical and or inverted trapezoid.
1.1 Capacity
The Terminal/Strategic capacity is defined on case by case basis according to the system
master plan.
The reservoirs must be covered. The cover protects the water against variations of temperature,
introduction of foreign bodies and reduces evaporation and thereby chlorine loss.
For preservation of water quality it is necessary to use appropriate construction materials and
an inner lining that does not adversely affect water quality.
Reservoirs must be vented for hygiene and taste. It is therefore necessary to cover ventilation
points with fine mesh to prevent the access or entry of animals, insects and dust.
The joints shall be treated with special attention. Particularly for concrete reservoirs, the most
appropriated solution should be chosen in order to avoid water leakage.
Control of water circulation in the reservoir is necessary to prevent short circuiting of water (as
water enters the reservoir it exits shortly afterwards leaving the remaining water in the tank for
extended periods) which leads to stagnation and water quality problems.
For better circulation of the water, baffles (plug flow) or jet plume (mixing nozzles) could be
installed.
After each intervention as a result of confirmed contaminated water in the reservoirs or at least
once a year all reservoirs are to be emptied, cleaned and disinfected.
2. DESIGN OF RESERVOIRS
The design of the reservoir depends on technical, economical, geographical and aesthetic
considerations and could change with time and location.
Each site should have a boundary/perimeter fence which should comply with legislation and
PAEW’s security and Health Safety Environment (HSE) Policy.
In line with Ministerial Decree (MD) No 286 the Design team must carry out an assessment of all
potential Hazards during construction and operation phases. This must include a risk
assessment detailing the future requirements for fire fighting, manual handling, electrics, lone
working, confined spaces etc. HSE PAEW is to be consulted at all stages of the design.
The overflow line should prevent overfilling of the reservoir. There is no valve on the overflow
line. The drainage line is taken from the low point of the reservoir.
The drainage line is connected with the overflow line and is equipped with a valve (normally
closed). The invert (base) of the reservoir is made so that water flows naturally to the drainage
line (slope of 0.5% minimum). A sump is to be incorporated in the base of reservoir (ground and
submerged reservoirs only).
For RCC reservoirs, the drainage system should be installed beneath reservoir in case of
leakage.
Inverted filter with perforated laterals and manifold to be installed for monitoring tank leakage
from bottom.
For the safety and security of the site Royal Oman Police and Civil Defence Authority’s
regulations shall be followed.
Adopt PAEW standard components that are readily available at PAEW stores
The location shall be selected so that water pressure to consumers meets PAEW’s criteria. The
choice of reservoir site is usually determined by the land availability for reservoir, inlet/outlet/scour,
overflow pipework, flow meter and pump station structure etc. The location shall not be near or next to
heritage places and graveyard. In Oman, mostly the service/storage reservoirs shall be kept on the
jabel (mountain) to supply water to the demand areas. The choice of ground reservoir at jabel or
elevated tank at ground shall be decided based on OPEX and CAPEX cost analysis. To ensure that
the proposed reservoir location and layout are acceptable, the proposed site shall be approved in
advance by PAEW. Consideration should also be given to the potential likelihood of future
development to enable a future storage of similar or required size within the site footprint.
Factors Requirements
Site selection Preferably center to the distribution area and proximity to
the source.
Electrical power supply facilities should be available or able
to be provided economically to the site.
Not near/next to the graveyard, tomb and heritage places
safe access to the site in all weather conditions
Provision of sufficient buffer from existing houses, and
future planned area development
Design Access road shall be designed as per the MoT standards.
The ascending gradient should not be more than 10%
(1V:10H)
Overflow
Overflow line
High high
level (HH)
High level
Low level
Firefighting reserve
Strainer/Screen
Inlet
Outlet/ Distribution
Meter Check Valve
to network
Sampling point or online
analyser
The low level is based on reservoir capacity, depth and daily demand. Furthermore, the criteria
of the time required to intervene in the event of a low alarm must be a major consideration
(travel time to site).
Partition shall not be required if the effective capacity of ground level reservoir is less than 25
cubic meter.
The inlet pipe diameter should be sized for the ultimate designed flows (considering one
compartment is filling and other under maintenance). A 90° bend shall be provided on the
discharge to allow proper mixing.
Motorized Operated Valve (MOV) shall be provided at the inlet of reservoir. If the reservoir
receives water from simple direct pumping main (single discharge) and the altitude of
reservoir is higher than the en-route elevation then the manually operated valve shall be
provided. However, if the inlet pipe size exceeds DN 400 (and DN 400) MOV shall be
provided to facilitate for easy operation.
The outlet pipe diameter shall be sized for peak instantaneous (peak hour demand or fire
flow scenario whichever is more) flows and shall be one pipe size larger than in the
discharge watermain to allow for a future increase in capacity.
The outlet pipe is to be positioned at a height to minimise the risk of any accumulated
sediment within the reservoir being disturbed and being discharged during reservoir
operation. This is typically achieved by positioning the outlet above the designed grade of the
reservoir floor, normally graded to achieve a minimum 100mm fall.
A redundant outlet shall be provided in each compartment of one size less than the main
outlet or DN 200mm whichever is greater. The redundant outlet shall be positioned next to
main outlet within the same outlet chamber. It shall be closed with the blank flange and to be
identified as “Redundant”.
An overflow pipe shall be provided in each compartment with a suitable inlet arrangement set
at an appropriate invert level. The overflow pipe diameter shall be sized for designed peak
instantaneous flows (all pumping running at possible extreme flow regime, no outflow from
reservoir) and sized to prevent excessive velocity. In general, the overflow pipe size is one
size up than the inlet pipeline. Bellmouth fitting is preferable for overflow arrangement,
situated a minimum 100mm above top water level with minimum of 300mm freeboard
between top of bellmouth and underside of roof elements and it should be free of obstruction
from roof members.
The overflow line shall be properly routed to nearby wadi and sufficient diligence should be
made in such that the overflow water should not cause any inconvenience by flooding nearby
dwelling or public access roads.
The scour point is to be located as to optimize scour and cleaning activities. A suitably sized
scour pipe shall be connected to the overflow line with a valve connection.
