Professional Documents
Culture Documents
Occ183 Ag
Occ183 Ag
Government of India
िवद् युत मं ालय
Ministry of Power
उ र े ीय िवद् युत सिमित
Northern Regional Power Committee
चालन सम य उप-सिमित
सिमित की 183वी ं बैठक का आयोजन वीिडयो कॉ िसं ग के मा म से
िदनां क 20.05.2021 को 11:00 बजे से िकया जाये गा I उ बैठक की कायसूची उ र े ीय िवद् यु त्
सिमित की वे बसाइट http://164
164.100.60.165 पर उपल है I
((सौिम मजूमदार)
अधी ण अिभयंता ( चालन)
18-ए,शहीदजीतिसंहमाग, कटवा रयासराय, नईिद ीी- 110016 फोन:011-26513265 ई-मेल: seo-nrpc@nic.inवे बसाईट:
: www.nrpc.gov.in
18-A,
A, ShaheedJeet Singh Marg, KatwariaSarai, New Delhi
Delhi-110016 Phone: 011-26513265 e- mail: seo-nrpc@nic.in Website: www.nrpc.gov.in
ख -क: उ. े.िव.स. Part-A: NRPC
1. Confirmation of Minutes
The minutes of the 182nd OCC meeting which was held on 20.04.2021 through video
conferencing were issued vide letter of even number dated 07.05.2021.
Sub-committee may deliberate and kindly confirm the Minutes.
Haryana Haryana
7000
3000
6000 Energy
Peak 2500
5000 Demand(MW) Requirement
4000 2000 (MU)
3000 1500
2000 1000 Energy
Peak Met(MW)
1000
Availability(
500
MU)
0
0
Apr-21
Apr-21
Rajasthan Rajasthan
1400 900
1200 800
700
1000 Energy
Peak 600
800 500
Requirement(
Demand(MW)
MU)
600 400
300 Energy
400 Peak Met(MW)
200 Availability(M
200 100 U)
0 0
Apr-21 Apr-21
4000 2500
Energy
Peak 2000
3000 Requiremen
Demand(MW)
1500 t(MU)
2000
1000 Energy
1000 Peak
500 Availability(
Met(MW)
0 0 MU)
Apr-21 Apr-21
Delhi Delhi
5000 2234.3
4000 2234.2
Peak 2234.1
Energy
3000 Demand(M Requiremen
W) 2234 t(MU)
2000
Peak 2233.9 Energy
1000 Met(MW) Availability(
2233.8
MU)
0 2233.7
Apr-21 Apr-21
Revised
Availability / Revised Peak
State / UT Energy
Requirement (MW)
(MU)
SLDCs are requested to update the anticipated power supply position of their
respective state / UT for the month of June-2021 and submit the measures
proposed to be taken to bridge the gap between demand & availability, as well to
dispose of the surplus, if any, in the prescribed format.
All the remaining states/UTs viz., Uttarakhand, UTs of J&K and Ladakh and
Chandigarh are again requested to submit the requisite data w.e.f. April 2018 as per
the billed data information in the format given as under:
<Month>
As decided in the 175th OCC meeting, the nominations for matter specific meeting
has been received from HVPN, UHBVN/DHBVN, PSPCL, RVPN (SLDC &
Automation), UPPTCL, KESCO (DISCOM-UP), NPCL (DISCOM-UP).
Meetings on ADMS implementation road map have been held with the officers of
Haryana, Himachal Pradesh and Punjab on 05.02.2021, 19.02.2021 and 05.03.2021
respectively. In these meeting, issues and apprehensions on ADMS were discussed
along with vital aspects like addressing the commercial issues, basic architecture for
scheme and funding possibilities for the scheme.
Members may kindly note.
With nationwide lockdown ordered across the country during Covid-19 pandemic in
2020, the demand and energy consumption was much lower compared to previous
years. This year before the rise of Covid-19 cases till March, the demand across
Northern region was slightly higher compared to previous years. However, due to
increasing covid cases and restrictions imposed by several state governments the
demand across Northern region has remained lower than 2019 from mid-April till first
week of May. In view of above, it once again becomes important that SLDCs interact
with DISCOMS regularly and assess the local conditions and carry out load
forecasting accordingly so that deviations in real-time are minimised.
In line with the above decisions, all utilities are requested to share the
information about transmission elements/ generating units which are expected
to be first time charged in the next 45 days.
In line with section 5.2. (c) of IEGC, list of important grid elements in Northern region
would be compiled by NRLDC shortly. Such elements shall be opened/closed only on
instructions from NRLDC. NRLDC has requested utilities to submit the list of
all elements with details charged under their jurisdiction from 1.4.2020 till date including
those expected to be commissioned till May 2021 so that the same could be included in
the list vide email dated 23rd March 2021.
However, response from most of the utilities is still pending. Last updated document is
available at following link https://nrldc.in/download/nr-important-grid-elements-may-
2020/?wpdmdl=8138.
