TAKENAKA VIETNAM

HOSHINO PROJECT

PROJECT NAME: HVC BINH DUONG NEW FACTORY


LOCATION: Lot B - 3A7 - CN, MY PHUOC III IPZ, THOI HOA, BEN CAT, BINH DUONG

METHOD OF TESTING & COMMISSIONING


FOR
DRAINAGE SYSTEM
M – TC – 104

APPROVED BY: APPROVED BY: PREPARED BY:

CLIENT TAKENAKA VIETNAM KINDEN VIETNAM

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

TESTING & COMMISSIONING FOR DRAINAGE SYSTEM

CONTENTS:

A. Testing & Commissioning Procedure

B. Testing Equipment

C. Testing & Commissioning Record

C.1 Equipment List

C.2 Flow Test Record

C.3 Drainage Pump Functional and Pump Pit Water Level Record

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

A. TESTING AND COMMISSIONING PROCEDURE

Flow Working Points


 Check the installation of pipe
Check conditon  Check the installation of writing for drainage pump and level lod from
pump panel
 Check the installation of pump and panel
 Check the discharge point
 Rain water pump (RP): Gutter
 Sewage pump (SP-SW), Kitchen drain pump (SP-K): WWTP tank

Power on  Power supply to pump panel by KINDEN <with SHINRYO>


 Check float level
Leak test
Civil
 Check water proof by civil
Water filling to tank
 Check cleaning inside tank

Leak test for tank

 Check items refer to commissioning record


Commissioning for pump

Finish  Continue to commissioning of BMS

 Must finish water stagnant test before flow test


Drainage flow test
 Check the installation of sanitary fixture/ drainage point for tenant/ backyard
drainage
 Use clean small ball (make hole opening)

※ Toilet drainage flow check:


Flow test from farthest closet and service sink in each toilet
(Closet: Sewage water) (Service sink: Waste water)
 Drainage flow test for each sanitary fixture at the same
 Closet
 Urinal
Sanitary fixture numbers Flow test numbers at same
1 1
2~4 2
……… ……..
□ e.g)
Cutomer toilet (M)
Closet: 7 numbers
Urinal: 4 numbers

■ Result: Flow test at the time


For closet: 3 numbers
For urinal: 2 numbers

Finish
Finish

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

B. TESTING EQUIPMENT
NO EQUIPMENT NO. EQUIPMENT
1 Insulation Tester for Pump 2 Voltmeter For Pump

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

C. TEST AND COMMISSIONING RECORD


C.1 Equipment List
Drawing No. Drawing Name
M-PL-01 PLUMBING EQUIPMENT LIST

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

C.2 Flow Test Record

HVC BINH DUONG NEW FACTORY

Photo No. 01

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 1 (Male)

Date: 16/03/2019

Time: 11:15
Contents
Attendance: Mr. Thuy
WC-01

Photo No. 02

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 1 (Male)

Date: 16/03/2019

Time: 11:16
Contents
Attendance: Mr. Thuy
WC-02

Photo No. 03

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 1 (Male)

Date: 16/03/2019

Time: 11:17
Contents Attendance: Mr. Thuy
WC-03

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 04

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 1 (Female)

Date: 16/03/2019

Time: 11:21
Contents
Attendance: Mr. Thuy
WC-01

Photo No. 05

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 1 (Female)

Date: 16/03/2019

Time: 11:22
Contents
Attendance: Mr. Thuy
WC-02

Photo No. 06

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 1 (Female)

Date: 16/03/2019

Time: 11:23
Contents Attendance: Mr. Thuy
WC-03

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 07

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 1 (Female)

Date: 16/03/2019

Time: 11:21
Contents
Attendance: Mr. Thuy
WC-01

Photo No. 08

TOILET DRAINAGE FLOW CHECK

Location: TOILET-1 to MH-21

Date: 16/03/2019

Time: 11:30
Contents
Attendance: Mr. Thuy

Photo No. 09

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 2 (Male)

Date: 20/03/2019

Time: 11:20
Contents Attendance: Mr. Thuy
WC-01

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 10

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 2 (Male)

Date: 20/03/2019

Time: 11:20
Contents
Attendance: Mr. Thuy
WC-02

Photo No. 11

TOILET DRAINAGE FLOW CHECK

Location: TOILET-2 to MH-14

Date: 16/03/2019

Time: 11:30
Contents
Attendance: Mr. Thuy
MH-14

Photo No. 12

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 3 (Male)

Date: 20/03/2019

Time: 11:00
Contents Attendance: Mr. Thuy
WC-01

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 13

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 3 (Male)

Date: 20/03/2019

Time: 11:00
Contents
Attendance: Mr. Thuy
WC-02

Photo No. 14

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 3 (Male)