After completion of water retaining structure shall be tested before applying of any sort of
finishes including water proofing/coating/lining or any other finishes on internal and external wall
faces. The leakage test should be conducted with the bare structure. Upon completion of
leakage test and witnessed/certified by the supervision consultant/PAEW/authorised third party
the inner and outer wall faces shall be finished.
To confirm a reservoirs physical integrity, security and water quality, routine and periodic
exterior and interior inspections are necessary.
For the interior inspection the frequency varies by country. Oman does not specify a
compulsory frequency of inspection. A sound procedure would be to carry out an inspection
each time a reservoir is cleaned. This provides regular assessments of condition and identifies
remedial works that are needed before the deterioration is too great.
Inspection frequencies will be discussed and set by regional Operations Manager on guidance
provided by General Manager Operations, General Manager Asset Management, HSE, Water
Quality or their departments.
The protection of access to water facilities is important. Metal fences must be provided to
prevent trespassing, theft and introduction of harmful products to the water from act of domestic
and non-domestic aggression.
The following elements should be installed on sites that or deemed high or medium risks:
Secured perimeter with minimum of 2.5 meters with barbed wire at the top and security
gates lighting and signing as required,
Secured doors, secured reservoir hatches, secured chamber hatches with security
locks,
Secure Ventilation grilles, secured access ladder (s),
Secure electrical installation or other utilities,
CCTV or other monitoring equipment deemed necessary for the site by risk analysis or
advised from security advisors, Royal Oman Police (ROP) or PAEW.
As previous, reservoirs are normally enclosed but at low risks sites this could be of chain link
type as it would normally be to stop animals and tress passers only.
The following briefings and diagrams are designed to be incorporated on sites that are deemed
medium or high risk.
Air lock style double doors with sealed panels (internal and external) at locations with direct
access to treated water, will meet the specifications listed below.
These doors are equipped with a second internal anti contamination door with seals, hinges and
fastenings including fully concealed door locks at 90°open position. They are made from a
single plate of stainless steel with folded and shaped edges of 4mm minimum thickness and
include stiffeners as needed. The door is mounted on an outer frame that is seal to and built in
to the masonry.
Closing the sash exterior is provided by three anchor points and a concealed handle.
Locking is done by turning the lock 90°. Locks are hidden under a cover ensuring its external
protection. The number of keys is limited and they are common to all sites.
Each door and the first gate outside are fitted with an open sensor and a vibration sensor with a
combination box equipped with cable gland for a cable of 8 to10 mm in diameter. The output
cables are made by passages through the masonry and flowing into the compartment between
the 2 doors.
The implementation of louvre ventilation facades of watertight doors is not allowed. The opening
direction (right /left) of doors will be interior to exterior.
Identification plate
Dimension of passage
Padlock device conceals
Interior door
Hatches are to be of the type raised in single or multiple doors and equipped with a second
inner door with single or multiple covers forming an internal compartment which provides
insulation between the inside and the outside to protect the reservoir. This internal anti-
contamination compartment includes a drainage system and mounts for the hatch.
The assembly of (the) wing (s) Internal (s) includes ventilation to allow the free flow of air from
the tank, preventing the accumulation of high levels of chlorine and protects the roof of the tank
from the phenomenon of "sucking" during declining water levels. The outlet of the ventilation
must be protected by a mosquito grid made of stainless steel 316.
On the first cover of each door an open sensor and a vibration sensor with a combination box
equipped with cable gland for cable of 8 to 10 mm in diameter in sufficient quantity is to be
fitted. The output cables are made by passages through the wall bracket and terminating in the
compartment between the two traps.
The doors are sealed, vented and equipped with fixing points and concealed hinges. Opening of
the doors is supported by stainless steel springs. The doors should automatically lock in the
open position at 90 degrees. The outer cover is domed to promote runoff and lifting is done by
an external handle located on one side.
Locking is done by turning the lock 900. Locks are hidden under a cover ensuring its external
protection. The number of keys is limited and they are common to all sites. Access cover must
be single man lift type.
Exterior cover
Interior cover
Concealed
hings
Padlock system
conceals
Anti-insect netting
Folding security
bars
Interior cover
Concealed
Padlock system
hings
conceals
Anti-insect netting
Dimension of passage
Opening for cable
Reservoir shall have sufficient and safe ventilation facility. It shall protect against any intrusion
from outside by any means.
Exterior part of such an arrangement has metallic louvers to protect against any
thorough entry of solid or liquid contents. Louvers are located slanting at an angle
staggered and closely pitched so as to provide full protection. The outer louvers
framework shall be removed only with special tools for maintenance and cleaning
purposes.
Second and middle section has a closely woven mesh made of 316 stainless steel and
it is firmly fixed to the frame. The mesh avoids entry of any insects, reptiles or crawling
creatures.
Baffles
Anti-insect
netting
For security and maintenance of the exterior of the reservoir a ladder equipped with a safety
cage and hand rail must be installed. The ladder should be in aluminium or stainless steel.
Outside ladder shall have locking facility to restrict access to unauthorised personnel.
The internal ladder should be constructed of completely GRP or stainless steel only. Four rungs
of the ladder must protrude outside of the entry hatch. This can be achieved by part of the
Each site should be equipped with lighting which complies with Royal Oman Police and Civil
Defense Authority’s regulations and PAEW’s security and HSE Policy.
On the elevated reservoirs and the ones on high mountains spots Aviation warning light shall be
installed.
3. HYDRAULIC EQUIPMENT
The specification of each material will be given in the Standard Specification of PAEW.
3.1 Pipes
The type of pipe depends on the fluid being transported and the environment in which it is
installed. Usually, reservoirs pipes are made of steel (painted or stainless steel) or ductile iron.
3.2 Valves
Inlet and outlet valves should be Modulated butterfly valves. If connected with SCADA system,
these valves should be electrically opened and closed automatically with level detection.
For security of installation and operations it is necessary to have a by-pass pipe between the
inlet and outlet pipes.
A check valve (non-return) should be installed on the outlet before the by-pass.
For the detection of water levels in the reservoir the following solutions could be used.
1. 1 level sensor (4-20 mA) installed in the reservoir to measure the depth of water,
2. 4 float level controllers ''(level switches) Pear shape type '' for very low level, very high
level and overflow,
3. Hydrostatic level transmitters,
4. Ultrasonic level transmitters,
5. Pressure regulating valve,
6. Mechanical level indicator (cat and mouse type).
For level detection the recommended option is to equip each compartment of the reservoir with
one ultrasonic level sensor and two float level controlers (for LL and HH levels as additional
security). The motorized valve shall be installed at the main inlet.