NRLDC has prepared draft list of important grid elements document of Northern region
2021, circulated vide email dtd. 12.05.2021 to all the constituents and has requested
them to provide any feedback related to inclusion/deletion of elements.
Moreover, on 6th May 2021, it was seen that some of the Northern region states
continued to underdraw from the grid. The need to maintain proper load-generation
balance has been discussed numerous times in OCC meetings. Measures such as
accurate load forecasting, backing down intra-state generation, selling power in real-time
market, surrendering ISGS power timely, avoiding manual opening of feeders in
coordination with DISCOMs have been suggested to SLDCs to minimise the load-
generation mismatch. It is once again requested to all SLDCs to take necessary actions
to minimise these deviations during real-time.
In 181 OCC meeting, it was discussed that telemetry data of the following transmission
elements was not available for a considerable duration on multiple occasions:
The Telemetry data of the above elements was out/suspect, but on enquiry by the real
time engineers it was reported that line/ICT is in service. However, despite repeated
requests data was not made available for considerable time nor exact reason for non-
availability of data was intimated.
On analysis with the relevant supporting data such as SCADA data (eDNA) and energy
meter data, it seems that the following transmission elements have been kept open
without NRLDC coordination/permission which is a gross violation of IEGC.
In 181 OCC meeting, POWERGRID representative informed that the agenda was
included in additional agenda and after receipt of agenda, POWERGRID has asked site
for clarification. After receiving clarification from site, they would share their views with
NRLDC/ NRPC and OCC forum.
As discussed in last OCC meeting, all SLDCs need to furnish ATC/TTC details of
their control area at respective SLDC websites. However, it is being observed that
only SLDCs of Haryana, UP, Punjab, Delhi (real-time violation) are uploading
ATC/TTC limits on their websites. To assist SLDCs in ATC/TTC assessment, NRLDC
has also been carrying out interactions over video-conference with SLDCs. All
SLDCs are requested to share basecase as well as ATC/TTC assessment with
NRLDC/NRPC on monthly basis as well as upload ATC/TTC limits on their websites.
J&K and Ladakh U/Ts, Uttarakhand and HP representatives are once again asked to
advise the concerned officers to evaluate their ATC/TTC limits in coordination with
NRLDC and share latest assessment in OCC meeting.
Members may like to discuss.
400 KV Koldam(NT)-Ludhiana(PG)
5 3 NTPC/POWERGRID
(PKTCL) Ckt-2
400 KV Meerut(PG)-Muzaffarnagar(UP)
6 3 UP
(PG) Ckt-1
220 KV
7 SingoliBhatwari(Singoli(LTUHP))- 6 Uttarakhand
Srinagar(UK) (PTCUL) Ckt-2
18. Multiple element tripping events in Northern region in the month of Apr’21:
A total of 18 grid events occurred in the month of Apr’21 of which8 are of GD-1
category. The preliminary report of all the events have been issued from NRLDC. A
list of all these events along with the status of details received by 05-May-2021 is
attached at Annexure-B.IV.
Maximum Fault Duration is 680ms in the event of multiple element tripping at 400 kV
Jaisalmer (Raj)on 28-Apr-21 at 18:32hrs.
Delayed clearance of fault (more than 100ms for 400kV and 160ms for 220kV
system) observed in total 4 events out of 18 grid events occurred in the month. In
2number of events, fault didn’t capture through PMU data.
19. Details of tripping of Inter-Regional lines from Northern Region for Apr’21:
A total of 5 inter-regional lines tripping occurred in the month of Apr’21. The list is
attached at Annexure-B.V. Out of 5 number of trippings, 2 tripping incidents is
related to HVDC system. The status of receipt of preliminary reports, DR/EL within
24hrs of the event and fault clearing time as per PMU data has also been mentioned
in the table. The non-receipt of DR/EL & preliminary report within 24hrs of the event
is in violation of various regulations. As per regulations, all the utilities shall furnish
the DR/EL, flag details & preliminary report to RLDC/RPC within 24hrs of the event.
They shall also furnish the detailed investigation report within 7 days of the event if
fault clearance time is higher than mandated by CEA (Grid Standard) Regulations.
Members may please note and advise the concerned for taking corrective action to
avoid such trippings as well as timely submission of the information.
20. Status of DR/EL and tripping report of utilities for the month of Apr-2021.
The status of receipt of DR/EL and tripping report of utilities for the month of Apr 2021
is attached at Annexure-B.VI. It is to be noted that as per the IEGC provision under
clause 5.2 (r), detailed tripping report along with DR & EL has to be furnished within
24 hrs of the occurrence of the event.However, it is evident from the submitted data
that reporting status is not satisfactory and needs improvement. Also it is observed
that reporting status has been improved from CPCC2, HP, Rajasthan and UP in April,
2021 compared to the previous month.