Date: 20/03/2019

Contents Time: 11:02


WC-03 Attendance: Mr. Thuy

Photo No. 15

TOILET DRAINAGE FLOW CHECK


TOILET – 3 (Male) to
Location:
MH-25
Date: 20/03/2019

Time: 11:02
Contents Attendance: Mr. Thuy

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 16

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 3 (Female)

Date: 20/03/2019

Time: 10:50
Contents
Attendance: Mr. Thuy
WC-01

Photo No. 17

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 3 (Female)

Date: 20/03/2019

Contents Time: 10:50


WC-02 Attendance: Mr. Thuy

Photo No. 18

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 3 (Female)

Date: 20/03/2019

Time: 10:50
Contents
Attendance: Mr. Thuy
WC-03

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 19

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 3 (Female)

Date: 20/03/2019

Time: 10:50
Contents
Attendance: Mr. Thuy
WC-04

Photo No. 20

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 3 (Female)

Date: 20/03/2019

Contents Time: 10:50


WC-05 Attendance: Mr. Thuy

Photo No. 21

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 3 (Female)

Date: 20/03/2019

Time: 10:50
Contents
Attendance: Mr. Thuy
WC-06

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 22

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 3 (Female)

Date: 20/03/2019

Time: 10:50
Contents
Attendance: Mr. Thuy
WC-07

Photo No. 23

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 3 (Female)

Date: 20/03/2019

Time: 10:50
Contents
Attendance: Mr. Thuy
WC-08

Photo No. 24

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 3 (Female)

Date: 20/03/2019

Time: 10:50
Contents
Attendance: Mr. Thuy
WC-09

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 25

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 3 (Female)

Date: 20/03/2019

Time: 11:50
Contents
Attendance: Mr. Thuy
WC-10

Photo No. 26

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 3 to MH-25

Date: 20/03/2019

Time: 11:20
Contents
Attendance: Mr. Thuy
MH-25

Photo No. 27

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 4 (Male)

Date: 20/03/2019

Time: 09:30
Contents
Attendance: Mr. Thuy
WC-1

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 28

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 4 (Male)

Date: 20/03/2019

Time: 09:30
Contents
Attendance: Mr. Thuy
WC-2

Photo No. 29

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 4 (Female)

Date: 20/03/2019

Time: 09:30
Contents
Attendance: Mr. Thuy
WC-1

Photo No. 30

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 4 (Female)

Date: 20/03/2019

Time: 09:30
Contents
Attendance: Mr. Thuy
WC-2

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 31

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 4 (Female)

Date: 20/03/2019

Time: 09:30
Contents
Attendance: Mr. Thuy
WC-3

Photo No. 32

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 4 (Female)

Date: 20/03/2019

Time: 09:30
Contents
Attendance: Mr. Thuy
MH-4

Photo No. 33

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 5 (Female)

Date: 20/03/2019

Time: 10:00
Contents
Attendance: Mr. Thuy
WC-1

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 34

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 5 (Female)

Date: 20/03/2019

Time: 10:00
Contents
Attendance: Mr. Thuy
WC-2

Photo No. 35

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 5 (Female)

Date: 20/03/2019

Time: 10:00
Contents
Attendance: Mr. Thuy
WC-3

Photo No. 36

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 5 (Female)

Date: 20/03/2019

Time: 10:00
Contents
Attendance: Mr. Thuy
WC-4

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 37

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 5 (Female)

Date: 20/03/2019

Time: 10:00
Contents
Attendance: Mr. Thuy
WC-5

Photo No. 38

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 5 (Female)

Date: 20/03/2019

Time: 10:00
Contents
Attendance: Mr. Thuy
MH-6

Photo No. 39

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 5 (Female)

Date: 20/03/2019

Time: 10:00
Contents
Attendance: Mr. Thuy
WC-7

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 40

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 5 (Female)

Date: 20/03/2019

Time: 10:00
Contents
Attendance: Mr. Thuy
WC-8

Photo No. 41

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 5 (Female)

Date: 20/03/2019

Time: 10:00
Contents
Attendance: Mr. Thuy
MH-9

Photo No. 42

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 5 (Female)

Date: 20/03/2019

Time: 10:00
Contents Attendance: Mr. Thuy
WC-10

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 43

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 5 (Female)

Date: 20/03/2019

Time: 10:00
Contents
Attendance: Mr. Thuy
WC-11

Photo No. 44

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 5 (Female)

Date: 20/03/2019

Time: 10:00
Contents
Attendance: Mr. Thuy
MH-12

Photo No. 45

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 5 (Female)

Date: 20/03/2019

Time: 10:00
Contents
Attendance: Mr. Thuy
WC-13

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 46

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 5 (Female)