3.4 Meters
To know the quantity of water received and pumped out and to monitor for leakage from the
reservoir the inlet (optional only for specific case) and outlet pipe should be equipped with an
electro-magnetic flow meter.
If a reservoir consists of two compartments, the flow meter shall be installed on the common
outlet.
If a reservoir is feeding the pump station as suction and located in the same compound as the
pumps, then the flow meter shall be on the common discharge line of the pumps and no need
to install a flow meter at the outlet of the reservoir.
In order to monitor the quality of the water the sampling points shall be located on inlet and
outlet mains, (ensuring that samples can be collected when one or more cells are taken out of
service). An online monitoring may be installed on critical reservoirs e.g. distribution or
transmission.
Access road is to be provided from nearest public road to the PAEW site (reservoir/pump
station), where the access from a public road is not available then a suitable access road
shall be created. The design of access is based on the size of operating and maintenance
vehicles (min. 3T truck capacity).
As part of the designing/planning phase, necessary approvals should be obtained for the
access road from the following respective regional authorities with a detailed drawing
showing the followings
project location
access road layouts including daylight of cutting/filling
cross sections at different chainage (shows bench cutting/filling)
longitudinal profile shows the percentage of ascending and descending slope
road markings and signs etc.
Approvals shall be required from the other relevant authorities which may be deemed
required for the project.
3.6.2 Flooding
The
The site survey shall also indicate the proximity of adjoining properties, particularly those
which may be impacted upon adversely by the construction and operation of the reservoir.
Reservoir foundations;
Pipework thrust restraint;
Access road and hardstand area;
Settlement issues
Maximum height of bench cutting\filling
The geotechnical consultant is to prepare both a factual and interpretive report which details
the investigation and findings.
4. SCADA
The Supervisory Control and Data Acquisition (SCADA) and Programmable Logic Controller
(PLC) shall supervise, monitor and control the reservoirs.
All the data shall be collected from the different units and transferred to the Regional Control
Room.
The following represents the basic minimum which should be monitored in the SCADA system.
Continuous monitoring of level (data);
Low Low level (alarm);
Low level (alarm);
High level (alarm);
High High level (alarm);
Overflow (alarm);
Suction and discharge pressure low and high alarms;
Position and command of inlet and outlet valves;
Water quality parameters (chlorination, turbidity, conductivity ,pH and temperature
(data + alarms) to be confirmed by Water Quality department;
Flow inlet/outlet (data + alarms);
Historic data;
Fire alarm;
Chlorine leakage alarm.
CHLORINATION
Electronic Document, only the original archived in Quality Department is signed / Printed copies uncontrolled
Revision Date Details
Contents
1. SCOPE ........................................................................................................................................................... 3
2. RESPONSABILITIES ................................................................................................................................... 3
3. ASSOCIATED DOCUMENTS .................................................................................................................... 3
4. CHLORINE DISINFECTION THEORY ..................................................................................................... 4
5. SECONDARY CHLORINATION REQUIREMENTS ............................................................................... 6
5.1 Water Quality Standard Orientations ........................................................................................................ 6
5.2 Water Systems in PAEW, Water Age & Transfer Time .......................................................................... 6
5.2.1 Transmission systems/SR ...................................................................................................................... 6
4.2.1 Wells ...................................................................................................................................................... 7
5.3 Predictive and Decision-making tool : Water Quality modeling.............................................................. 7
6. CHOICE OF DISINFECTION SYSTEM ..................................................................................................... 8
7. DISINFECTION SYSTEMS, AGENTS & TECHNOLOGIES................................................................. 10
7.1 Disinfection agents recommended by PAEW for new projects ............................................................. 10
7.1.1 Calcium Hypochlorite .......................................................................................................................... 10
7.1.2 Sodium Hypochlorite ........................................................................................................................... 10
7.1.3 Sodium Dichloroisocyanurate or DCCNa ........................................................................................... 10
7.1.4 On-Site Electrolytic Chlorine Generation System (OSEC) ................................................................ 11
7.2 Disinfection Agents not recommended by PAEW for new project........................................................ 12
7.2.1 Chlorine Gas ........................................................................................................................................ 12
7.2.2 Chlorine dioxide................................................................................................................................... 13
7.3 Others Techniques (non chlorine based) ................................................................................................. 13
7.3.1 UV light................................................................................................................................................ 13
7.3.2 Ozone ................................................................................................................................................... 13
7.4 Choice of disinfection system summary ................................................................................................. 14
8. CHLORINE MEASUREMENT & MONITORING .................................................................................. 15
8.1 Regulation/Control of dosage flow ......................................................................................................... 15
8.1.1 Wells .................................................................................................................................................... 15
8.1.2 Reservoir or Pumping Stations ............................................................................................................ 15
8.2 Type of measurement............................................................................................................................... 16
8.3 On-line analysers ..................................................................................................................................... 17
8.4 Water Quality sampling point.................................................................................................................. 19
9. MONITORING SCADA LEVELS AND ALARMS ................................................................................. 19
10. HSE GUIDELINES ON CHLORINATION UNITS.............................................................................. 19
11. DOCUMENTATION .............................................................................................................................. 21
References ............................................................................................................................................................ 22
CHLORINATION
Figures
Tables
Abbreviations
CHLORINATION
1. SCOPE
This document has been prepared as a Guide for PAEW engineers and their Consultants with
regards to potable water disinfection and by chlorination. Note that other methods of
disinfection (e.g. UV, ozone, etc.) are presented but not detailed in this document.
This document describes the different solutions proposed for chlorination alongside with criteria
in order to choose the most suitable system for PAEW infrastructures.
2. RESPONSABILITIES
It is the responsibility of the HSE Manager to review this document annually in line with all HSE
acts, law and regulations.
It is the Water Quality Manager’s responsibility to review this document annually in line with
Omani Water Standards and best/new practices occurring in the water Business.
It is the Technical Standards Manager responsibility to review this document in line with
International Standards and best/new practices occurring in the water Business every three
years.