Members may please note and advise the concerned for timely submission of the
information. It is requested that DR/EL of all the trippings shall be uploaded onWeb
Based Tripping Monitoring System “http://103.7.128.184/Account/Login.aspx”
within 24 hours of the events as per IEGC clause 5.2.r and clause 15.3 of CEA grid
standard.
Starting End
S. Event Time
Event Description Frequency Frequency Δf
No. Date (in hrs.)
(in Hz) (in Hz)
08- As reported, On 8th April, 230 kV
1 Apr- 03:31hrs TTPS-TTN AUTO-1 and 230 kV 49.99 49.95 -0.04
21 TTPS_STERLITE tripped at 03:29
The Hon’ble CERC approved procedure has already been shared with all concerned
during previous OCC meetings. FRC observed for each state control area for the
events is tabulated below:
In line with the decisions taken during various OCC meetings, the time and date of
the FRC events were e-mailed
mailed to respective utilities.. Constituents may submit the
FRC of their control areas for the above event and reason of poor response, if
observed.
FRC information has been received from AD Hydro, NHPC, SJVN, Singrauli (NTPC),
Rosa TPS, UP, Punjab and Rajasthan cocontrol
ntrol area for the aforementioned event.
Other utilities are also requested to kindly share the FRC calculations and further
action taken at their end.
Power System Stabilizer is an important part for damping of inter area and local
mode of oscillations in the grid. As we all know, Indian electricity grid is continuously
expanding and lots of Power Electronics devices were also commissioned in recent
years changing the dynamics of grid. PSS tuning /re/re-tuning
tuning is required
require for damping of
oscillations.
In this regard one committee at NRPC level was formed in year 2014 and it was
agreed that If results of Step Response Test indicate sufficient damping, generating
company would perform next Step Test after three year or at th the time of major
overhauling of the machine, whichever will be earlier and Generating Companies
would arrange for re-tuning
tuning of PSS, if Step Response Test indicates insufficient
damping or oscillations.
Status report in above format updated till 10th May 2021 is attached as Annexure-
B.VII
It is once again requested to all the members to submit the report of PSS tuning/ re-
tuning/ Step Response Test through email to NRPC and NRLDC at seo-nrpc@nic.in
and nrldcso2@gmail.com respectively.
Member may also update about the future plan for PSS tuning.
Two frequent events of Bus bar protection at 400kV Jhakri substation occurred on
29th April, 2021 & 04th May, 2021.
CHANDIGARH Sep-2019
◎ DELHI Feb-2021
Progress of Information regarding ◎ HARYANA Feb-2021
installing new installation of new capacitors ◎ HP Mar-2021
2 capacitors and and repair of defective ◎ J&K and LADAKH Not Available
repair of defective capacitors is to be submitted to ◎ PUNJAB Nov-2020
capacitors NRPC Secretariat. ◎ RAJASTHAN Mar-2021
◎ UP Dec-2020
◎ UTTARAKHAND Feb-2021
All States/UTs are requested to
furnish updated status on monthly
basis.
Power transformers at APRL, Kawai, Chhabra, Kalisindh and ICTs at Anta are experiencing
abnormal humming since 1600 hrs of 21st April’21.
Sudden change in the humming was observed from all three single-phase Generator
Transformers at APML, Kawai since 16:00 hrs on 21st April; when the unit#1 was running at
rated load (660MWs). Humming mitigated only with decrease in load (from 660 Mw to 590 Mw).
After synchronizing the other unit, associated GT also similar magnetostriction behavior.
It was observed that there was absence of any noticeable phase unbalance or harmonics in
stator currents or voltages.
SLDC, RVPNL attempted switching off one of the ICTs at Anta end opening of 400kV Chhabra-
Anta lines 1&2; without any benefit.
Increased humming—in the tune of 80-85 dB instead (of less than 60 dB earlier)—possibly
caused by superimposed small signal frequencies is impacting not only GT’s at APML, Kawai;
our all Power transformers in the complex.
Abnormal humming serious concern and need to be addressed at the earliest to prevent
potential damage to GTs and ICTs in the complex.
Immediate help and guidance in arresting the problem is sought from the forum.
SMALL SIGNALS OSCILLATIONS AT KAWAI
Generator Current
2. Kawai Unit#1 disturbance records, DR2-26.04.2021 18:15:20 hrs
Generator Voltage
Generator Current
3. Kawai Unit#1 disturbance records DR2-27.04.2021 08:25:23 hrs
Generator Voltage
Generator Current
4. Mundra Unit#8 disturbance trigger DR2-27.04.2021 11:40:47 hrs
Generator Voltage
Generator Current
Annexure-A.III
AGENDA of POWERGRID-NR-III for 183 OCC Meeting
They added that Pole-I is having same capacity and comparatively free from such constraints and
proposed for operation of pole-I instead of pole-II till the time the RoW issue gets resolved.
After detailed deliberation and analysis of the facts OCC felt that there is severe ROW issue in the
span of 1293-1294 which is beyond the control of licensee and advised Powergrid to be in continuous
touch with the District Authorities to resolve the issue.