Date: 20/03/2019

Time: 10:00
Contents
Attendance: Mr. Thuy
WC-14

Photo No. 47

TOILET DRAINAGE FLOW CHECK

Location: TOILET 4,5 to MH-20

Date: 20/03/2019

Time: 10:00
Contents
Attendance: Mr. Thuy
MH-20

Photo No. 48

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Male)

Date: 16/03/2019

Time: 14:40
Contents
Attendance: Mr. Thuy
WC-1

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 49

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Male)

Date: 16/03/2019

Time: 14:40
Contents
Attendance: Mr. Thuy
WC-2

Photo No. 50

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Male)

Date: 16/03/2019

Time: 14:40
Contents
Attendance: Mr. Thuy
WC-3

Photo No. 51

TOILET DRAINAGE FLOW CHECK


TOILET– 6 ( Male ) to
Location:
MH-24
Date: 16/03/2019

Time: 14:50
Contents
MH-24 Attendance: Mr. Thuy

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 52

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
WC-1

Photo No. 53

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
MH-2

Photo No. 54

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
WC-3

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 55

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
WC-4

Photo No. 56

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
MH-5

Photo No. 57

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
WC-6

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 58

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
WC-7

Photo No. 59

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
MH-8

Photo No. 60

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
WC-9

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 61

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
WC-10

Photo No. 62

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
MH-11

Photo No. 63

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents Attendance: Mr. Thuy
WC-12

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 64

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
WC-13

Photo No. 65

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
MH-14

Photo No. 66

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
WC-15

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 67

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
WC-16

Photo No. 68

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
MH-17

Photo No. 69

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
WC-18

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 70

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 6 (Female)

Date: 16/03/2019

Time: 13:45
Contents
Attendance: Mr. Thuy
WC-19

Photo No. 71

TOILET DRAINAGE FLOW CHECK


TOILET – 6 (Female) to
Location:
MH-24
Date: 16/03/2019

Time: 14:30
Contents
MH-24 Attendance: Mr. Thuy

Photo No. 72

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 7 (Male)

Date: 16/03/2019

Time: 15:00
Contents
Attendance: Mr. Thuy
WC-1

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 73

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 7 (Male)

Date: 16/03/2019

Time: 15:00
Contents
Attendance: Mr. Thuy
WC-2

Photo No. 74

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 7 (Female)

Date: 16/03/2019

Time: 14:50
Contents
Attendance: Mr. Thuy
WC-1

Photo No. 75

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 7 (Female)

Date: 16/03/2019

Time: 14:50
Contents
Attendance: Mr. Thuy
WC-2

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 76

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 7 (Female)

Date: 16/03/2019

Time: 14:50
Contents
Attendance: Mr. Thuy
WC-3

Photo No. 77

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 7 (Female)

Date: 16/03/2019

Time: 14:50
Contents
Attendance: Mr. Thuy
MH-4

Photo No. 78

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 7 (Female)

Date: 16/03/2019

Time: 14:50
Contents
Attendance: Mr. Thuy
WC-5

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 79

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 7 (Female)

Date: 16/03/2019

Time: 14:50
Contents
Attendance: Mr. Thuy
WC-6

Photo No. 80

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 7 (Female)

Date: 16/03/2019

Time: 14:50
Contents
Attendance: Mr. Thuy
MH-7

Photo No. 81

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 7 (Female)

Date: 16/03/2019

Time: 14:50
Contents
Attendance: Mr. Thuy
WC-8

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 82

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 7 (Female)

Date: 16/03/2019

Time: 14:50
Contents
Attendance: Mr. Thuy
WC-9

Photo No. 83

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 7 (Female)

Date: 16/03/2019

Time: 14:50
Contents
Attendance: Mr. Thuy
MH-10

Photo No. 84

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 7 (Female)

Date: 16/03/2019

Time: 14:50
Contents
Attendance: Mr. Thuy
WC-11

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

HVC BINH DUONG NEW FACTORY

Photo No. 85

TOILET DRAINAGE FLOW CHECK

Location: TOILET – 7 to MH-15

Date: 16/03/2019

Time: 15:15
Contents
Attendance: Mr. Thuy
MH-15

Photo No.

TOILET DRAINAGE FLOW CHECK

Location:

Date:

Time:
Contents
Attendance:

Photo No.