The Consultant is responsible for studying the requirements and submitting for approval
detailed drawings for a continuous and safe operation of the chlorination system after preferred
system analysis has been undertaken. The Consultant is also responsible for supervising the
installation works.
The Installer is responsible for the build, pre-commissioning, commissioning and complete
functioning of the installation. It is also the Installer’s responsibility to ensure that all
commissioning documentation meets the requirements of PAEW.
The day-to-day Operations & Maintenance is undertaken by O&M contractors as soon as the
project is handed over by the Installer. One year warranty shall be included for each new
project (after commissioning).
The chlorination system shall be designed and suitable for operation in the climatic conditions in
the Sultanate of Oman.
3. ASSOCIATED DOCUMENTS
CHLORINATION
Chlorine is widely used in water industry as a disinfection agent. PAEW recommends the use of
hypochlorite (sodium or calcium) and DCCNa (described in section 7). Even if the initial
reagents are different (sodium hypochlorite, calcium hypochlorite, DCCNa), the active agent
remains the same; free chlorine.
The following section will give a brief overview of chlorine disinfection theory, and how the
disinfection efficiency is influenced by pH, temperature, disinfectant concentration and contact
time.
The figure below gives a summary of the different forms of chlorine depending on pH.
Chlorine is a powerful oxidant. It will react with some elements and it will also have a biocide
action. The two main forms of chlorine are: the free chlorine and the combined chlorine.
- The first one (free chlorine) will be divided, after dissociation in the water, into 3 different
types of chlorine (dichlore, hypochlorous acid, hypochlorite ion), with a different level of
biocide action efficiency for each type, depending on pH values.
- The second one (combined chlorine) will be combined with some oxydable element and
will not have any biocide action.
CHLORINATION
It can be noted that at pH=7.5, HClO and ClO- concentration are close to 50%. The most
efficient disinfectant form is the hypochlorous acid (HClO). The best range of pH for a good
disinfection will be between 6.5 and 7.5.
High temperatures will favour the bactericide effect, although low temperatures favour HClO
against ClO-. High temperatures will speed up the disinfection reaction. However, one major
drawback is that high temperatures decrease the reagent stability in time, and therefore its
efficiency.
The biocide efficiency of the different reagents can also be determined from the product of dose
(in mg/L) with contact time (in minutes). The table below highlights the CT (mg.min/L) for
different types of reagents recommended in this document.
CHLORINATION
5. SECONDARY CHLORINATION REQUIREMENTS
The current Omani Un-bottled Drinking water Standards (8/2006) specify a free chlorine
concentration range of 0.2 - 0.5 mg/l as an acceptable range for drinking water through public
distribution systems. This standard is currently used to monitor compliance at all points from
treatment plant outlet to customer’s tap within PAEW perimeter of operation.
Regarding the commonly encountered long distances between production sites and customers,
the level of chlorine may decrease to zero without any post chlorination facilities, increasing the
water quality degradation risk.
Two main configurations are mentioned in this guideline, depending on the type of asset:
Service Distribution
Reservoir (SR) Network
Well water disinfection, straight after water abstraction from water tables.
In transmission systems, location of the post chlorination units will depend on two main
aspects:
Water age and transfer time;
Chlorine decay throughout the water networks (depending on both the pipe material
and the chlorine decay in the water due to initial concentration, temperature and
organic matter content)
The water age and transfer time have been calculated using hydraulic modelling tools and/or
average daily demand data and pipes layout, and added on schematics for each governorate,
as presented in Figure 4 (ie. South Batinah).
CHLORINATION
It is worth noting that most of the water in the transmission system is coming from desalinated
water (rarely blended with ground water), whether it concerns MSF or RO process based
treatment plants.
The water is generally chlorinated at the production point at concentration range of 0.2 - 0.5
mg/L.
Laboratory tests have showed that chlorine reaches a level of 0.05 mg/L after 100h1 with an
initial concentration of 0.5mg/L. Therefore, without taking into account the material and the
diameter of the pipe, it could be considered that the water should be secondary chlorinated
after 100h of water age at the service reservoir (primary distribution point) at the maximum. In
reality, this time may be lower due to specific constraints and this value may be considered as
maximum acceptable one. Specific tests and guidance will be given by the Water Quality
Department depending on each case.
4.2.1 WELLS
Most of PAEW wells water is not disinfected and present a high risk of microbial contamination.
The groundwater may also contain more organics than water produced by desalination plants.
Thus, special attention shall be paid to the disinfection treatment, as there is a higher risk of
generation of by-products such as chloramine or THMs and chlorine decay may be higher and
risk of bacteria "re-growth" also higher.
Water quality network modelling is a very powerful decision support tool to determine at the first
place the location of post chlorination units.
Based on the distribution and transmission network configuration (length, diameter, time of
transfer, etc.) the required free chlorine concentration at the distribution reservoir will be set,
and the post-chlorination units located where required, based on transmission and distribution
water quality model. Basically, once the free chlorine concentration leaving the production site
1
Tests realised in PAEW Central Laboratory in Ghubra (22/09/2012) and in Sur Desalination Plant laboratory
(20/09/2012)
CHLORINATION
is determined, it shall be possible to predict the remaining free chlorine in the transmission and
distribution network. Chlorine decay kinetic factors will be determined through laboratory tests
and on-site sampling campaigns.
The main considerations which affect the final choice of a disinfection technology are:
Technical
o Original Water Quality & Flow to be treated;
o By-products (very low in Oman, as organic matter theoretically is inexistent in
desalinated water – but present in surface freshwater and water tables);
o Dosage & Contact time;
o Treatment capacity;
Geography
o Access to site (for reagents delivery);
o Storage space on site with respect to HSE rules;
Logistics
o Procurement and delivery of reagents;
o Availability of reagents in Oman;
Resources
Equipment
HSE rules
Emergency services
Cost
o Supply & Installation costs
o Maintenance costs
Preventive;
Corrective;
o Operational Costs;
Chemicals & Reagents;
Spare parts.
The table below gives some examples by criteria (technical, geographical, etc.) to take into
account for the choice of a disinfection system.
CHLORINATION
What are the Max & Min flows to be treated?
What is the required Maximum dose rate?
Is the proposal for Manual or Automatic dosing &
control ?