Further, OCC opined that till the resolution of ROW issues, Pole-1 may be frequently used upto its
optimum limits as the clearance of Pole-1 is better to avoid the unnecessary trippings of Pole-2 and
requested ERLDC to take up the issue with NLDC for un-interrupted and reliable pole operation of
HVDC BNC-Agra. Further OCC felt that the operation of HVDC BNC-Agra is being looked/controlled by
NRPC/ NLDC the operational and availability issues may be placed before NRPC/NLDC for final
resolution.”
The Detail of tripping/restarting of 800 KV HVDC AGRA-BNC Line P-2 are as follows: -
Based on the above it is evident that fault location is at same distance and falls
between span 1293-1294 and fault is caused by underlying eucalyptus trees.
Cutting/lopping of these trees are still pending due to stiff resistance from local
villagers, which has already been accepted in 178 OCC, meeting by ERPC.
Date:30.04.2021
Eastern Regional Power Committee
14, Golf Club Road, Tollygunge
Kolkata:700033
Members noted.
In recent past HVDC (BNC-Agra) Pole restarting/tripping observed and details of line tripping’s are
as per the following: -
Based on the above relay indications Line Patrolling Team carry out necessary checking and found
that flash-over has occurred in between span 1293-1294 due to underlying eucalyptus trees.
However, even after identifying all the problems, subject trees could not be accessed due to stiff
resistance (severe ROW) from local villagers.
The villager’s forcefully stopped POWERGRID Line Maintenance staffs to enter in the corridor in
span-1293-1294. Considering the seriousness of the issue, letter have been issued to DM,
Jalpaiguri with copy to SP, Jalpaiguri seeking administrative support in order to remove the trees
under the line corridor.
2
Our officials along with T&P’s were continuously trying to enter in the corridor of span 1293-1294
for tree cutting but due to severe resistance of local villagers they could not enter in the corridor till
date. Our officials also approached to District Magistrate Jalpaiguri, SDO Jalpaiguri, BDO
Dhupguri, OC Dhupguri (local Thana) for administrative help but due to “West Bengal Assembly
Election” they suggested that serious Law & Order crisis may evolve if any action is taken at
present.
In this regard it is to mention that since commissioning of the line, line patrolling/maintenance work
from Tower No.-1292 to Tower No.-1295 under Altagram village, P.S-Dhupguri, Dist.-Jalpaiguri
were severely obstructed/resisted by villagers. Copy of previous mail communications & letter
enclosed for reference. The severe ROW problem in that village have been time to time reported
to all concerned district administration officials but in spite of several meetings, the problem could
not be resolved till date.
At present due to ongoing election activity, it is really beyond control of POWERGRID for clearing
the ROW until strong administrative support from district authority. As already assured by district
authority, the matter will be taken up after completion of election activity (By mid-way of May-21).
1. As per design, each POLE between BNC to Agra is capable of carrying 1500 MW through
Pole-I & II individually. Presently it has been observed that most of the time power flow direction
are from NR to NER with maximum 500 MW load flow. Details of synopsis of power flow are given
below: -
3
Deliberation in the meeting
Powergrid representative explained the issue and informed that as per the present status the tree
cutting in the line span of 1293-1294 could not be carried out due to RoW issue which leads to
several flashover of Pole-2 of HVDC line. The same can be carried out only after getting
administrative support from district authority after the completion of assembly election in West
Bengal.
They added that Pole-I is having same capacity and comparatively free from such constraints and
proposed for operation of pole-I instead of pole-II till the time the RoW issue gets resolved.
After detailed deliberation and analysis of the facts OCC felt that there is severe ROW issue in the
span of 1293-1294 which is beyond the control of licensee and advised Powergrid to be in
continuous touch with the District Authorities to resolve the issue.
Further, OCC opined that till the resolution of ROW issues, Pole-1 may be frequently used upto its
optimum limits as the clearance of Pole-1 is better to avoid the unnecessary trippings of Pole-2
and requested ERLDC to take up the issue with NLDC for un-interrupted and reliable pole
operation of HVDC BNC-Agra.
Further OCC felt that the operation of HVDC BNC-Agra is being looked/controlled by NRPC/ NLDC
the operational and availability issues may be placed before NRPC/NLDC for final resolution.
4
Annexure-A.IV
Agenda;
Deemed availability of outage of Transmission lines for installation of Bird Diverter as per
requirement of NGT.
NGT vide order dt 23/12/2020 has directed to install bird diverters in transmission lines passing
through the GIB ( Great Indian Bustard area) within a period of 1-3 years. Point 4.2 of the
recommendation of the said order is produced below:-
Quote
“Mitigate all power transmission lines passing through priority bustard habitats identified by WII
(Please refer Annexure 10) by undergrounding cables (where technically/ technologically feasible) or
installing bird diverters to make them prominent to birds. The priority areas where this intervention is
required has been mapped by the Wildlife Institute of India and a technical-cum-financial proposal
has been submitted to RVPNL for necessary approvals from Rajasthan Energy Department for
mitigation. This action must be expeditiously implemented in the short-term (1-3 years), as power-line
mortality is currently the biggest threat to the species.”