TOILET DRAINAGE FLOW CHECK

Location:

Date:

Time:
Contents Attendance:

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

DRAWING ATTACHMENT
Drawing No Drawing Name
M-PL-06 WASTE WATER PIPING PLAN

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

C.3 Drainage Pump Functional And Pump Pit Water Level Record

TEST REPORT FOR PUMP No. 01


Project name : HVC BINH DUONG NEW FACTORY Test Date: 10/3/2019
Location Outside Executer : Mr Viet
Drainage Pump Equipment No: DP-1
Equipment
Model No:   50 DVS 5.75 Serial No: SP-8942

Design Capacity: 100 Lit/min x 2 set Pump Head: 10m

Panel name : DP-1  Panel location: On Pump Pit DP-1


CONTROL PANEL RESULT
Rating Measure Good Bad

Voltage 380 V 386V

Pump 1 Current 1.9 A 1.7 A


Electricity
Insulation Over 100MΩ

Voltage 380V 386V

Pump 2 Current 1.9 A 1.6 A


Insulation Over 100MΩ

Low -
Control Pressure switch
High -

Painting OK NG

Damage YES NO

Appearance Abnormal sound YES NO

Abnormal vibration YES NO

Abnormal heat YES NO

Anchor bolt OK NG
Installation
Anti-vibration OK NG

Pump Pit Water Level Record

Water Level: 208mm OK NG

Water Level: 455mm OK NG

Water Level: 608mm OK NG

Water Level: 758mm OK NG

TEST REPORT FOR PUMP No. 02

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

Project name : HVC BINH DUONG NEW FACTORY Test Date: 10/3/2019
Location Outside Executer : Mr Viet
Drainage Pump Equipment No: DP-2
Equipment
Model No:   50 DVS 5.75 Serial No: SP-8942

Design Capacity: 100 Lit/min x 2 set Pump Head: 10m

Panel name : DP-2  Panel location: On Pump Pit DP-2


CONTROL PANEL RESULT
Rating Measure Good Bad

Voltage 380 V 392V

Pump 1 Current 1.9 A 1.85 A


Electricity
Insulation Over 100MΩ

Voltage 380V 392V

Pump 2 Current 1.9 A 1.79 A


Insulation Over 100MΩ

Low -
Control Pressure switch
High -

Painting OK NG

Damage YES NO

Appearance Abnormal sound YES NO

Abnormal vibration YES NO

Abnormal heat YES NO

Anchor bolt OK NG
Installation
Anti-vibration OK NG

Pump Pit Water Level Record

Water Level: 200mm OK NG

Water Level: 600mm OK NG

Water Level: 750mm OK NG

Water Level: 900mm OK NG

TEST REPORT FOR PUMP No. 03


Project name : HVC BINH DUONG NEW FACTORY Test Date: 10/3/2019
Location Outside Executer : Mr Viet

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

Drainage Pump Equipment No: DP-3


Equipment
Model No:   50 DVS 5.75 Serial No: SP-8942

Design Capacity: 100 Lit/min x 2 set Pump Head: 10m

Panel name : DP-3  Panel location: On Pump Pit DP-3


CONTROL PANEL RESULT
Rating Measure Good Bad

Voltage 380 V 387V

Pump 1 Current 1.9 A 1.65 A


Electricity
Insulation Over 100MΩ

Voltage 380V 387V

Pump 2 Current 1.9 A 1.7A


Insulation Over 100MΩ

Low -
Control Pressure switch
High -

Painting OK NG

Damage YES NO

Appearance Abnormal sound YES NO

Abnormal vibration YES NO

Abnormal heat YES NO

Anchor bolt OK NG
Installation
Anti-vibration OK NG

Pump Pit Water Level Record

Water Level: 200mm OK NG

Water Level: 450mm OK NG

Water Level: 600mm OK NG

Water Level: 750mm OK NG

TEST REPORT FOR PUMP No. 04


Project name : HVC BINH DUONG NEW FACTORY Test Date: 10/3/2019
Location Outside Executer : Mr Viet
Equipment Drainage Pump Equipment No: DP-4

PROJECT NAME: HVC BINH DUONG NEW FACTORY


TAKENAKA VIETNAM

Model No:  65 DVS 5.75 Serial No: SP-1982

Design Capacity: 300 Lit/min x 2 set Pump Head: 10m

Panel name : DP-4  Panel location: On Pump Pit DP-4


CONTROL PANEL RESULT
Rating Measure Good Bad

Voltage 380 V 392V

Pump 1 Current 1.9 A 1.67 A


Electricity
Insulation Over 100MΩ

Voltage 380V 392V

Pump 2 Current 1.9 A 1.73 A


Insulation Over 100MΩ

Low -
Control Pressure switch
High -

Painting OK NG

Damage YES NO

Appearance Abnormal sound YES NO

Abnormal vibration YES NO

Abnormal heat YES NO

Anchor bolt OK NG
Installation
Anti-vibration OK NG

Pump Pit Water Level Record

Water Level: 200mm OK NG

Water Level: 640mm OK NG

Water Level: 608mm OK NG

Water Level: 940mm OK NG

DRAWING ATTACHMENT
No. Drawing Name
M-PL-06-3 DETAIL PUMPIT (1),(2),(3),(4)

PROJECT NAME: HVC BINH DUONG NEW FACTORY