1 Technical
What Chemical stock level is required on site ?
What chemical control measures are in place or
planned for the site ?
What are SCADA requirements / availability ?
What is distance from the chemical storage area to the
nearest populated area?
What limitations does the access route impose on
2 Geography
transport ?
Are there any topographical issues ?
What restrictions apply to the site and surrounding
d
area ?
de
en
Are the Hazardous material Regulations met? m
3 Regulation / Legal
m
co
Does Future Legislation impact on the choice?
e
R
What exclusion zones are in place (or proposed)
t
No
around the facility? e.g Transport load restrictions,
Airports, Miltary bases, environmental.
What volume (by weight) is required to be
transported?
Are there any delivery constraints from the supplier
which impact on stores capability?
4 Logistics
Are spares readility available?
Are there near‐ by Assets that are available for Shared
storage, chemical delivery?
5 Resources Is staffing & training required?
6 Equipment Does history prevent its use?
Can the equipment be used so far as reasonably
7 HSE
practicable?
8 Emergency Services Are they available?
9 Cost Which is the best whole life cost option?
1 New projects
2 Existing projects Review ofprojects in progress
3 Existing assets
CHLORINATION
Calcium Hypochlorite is available on the market under different trade names, either in powder,
granular or agglomerated form. Its main characteristics are as follow:
- Free chlorine rate : up to 70%
- Purchased in 25kg or 50kg bags
- Solubility : from 215 g/l at 00C to 234 g/l at 400C
- Working solution concentration generally lower than 100 g Ca(ClO)2 per litre
- Deterioration in time : 2 to 2.5% over 1 year against 4% for Sodium Hypochlorite
Sodium hypochlorite, often referred to as liquid bleach, is the most widely used of the
hypochlorites in potable water treatment.
- Free chlorine rate : around 15%
- Large storage area required compared to solid calcium hypochlorite
- Easy and safe to handle
- Commercial liquid bleach is usually delivered at a concentration of 149 à 158 g Cl2/L.
DCCNa is the most recent product releasing chlorine. It presents some benefits (high stability
under high temperatures, higher free chlorine rate) compared with bleach and other products
releasing free chlorine.
Like Calcium Hypochlorite, DCCNa is available under different forms; powder, tablets, granula
or agglomerated.
- Solubility: 30g/100mL at 25°C
- Free chlorine rate : around 90%
- Very stable and easy to use source of free chlorine
- Not toxic
CHLORINATION
7.1.4 ON-SITE ELECTROLYTIC CHLORINE GENERATION SYSTEM (OSEC)
When using OSEC, chlorine and sodium hydroxide are produced in-situ by electrolysis, by
passing an electric current through salt water (or brine). The typical produced chlorine
concentrations are between 6g/L and 30g/L depending on the technology.
Basically;
- Hypochlorite is produced at an average concentration of 6-8 g/L;
- Salt of average quality can be used;
- Complex maintenance, but cells are only replaced every 4-5 years.
The operating figure below highlights how these OSEC technologies work.
The water arrives by (1) and is cooled or heated (up to 20°C). The water crosses a softener (3)
and goes directly in a salt saturator (4). A dilution is made in a tank (6) if necessary. The pump
(5) injects the water in the electro- chlorinator (membrane or open cells) (7). The chlorinated
water is stored not more than 24 or 48h in the tank (8) and injected in the network (10) by the
pressure pump (9). Operation can be automatically monitored by flow meter and on-line
analyser, connected to a SCADA system.
CHLORINATION
Gas Chlorine is available typically in steel containers, under a pressure of about 40 bars. This
can be drawn off as a liquid with a controlled evaporation (liquid to gas) phase or drawn off
directly as a gas. The required chlorine levels dictate the process requirement.
The specific gravity of the liquid chlorine is about 1.44 at 20° C decreasing to 1.25 at 70º C. This
results in liquid chlorine filling the entire volume of the container at 70ºC.
The figure below shows how the chlorine gas system works:
The water which needs to be chlorinated arrives through the pipe (1). The gas is stored in the
cylinder (2). The water which will be used for gas transportation is collected (3), pressurized
with the high pressure pump (4). The gas is injected in the water in (9). The high chlorinated
water is injected through the injection point (6), and a sample is collected in (8) to be analyzed
(11). The flow is monitored by a flow meter (5) and all information are amplified and collected
(12), in order to calculate the injection rate in the recorder (13) and transferred to the control
unit (14). (15) is a filter used to de-chlorinate the water when the calibration of analyzer is
requested.
CHLORINATION
7.2.2 CHLORINE DIOXIDE
Chlorine dioxide (ClO2) is a yellow or orange gas also called biocide. This gas is not stable,
and very soluble in the water. Its disinfection efficiency is generally higher than hypochlorite or
chlorine gas and it does not depend on the pH range (5-10). However, due to its instability, this
reagent must be produced on site from sodium chlorite, chlorhydric acid and chlorine gas. The
residual chlorine dioxide reacts with HDPE and causes a rapid ageing of the pipe. Thus, ClO2
oxidizes the superficial layer of the pipe, and creates small slots that tend to shorten the pipe
lifespan.
PAEW does not allow these solutions as a matter of safety. Chlorine gas is heavier than air
and escaped gas will therefore concentrate at floor level, or collect in ducts under the floor.
Chlorine is a toxic and highly irritating gas immediately affecting the eyes, nose, throat, larynx
and main bronchial tubes. Finally, if there is an explosion, the dispersion of chlorine gas could
be dramatic if stored within cities.
The two techniques presented below are generally used at the outlet of treatment facilities, but
not in networks.
7.3.1 UV LIGHT
UV-C rays are the only rays which have a germicide effect, the most efficient wavelength being
at 253.7 nm. There are some advantages to use UV light such as no storage of chemical
reagents is required and the disinfectant action is very quick. However, the efficiency of this
technology is difficult to monitor, as the microorganisms are not destroyed, but only
“deactivated”.
By using this technology, no remaining effect will occur in the network.
7.3.2 OZONE
Ozone is one of the most powerful oxidant, and has a very efficient disinfectant power. It is
produced from dry air or oxygen by discharge of electricity or through photochemical reactions.