Unquote
The same was again directed by honourable Supreme Court vide this order dt. 19/04/2021.
Accordingly, POWERGRID is planning to install bird diverters, in a phased manner, on the
transmission lines passing through GIS area / potential area. In 1st phase following lines are
considered for installation of bird diverters:-
i) 765KV Ajmer – Bikaner
ii) 765KV Bikaner – Moga
iii) 765KV Bhadla – Bikaner
iv) 765KV Banaskantha – Chittorgarh
v) 765KV Jhatikara – Kanpur
vi) 400KV LILO of Bikaner (RRVPNL) – Bhadla (RRVPNL) at Bhadla
vii) 400KV Bhadla (POWERGRID) – Bhadla (RRVPNL)
viii) 400KV Ajmer – Ajmer
ix) 400KV Agra – Bhiwadi
Since Installation of Bird diverters cannot be done without line shutdown, hence, such planned
outage of transmission lines, availed by POWERGRID for installation of bird diverters, shall be
considered as deemed available.
Members may discuss and approve.
Annexure-B.I
Annexure-B.II
11.05.2021
Connectivity Diagram Evacuation Lines
Evacuation Lines
Basecase Assumptions
• All India Aug’2021 Peak basecase considered
• Peak hydro i.e. 110% capacity considered
• Punjab Load: 10.7GW
• Haryana Load: 9.5GW
• HP Load: 1.35GW
• Total NR Load: 62.8GW
Existing SPS in complex: After Gumma revision
Case Contingency Action
Trip 1 unit of Karcham HPS, 1 unit of Jhakri
Case-1 Load on any of the lines at Jhakri, Rampur or Gumma
HPS, 1unit of Rampur HPS Trip and 1 unit of
towards Nalagarh or Panchkula exceeds 850 MW
Sawra-Kuddu HPS
Case-2 400 kV bus voltage at Karcham drops below 395 kV Trip 2 units of Karcham HPS
Power Flow of any outgoing line of Rampur or Jhakri or Initiate the Alarm to the operators at Jhakri,
Case-5
Gumma Substation exceed by 800MW Rampur &Karcham and Sawra Kuddu HEP
In case 6, only two triple snowbird lines are available for power evacuation. Assuming S/D or
tripping (N-1 contingency of one of the ckts), the safe power allowed is 2 units at Karcham, 3
units at Baspa and 2 units at Sorang i.e. Existing SPS.
Loadings for present scenario
Loadings after LILO at Sorang
Case-6: 400 kV Kala Amb (PG)-
Abdullapur D/C tripped
Safe loading
Observations:
• The major issue seems to be disruption of
Karcham Wangtoo- Wangtoo(HP)-Sorang-Kala
Amb- Abdullapur link i.e. Outage of this double
circuit path.
Outage Preliminary Report receipt status DR/EL receipt status Detailed Report receipt status
Fault
Name of Elements Event Generation Load Category as per Energy Unserved (in
S.No. Region Owner/ Agency Clearance
(Tripped/Manually opened) (As reported) Loss(MW) Loss(MW) CEA Grid Standards MU)
time (in ms)
Date Time within 24hrs after 24hrs Not Received within 24hrs after 24hrs Not Received Received Not Received
As reported, 400 KV Bamnoli(DV)-Tughlakabad(PG) (DTL) Ckt-1 and Ckt-2 both successfully auto-reclosed on B-N & R-N phase
to earth fault respectively and later both line tripped after 3sec on same faults. As per PMU, B-N phase to earth fault observed
1) 400 KV Bamnoli(DV)-Tughlakabad(PG) (DTL) Ckt-1 Y(DTL) Y(DTL) Y(DTL)
1 NR DTL 1-Apr-21 12:20 on 400 KV Bamnoli(DV)-Tughlakabad(PG) (DTL) Ckt-1 and R-N phase to earth fault observed on 400 KV Bamnoli(DV)- 0 0 GI-2 0 80
2) 400 KV Bamnoli(DV)-Tughlakabad(PG) (DTL) Ckt-2 Y(PG) Y(PG) Y(PG)
Tughlakabad(PG) (DTL) Ckt-2. In antecedent condition, 400 KV Bamnoli(DV)-Tughlakabad(PG) (DTL) Ckt-1 and Ckt-2 carrying
approx. 20MW each.
As reported, 400 KV Jaisalmer-Barmer (RS) Ckt-1 tripped on B-N phase to earth fault. Fault distance was 14.53km and fault
1) 400 KV Barmer(RS)-Rajwest(RW) (RS) Ckt-1 current was 7.269kA from Barmer end. At the same time, 400 KV Barmer(RS)-Rajwest(RW) (RS) Ckt-1 also tripped. As per PMU,
2 NR RRVPNL 2-Apr-21 14:17 0 0 GI-2 0 Y(Raj) Y(Raj) Y(Raj) 440
2) 400 KV Jaisalmer-Barmer (RS) Ckt-1 B-N phase to earth fault with delayed clearance of 440ms is observed. In antecedent condition, 400 KV Jaisalmer-Barmer (RS)
Ckt-1 & 400 KV Barmer(RS)-Rajwest(RW) (RS) Ckt-1 carrying 147MW & 216MW respectively.
As reported, 220 KV Bairasiul(NH)-Jessore(HP) (PG) Ckt-1 & 220 KV Bairasiul(NH)-Pong(BB) (PG) Ckt-1 tripped on Over Voltage.
As per PMU, B-N followed by multiple phase to earth faults in R phase is observed. As per SCADA, Bus-1 & Bus-2 voltage
1) 220 KV Bairasiul(NH)-Jessore(HP) (PG) Ckt-1
3 NR POWERGRID 6-Apr-21 23:35 observed as 239kV and 241kV. At the same time, 60MW Unit-1 & Unit-2 of Bairasiul(NH) also tripped. In antecedent condition, 120 0 GD-1 0.84 Y(HP) Y(BBMB) Y(NHPC) Y(NHPC) Y(NHPC) 80
2) 220 KV Bairasiul(NH)-Pong(BB) (PG) Ckt-1
220 KV Bairasiul(NH)-Jessore(HP) (PG) Ckt-1 & 220 KV Bairasiul(NH)-Pong(BB) (PG) Ckt-1, 60MW Unit-1 & Unit-2 of
Bairasiul(NH) carrying 73MW, 46MW, 61MW & 61MW respectively.
As reported, 400 KV Azamgarh-Mau (UP) Ckt-1 tripped on Y-N phase to earth fault. Fault occurred due to damage of Y phase
LA of 400 KV Azamgarh-Mau (UP) Ckt-1. Fault distance was 0.2km from Azamgarh end and 42.14km from Mau end. At the
1) 400 KV Azamgarh-Mau (UP) Ckt-1
6 NR UPPTCL 15-Apr-21 22:48 same time 400 KV Tanda(NT)-Azamgarh(UP) (UP) Ckt-1 also tripped. As per PMU, Y-N phase to earth fault with unsuccessful 0 0 GI-2 0 Y(UP) Y(NTPC) Y(UP) Y(NTPC) Y(UP) 80
2) 400 KV Tanda(NT)-Azamgarh(UP) (UP) Ckt-1
autoreclosing observed. In antecedent condition, 400 KV Azamgarh-Mau (UP) Ckt-1 and 400 KV Tanda(NT)-Azamgarh(UP) (UP)
Ckt-1 carrying 313MW & 71MW respectively.
As reported, 400 KV CLP Jhajjar(CLP)-Dhanoda(HV) (HVPNL) Ckt-1 tripped on DT received from Dhanoda(HV) end followed by
1) 400 KV CLP Jhajjar(CLP)-Dhanoda(HV) (HVPNL) Ckt-1 tripping of 660 MW Jhajjar(CLP) - UNIT 1. At the same time, 400 KV Deepalpur(JHKT)-Kabulpur(HV) (HVPNL) Ckt-1 also tripped.
7 NR 2) 660 MW Jhajjar(CLP) - UNIT 1 HVPNL 16-Apr-21 15:11 As per PMU, B-N phase to earth fault is observed. As per SCADA, load loss of approx. 360MW and generation loss of approx. 390 360 GD-1 1.08 Y(Har) Y(Har) Y(Har) 80
3) 400 KV Deepalpur(JHKT)-Kabulpur(HV) (HVPNL) Ckt-1 390MW is observed. In antecedent condition, 400 KV CLP Jhajjar(CLP)-Dhanoda(HV) (HVPNL) Ckt-1 and 400 KV
Deepalpur(JHKT)-Kabulpur(HV) (HVPNL) Ckt-1 carrying 314MW & 156MW respectively.
As reported, 400 KV Alaknanda GVK(UPC)-Vishnuprayag(JP) (UP) Ckt-1 & 400 KV Muzaffarnagar(UP)-Vishnuprayag(JP) (UP) Ckt-
1) 400 KV Muzaffarnagar(UP)-Vishnuprayag(JP) (UP) Ckt-1
8 NR UPPTCL 16-Apr-21 16:43 1 both tripped on Bus Bar protection operated at Vishnuprayag end due to B-N phase to earth fault. Lines tripped from 0 0 GI-2 0 Y(UP) Y(UP) Y(UP) 80
2) 400 KV Alaknanda GVK(UPC)-Vishnuprayag(JP) (UP) Ckt-1
remote end on DT received. As per PMU, B-N phase to earth fault is observed.
1) 400/220 kV 315 MVA ICT 1 at Srinagar(UK) As reported, 220 KV Singoli Bhatwari(Singoli(LTUHP))-Srinagar(UK) (PTCUL) Ckt-1 & Ckt-2 both tripped on B-R line to line fault.