It is colourless at room temperature and condenses to a dark blue liquid. It is generally
encountered in dilute form in a mixture of oxygen or air. Concentrations in excess of 30% in gas
can be very unstable and explosive.2
Despite of its excellent disinfectant power, Ozone does not have a persistent disinfection effect
in water networks.
PAEW does not recommend these two solutions. These techniques are never used in
networks. There is no remaining effect for both of them, as water transmission networks are
long and water age important, it would not be accurate to install such technologies according
to PAEW.
2 th
“White’s handbook of Chlorination and Alternative Disinfectants”5 edition; Black&Veatch corporation;
2010
CHLORINATION
7.4 CHOICE OF DISINFECTION SYSTEM SUMMARY
The table below summarises the different options discussed in the above paragraphs:
Table 3 Choice of Disinfection system summary
Sodium Sodium
Calcium
Chlorine Hypochlorite Hypochlorite Chlorine
Hypochlorite DCCNa UV Ozone
Gas (NaClO) (NaClO) Dioxyde
(Ca(ClO)2)
Bleach OSEC
Powder,
White powder,
Physical Yellow/ Tablets,
Gas granular or Yellow liquid Liquid Rays Gas
Aspect Orange gas granular, or
agglomerated
agglormerated
Free chlorine
> 99% 40 to 70% < 15 % < 15 % - 90% HClO N/A N/A
rate (%)
Deterioration Lamp
Stable 2 - 2.5 % a year 2 - 4 % a year 2 - 4 % a year Stable Stable N/A
rate ageing
Optimal pH
5 < pH < 7.5 5 < pH < 7.5 5 < pH < 7.5 5 < pH < 7.5 6 < pH < 10 6 < pH < 7.5 N/A N/A
range
Among these solutions, PAEW recommends either hypochlorite (Sodium or Calcium), DCCNa or On-
Site Electrolytic Chlorine Generation System.
Even if it is more complex than the direct use of hypochlorite, the Electro chlorination process remains
safer as it stores only salt on site. Moreover, free chlorine is generated continuously and enables a
very fine dosage. This process is safe, well known and widely used. It has been developed as an
alternative to pure chlorine storage. However, as the process is more complex, it does require more
maintenance.
The Consultant shall provide a detailed cost-benefit analysis to PAEW, shall several systems
be suitable for a new project.
CHLORINATION
The schematics below give an example of how the injection shall be controlled for wells and
pumping station or reservoir.
8.1.1 WELLS
Q2
FM
Q1
The flow of the pump (Q2) injecting chlorine in the water system is only controlled by the upstream
total flow (Q1 measured by flow meter FM) in the pipe. The dosing pump is working only if the well
pump is working.
Q1 Reservoir
FM
or PS
CHLORINATION
The flow of the pump (Q2) injecting chlorine in the system is monitored by both :
The Water Quality on-line analysers are installed at different locations depending on the type of
asset. The table below summarises the different kind of analyser by type of site:
In the water industry, different technologies of analyses are found to titrate the different forms of
chlorine. The two principal methodologies are:
CHLORINATION
The table below will give a comparison of different technologies of chlorine titration.
Water Quality can be continuously monitored through on-line analysers, the results data being
transferred to regional and national SCADA. The measuring chain for on-line analyser which is
shown on Figure 11 has to be followed to validate the data.
Calibration
Maintenance
On‐line analyzer
The below table gives an example of the different types of maintenance required for an on-line
chlorine analyser. There are several manufacturers in Oman and each maintenance
programme maintenance is specific. The maintenance programme shall be described by the
manufacturer’s user manual.
CHLORINATION
Table 6 Example of analyser maintenance schedule
PAEW should request the manufacturers to provide 2-year maintenance and 1-year warranty
contracts in order to follow maintenance operation requested in user manuals. Log books shall
be provided and filled in at each calibration after crosschecking with portable equipment or
replacing spare parts.
CHLORINATION
The sampling point is a fixed tap located on different types of assets owned by PAEW
(Reservoir, Pumping station, TFS, Water Treatment Plant). At regular intervals, the samplers
from the Water Quality team of PAEW take some samples, and a whole batch of parameters is
tested in the laboratory. As an example, here is a typical sampling point to be installed on the
network.
Figure 13 Sampling point (vertical pipe) Figure 12 Sampling point (network) technical
technical design design
The respective standard designs for sampling points are:
TET/SD/5016 Water Quality Sampling Point for Network
TET/SD/5017 Water Quality Sampling Point for vertical and horizontal pipe
The SCADA system shall supervise, monitor and control the following parameters:
All the analysers shall be connected to the SCADA system. All these information shall be
transferred to Regional Control Centre and National Control Centre.
1. Follow all principles of the Construction Design and Management Regulations 2002
CHLORINATION
2. Design and build safe facilities for chlorine stores, equipment, disinfection system and
chemicals.
The table below gives an overview of the different precautions to take when installing
chlorination units:
Table 7 On-site Requirements
Sodium Calcium
hypochlorite hypochlorite DCCNa On site generation
(liquid) (solid)
Raw material- Concentrated Powder or
Powder Salt
chemicals solution tablets
Power supply 240 Volt AC 240 Volt AC 240 Volt AC 240 Volt AC
Retention for
delivery of raw yes yes yes yes
material
Retention zone for
yes yes yes yes
installation
Ventilation yes yes yes yes
As electro chlorination systems generate Hydrogen the ATEX Directive covering the use of
equipment in a potentially explosive environment applies to the design of these systems. ATEX
requires that a zone is applied to any equipment and storage tanks which may contain
hydrogen. Within this zone any electrical equipment must be suitably rated for use within a
potentially explosive atmosphere. In addition to these requirements, gas and explosivity
detectors shall be installed (existing or new projects).
Regarding the retention zone, its volume shall at least be the same as the product storage
capacity. A high level alarm shall be installed in the retention location.
3. Set up procedures that can be handed over to the operators of the plant to ensure the
correct and safe systems of work are followed.