9 NR 2) 220 KV Singoli Bhatwari(Singoli(LTUHP))-Srinagar(UK) (PTCUL) Ckt-2 PTCUL 17-Apr-21 15:33 At the same time, 400/220 kV 315 MVA ICT 1 at Srinagar(UK) also tripped on three phase fault. As per PMU, B-R line to line 0 0 GI-2 0 Y(Utt) Y(Utt) Y(Utt) 80
3) 220 KV Singoli Bhatwari(Singoli(LTUHP))-Srinagar(UK) (PTCUL) Ckt-1 fault is observed.
As reported, 220 KV Khodri(UK)-Majri(HP) (UK) Ckt-1 & Ckt-2 both tripped from Khodri end on Bus Bar protection operated at
1) 220 KV Khodri(UK)-Majri(HP) (UK) Ckt-1 Khodri end (Bus 2) due to thunderstorm during inclement weather. As per PMU, no fault is observed. As per SCADA, load loss
10 NR PTCUL 20-Apr-21 14:30 0 150 GD-1 0.12 Y(HP) Y(Utt) Y(Utt) Y(HP) Y(Utt) NA
2) 220 KV Khodri(UK)-Majri(HP) (UK) Ckt-2 of approx. 150MW is observed. In antecedent condition, 220 KV Khodri(UK)-Majri(HP) (UK) Ckt-1 & Ckt-2 carrying 77MW &
73MW respectively.
As reported, 400kKV Bareilly(UP)-Bareilly(PG) (PG) Ckt-1 & Ckt-2 both tripped on Y-B line to line fault. Fault current was 26kA
1) 400 KV Bareilly(UP)-Bareilly(PG) (PG) Ckt-1 Y(UP) Y(UP)
11 NR POWERGRID, UPPTCL 21-Apr-21 16:46 at Bareilly(PG) end. As per PMU, Y-B line to line fault with delayed clearance of 380ms is observed. In antecedent condition, 0 0 GI-2 0 Y(UP) Y(PG) 360
2) 400 KV Bareilly(UP)-Bareilly(PG) (PG) Ckt-2 Y(PG) Y(PG)
400 kV Bareilly(UP)-Bareilly(PG) (PG) Ckt-1 & Ckt-2 carrying aprrox. 50MW each.
As reported, 400 KV Gorakhpur(PG)-Gorakhpur(UP) (PG) Ckt-1 tripped on Y-B fault, Fault Current was lb 5.87kA & Ic 5.804kA,
1) 400 KV Gorakhpur(PG)-Gorakhpur(UP) (PG) Ckt-1
Distance was 1.224km from Gorakhpur(UP). At the same time, 220 KV Gorakhpur(PG)-Gorakhpur_2(UP) (UP) Ckt-1, 400/220 kV
2) 220 KV Gorakhpur(PG)-Gorakhpur_2(UP) (UP) Ckt-1
12 NR POWERGRID, UPPTCL 22-Apr-21 02:52 315 MVA ICT 2 & ICT 3 at Gorakhpur(UP) all tripped on Bus Bar protection (Bus 1). As per PMU, Y-B phase to phase fault is 0 0 GI-2 0 Y(UP) Y(PG) Y(UP) Y(PG) Y(UP) 80
3) 400/220 kV 240 MVA ICT 3 at Gorakhpur(UP)
observed. In antecedent condition, 400 KV Gorakhpur(PG)-Gorakhpur(UP) (PG) Ckt-1, 400/220 kV 315 MVA ICT 2 & ICT 3 at
4) 400/220 kV 315 MVA ICT 2 at Gorakhpur(UP)
Gorakhpur(UP) carrying 92MW, 110MW & 80MW respectively.
As reported, 220 KV AD hydro(AD)-Nallagarh(PG) (ADHPL) Ckt-1 tripped on B-N phase to earth fault. Fault distance was 76.2km
from AD Hydro end & 79.28km from Nallagarh end. At the same time, 220 KV AD hydro(AD)-Phozal(HP) (ADHPL) Ckt-1 also
1) 220 KV AD hydro(AD)-Phozal(HP) (ADHPL) Ckt-1 Y(AD Hydro) Y(AD Hydro)
13 NR ADHPL 22-Apr-21 23:02 tripped due to under voltage. Under voltage occurred because 220 KV Phozal(HP)-Nallagarh(PG) (ADHPL) Ckt-1 was already 0 0 GI-1 0 Y(HP) Y(HP) Y(AD Hydro) 80
2) 220 KV AD hydro(AD)-Nallagarh(PG) (ADHPL) Ckt-1 Y(PG) Y(PG)
under forced outage. As per PMU, B-N phase to earth fault is observed. In antecedent condition, 220 KV AD hydro(AD)-
Nallagarh(PG) (ADHPL) Ckt-1 & 220 KV AD hydro(AD)-Phozal(HP) (ADHPL) Ckt-1 carrying approx. 18MW each.