4. Design emergency plans and equipment that can deal with a spills, leaks or
catastrophic failure in the given area and surrounding if required
CHLORINATION
5. The designer or contractor must provide or make provision for the following for
takeover by the operational owners of the asset;
a. Servicing schedules for alarms, detectors, and other equipment designed for
the security of the chlorination unit
b. Servicing schedules for the everyday use of equipment such as pumps,
mixers, processes etc.
c. Provide signage for the identification of the hazards, danger areas,
prohibition, mandatory and emergency as required
d. Provide Information on good housekeeping, cleaning and maintenance
regimes
e. Provide emergency response programs in line with the system installed.
f. Provide training, information and instruction on the equipment the process
used and the substances under COSHH required.
g. Provide a list of the PPE and Specialist PPE required for the system installed
h. Provide a HSE manual for the installation
PAEW Health, Safety and Environment department has designed policies, process safe
systems of work etc. that will accompany the end user of these systems and the contractor is
asked to ensure that the link for all HSE document:
http://paewportal/Eng/qms/SitePages/QMS%20Library/index.aspx is written in to their HSE
manuals as well as the email address for the HSE department hse@paew.gov.om.
Two matrixes are given in Appendix. They give an overview, by type of installation, of the
Personal Protective Equipment and emergency equipment required on chlorination sites.
11. DOCUMENTATION
The Consultant shall ensure that all documentation is included when a new chlorination system
is installed;
Technical Designs
Drawings
Functional descriptions
The Consultant shall also hand over the following documents to PAEW;
Maintenance log book (for analysers & chlorination units)
Preventive Maintenance schedule and List of spare parts with frequency of
replacement
CHLORINATION
REFERENCES
“Effects of Water Age on Distribution System Water Quality”, EPA, August 2002
CHLORINATION
APPENDIX : CHEMICAL AND CHLORINE GAS MATRIX FOR THE RECOMMENDED MINIMUM PPE IN LINE WITH THE VARIOUSE TYPES OF DISINFECTION OR POST
DISINFECTION UNITS
PPE
Gloves Chemical
Chemical Apron
Boots Chemical
Full EBA or BA
Gloves Work
Shoes Work
Face Shield
Boots Work
Dust mask
Apparatus
Bump cap
Ear Muffs
Ear plugs
Coveralls
Hard hat
Goggles
Glasses
Long
Gas
Item
1. This PPE Matrix is only a guide line, PPE listed is normal in the varying process range, but may change with technological advancements
2. Prior to any user carrying out work with COSHH substances or disinfection processes, staff must carry out a full risk and COSHH assessment and where required
make changes as necessary. And in line with Manufactures Safety Data Sheets (MSDS)
3. The following servicing guide should also be applied,
a. All Gas Monitors checked and recalibrated every 6 months unless single detector, then every two years and all cells replaced every two years
b. Where required, all SCBA should be checked and inspected by the user prior to use and every 6 months by independent certified operative, further it should
be refilled after it drops below 30% of the cylinder capacity.
c. All PPE must be replaced when worn, torn, and damaged or if over exposed i.e. during a serious spillage etc.
23/24
Standard Specification TET/SS/5501
Date: 14/05/2015
DISINFECTION and SECONDARY Issue: 1.1
CHLORINATION
APPENDIX : CHEMICAL AND CHLORINE GAS MATRIX FOR THE RECOMENDED EMERGENCY EQUIPMENT IN LINE WITH THE VARIOUSE TYPES OF
DISINFECTION OR POST DISINFECTION UNITS
detector. (note 3)
green white etc.
Equipment
Petroleum
Apparatus
Eye Wash
detectors
Detector
Training
Area
24/24
Design Guidelines TET/DG/5008
CATHODIC PROTECTION SYSTEM FOR Date: 14/05/2015
Issue: 1.0
WATER PIPELINE
Electronic Document, only the original archived in Quality Department is signed / Printed copies uncontrolled
Revision Date Details
Contents
1. Introduction ................................................................................................................................................... 2
1.1 Special Instructions .................................................................................................................................. 2
2. Cathodic Protection System ......................................................................................................................... 2
2.1 Methods of Applying Cathodic Protection .............................................................................................. 2
2.1.1 Sacrificial Anodes .................................................................................................................................... 2
2.1.2 Impressed Current .................................................................................................................................... 2
2.2 Sacrificial (Galvanic) Anodes Cathodic Protection ................................................................................ 3
2.3 Impressed Current Cathodic Protection ................................................................................................... 3
3. General Requirements .................................................................................................................................. 4
4. Basic Design Data/ Guidelines ..................................................................................................................... 5
4.1 Test Station ............................................................................................................................................... 6
4.2 Reference Electrodes ................................................................................................................................ 7
5. Functional Guarantee .................................................................................................................................... 7
6. Documentation .............................................................................................................................................. 8
1. INTRODUCTION
This document has been prepared as a Guide for PAEW engineers and their Consultants with
regards to Design and engineering activities for Cathodic Protection (CP) System for buried
water pipeline. This guide covers the requirement of the system using impressed current
anodes.
The CP system design expert is advised to visit the site in order to acquaint himself with all the
necessary information such as soil conditions, transportation facilities, data of similar pipelines
and underground cables & cable trench/corridor in the adjacent pipe corridor, electrical
transmission line/PDO/OXY pipeline interferences, etc. for proper design and execution of the
work. Ignorance of the site conditions will not be accepted as a basis of claim for any
compensation whatsoever.
Cathodic Protection (CP) is a technique for protecting metal structures, such as pipelines, from
electrolytic corrosion by making the structure the cathode in a cell, either by applying an
electromotive force directly or by putting it into contact with a more electropositive metal.
Cathodic protection may be achieved in either of two ways - by the use of an impressed current
from an electrical source, or by the use of sacrificial anodes (galvanic action).
As Magnesium is more reactive which can be used in high resistive medium such as Soil and
Water. Zinc and Aluminium anodes can be used in low resistive medium like sea water. The
choice of sacrificial anodes for the cathodic protection depends upon the soil resistivity values.
If this value is within 1000 Ohms-cm, Zinc anodes will be used and if the value is between
1000-7500 Ohms-cm, Mg anodes will be used.
As per the soil resistivity report, if the soil in the pipe invert is found to be corrosive, then it is
required to design a temporally cathodic protection using galvanic (sacrificial) anodes. The
system should be installed and operational immediately upon backfilling. This system is
required to maintain for the duration of lying of pipes or until the new ICCP systems is
commissioned or whichever is encountered first.
It is necessary to distribute the number of anodes along the length or over the pipeline structure
to be protected as this is general y limited to the small areas of protection.
Metallurgical testing and physical inspection of cast anodes, anode identification and
documentation shall be carried out in accordance with NACE SP0387.
The permanent Impressed Current type Cathodic Protection (ICCP) system for the buried
pipelines is preferred. The following minimum requirements shall be adopted;
- Two core of required cross-section stranded copper conductor, PVC insulated, overall
FRLS PVC sheathed armoured power cable for power connection from power supply
source to T/R unit.
- Required thermit weld cartridges complete with mould and all accessories of
Cathodic measurement bonding cables with pipeline and welding of the same with the
pipeline.
- Pure epoxy encapsulation of the anodes cable connections to pipeline.
- All civil, structural and electrical materials required for installation of CP system.
- All materials required for laying and termination of cables including cable trays, GI
conduits, lugs, glands, markers, grounding material, etc.
3. GENERAL REQUIREMENTS
Under the Cathodic Protection system shall cover the following for the various systems and
equipment’s:
Complete soil resistivity survey for the pipelines along the entire buried pipe lengths.
Detailed design as per the design data, standards and codes of practices specified and
the approved soil data.
Carrying out detailed engineering and get approval from PAEW and PAEW
representative.
Complete manufacture including shop fabrication, assembly, and testing and inspection
at manufacturer’s works.
Supervision, erection and commissioning, including but not limited to fabrication and/ or
pre-assembly, if any, civil works, testing and putting into satisfactory operation of all the
equipment/ system and handing over to PAEW and successful completion of initial
operation.
Conducting Functional Guarantee tests after successful completion of initial operation.
Submission of all the design drawings, design calculations, technical data sheets,
“As Built” drawings, manufacture and assembling practices, construction/ installation
The data of pipelines to be protected and wrapping and t y p e o f coating employed for
the protected pipelines are varies from project to project, these information shall be get from
respective project specification.
The Cathodic protection system will be sized in order to guarantee, at each point of same
system, the minimum pipe-to-soil potential value of (-) 0.95 V versus Cu/CuSO4 half-cell
reference electrode. The maximum negative potential value allowable at the drainage point
will be (-) 1.2V (as per BS7361/1991 - Section 2, Table 1).
Overall design Pipeline coating efficiency shall be considered as not more than 70%
througho ut the design pipeline of 30 years for design of ICCP system.
The design current protection density shall not be less than 0.5 mA/Sqm and 20% design
current is to be kept as provision for redundancy.
The design anode consumption rate shall not be less than 0.4 Kg/Amp/year for High Silicon
chromium iron anode.
Design life for the ICCP system shall be not less than 30 years.
The rating of transformer rectifier shall be considered for an additional requirement of 25%
power compared with the power required under normal operating condition.
Detailed design calculations for the design of the entire system t o b e s u b m i t t e d to PAEW
for approval.
As part of corrosion survey full particulars regarding secondary structure including power
cables, communication lines, oil/gas lines etc. which would adversely influence the system
or would be influenced by the system must be collected. The Cathodic protection system would
incorporate suitable mitigation measures for varying types of soil and moisture content.
Cathodically protected section of the pipe line shall be electrically isolated by use of insulating
joints.
The pipes in the cased crossings with seals shall be protected by sacrificial anodes. The
anodes shall be in the form of ribbon or arc shaped rod and would be welded to the carrier pipe
The external of casings would be coated in the same manner as carrier pipes and also
provided with anodes on both sides of the pipe.
Test stations along the pipeline shall be provided along the pipe corridor for monitoring the
performance of cathodic protection system and bonding of pipe lines in common pipe trench
at intervals not exceeding 1000 meters. Test stations shall have, besides pipe-to-soil
potential measurement and bonding facilities, four terminal facilities for line current
measurement.
At both sides of Wadi crossing, PDO/OXY and major road crossings, electric railway
crossings.
At all insulating joints. The test station shall have terminal facility for connection of
grounding cell to pipeline. Besides terminals shall also be provided for pipe-to-soil
potential measurement on both shoulders of joint.
At crossing of AC/DC electric traction system.
At vulnerable location with drastic change in soil resistivity.
At HT overhead line crossings and selected locations where HT line passes close to
pipe line.
In vicinity of DC networks or grounding system where interference problem are
suspected.
At valve location.
At crossing of other foreign pipe lines (bonding facility with resistor shall be provided).
Additional test stations described above, many of which shall fall intermediate between
potential test- cum-bond stations, shall have binding facilities. Some of these additional test
stations meant for a single pipe or such additional test stations may coincide with those test
stations located at 1000 metres interval.
Test stations at location of insulating joints shall be installed independently. Details of
terminal facilities and connection schemes for individual type of test station/ current
measuring station/ test- cum-bond station shall be as per relevant standards.
The location of all the test stations shall be marked with their connection schemes and other
relevant information. A test station schedule shall also be prepared.
Potential test-cum-bond station provided at regular interval as a means to bond, monitor and
control current flow in structures laid in common pipe corridor/trench. These potential test-
For separate control, reference electrode including one standby should be placed on
all the individual pipelines.
High purity copper/ copper sulphate and silver/ silver chloride reference electrodes
shall be used to provide stable potential measurement references.
Such duplicate electrodes shall be provided to guard against reference cell failure
possibilities in an unattended automatic system. Facilities shall be provided to reject
spurious signal during open or short circuiting of monitoring point.
5. FUNCTIONAL GUARANTEE
1. The system shall be guaranteed that the performance/ function of the CP system
installed shall be strictly in accordance with and conforming to the codes specified
and shall perform the specified duties as per following:
2. If the CP expert fails to prove the functional guarantee of the CP system as set forth
in the specification, the Main contractor/JV shall investigate the causes and provide
free of cost to PAEW to rectify/ replace the detects within a reasonable period to
prove the guarantees.
3. If the system fails to prove the guarantee within a reasonable period, PAEW shall have
the option to take over the equipment and rectify the same to fulfil the guarantee and/ or
to make necessary additions to make up the deficiency at the Contractor’s risk and cost.
All expenditure incurred by PAEW in this regard shall be to Contractor’s account
6. DOCUMENTATION
The following minimum design documentation [not essentially limited to these only] shall be
furnished by the CP specialist (for review and approval).