1) 400 KV Noida Sec 148-Noida Sec 123 (UP) Ckt-1 As reported, 400 KV Noida Sec 148-Noida Sec 123 (UP) Ckt-1 & Ckt-2, 400 KV Gr.Noida_2(UPC)-Noida Sec 148 (UP) CKt-1 & Ckt-
2) 400KV Bus 2 at Noida Sec 148(UP) 2, and 400/220 kV 500 MVA ICT 1 at Noida Sec 148(UP) all tripped on Bus bar protection operation at Noida Sec 148(UP).
3) 400KV Bus 1 at Noida Sec 148(UP) There was problem in both DC source 1 & 2. During the rectification of DC earth fault, both DC source were switched off
14 NR 4) 400 KV Noida Sec 148-Noida Sec 123 (UP) Ckt-2 UPPTCL 26-Apr-21 14:17 simultaneously by mistake which resulted into Bus Bar trip command to both bus and all 400kV elements got tripped. DC 0 0 GI-2 0 Y(UP) Y(UP) Y(UP) NA
5) 400 KV Gr.Noida_2(UPC)-Noida Sec 148 (UP) Ckt-2 earth fault found in RTCC panel of 500 MVA T/F. As per PMU, no fault is observed. As per SCADA, no load loss was observed as
6) 400 KV Gr.Noida_2(UPC)-Noida Sec 148 (UP) Ckt-1 load was fed from 220kV Bus through 220 KV sec-148- RC green and 220 KV sector 148 - 129 line. In antecedent condition,
7) 400/220 kV 500 MVA ICT 1 at Noida Sec 148(UP) 400/220 kV 500 MVA ICT 1 at Noida Sec 148(UP) carrying 207MW.
As reported, 400 KV Kankani-Jaisalmer (RS) Ckt-2 tripped on Y-N phase to earth fault, fault distance: 107.5km from Kankani
end and 38.9km from Jaisalmer end. At the same time, 400 KV Akal-Jaisalmer (RS) Ckt-1 and 400 KV Jaisalmer-Barmer (RS) Ckt-
1) 400 KV Jaisalmer-Barmer (RS) Ckt-2
2 both tripped in Z-2 from remote end only. As per PMU, Y-N phase to earth fault with delayed clearance of 680ms is
15 NR 2) 400 KV Akal-Jaisalmer (RS) Ckt-1 RRVPNL 28-Apr-21 18:32 0 0 GI-2 0 Y(Raj) Y(Raj) Y(Raj) 680
observed. As per SOE, line didn't trip from Jaisalmer end and later fault cleared in Z-2 tripping of 400 KV Akal-Jaisalmer (RS) Ckt-
3) 400 KV Kankani-Jaisalmer (RS) Ckt-2
1 and 400 KV Jaisalmer-Barmer (RS) Ckt-2 from remote end only. In antecedent condition, 400 KV Kankani-Jaisalmer (RS) Ckt-2,
400 KV Akal-Jaisalmer (RS) Ckt-1 and 400 KV Jaisalmer-Barmer (RS) Ckt-2 carrying 53MW, 46MW and 19MW respectively.
Outage Preliminary Report receipt status DR/EL receipt status Detailed Report receipt status
Fault
Name of Elements Event Generation Load Category as per Energy Unserved (in
S.No. Region Owner/ Agency Clearance
(Tripped/Manually opened) (As reported) Loss(MW) Loss(MW) CEA Grid Standards MU)
time (in ms)
Date Time within 24hrs after 24hrs Not Received within 24hrs after 24hrs Not Received Received Not Received
As reported, 400 KV Nathpa Jhakri(SJ)-Karcham Wangtoo(JSW) (HBPCL) Ckt-1, 400kV Nathpha Jhakri-Gumma Ckt-1, 400 KV
1) 400KV Bus 3 at Nathpa Jhakri(SJ)
Nathpa Jhakri(SJ)-Rampur HEP(SJ) (PG) Ckt-1 and 250MW Unit1 at Nathpa Jhakri(SJ) all tripped on bus bar protection
2) 400KV Bus 1 at Nathpa Jhakri(SJ)
operation of bus 1 & bus 3. Bus bar operated because Bus Bar-1 compartment of N. Jhakri-Karcham Wangtoo-2 had some Y(SJVNL) Y(SJVNL)
3) 400 KV Nathpa Jhakri(SJ)-Karcham Wangtoo(JSW) (HBPCL) Ckt-1
17 NR JSW, POWERGRID, SJVNL 29-Apr-21 02:15 issue with the dielectric strength of SF-G gas. As per PMU, R-N phase to earth fault is observed. As per SCADA, generation loss 60 0 GD-1 0.22 Y(PG) Y(JSW) Y(PG) Y(JSW) Y(SJVNL) 80
4) 400 KV Nathpa Jhakri(SJ)-Rampur HEP(SJ) (PG) Ckt-1
of approx. 60MW is observed at Nathpa Jhakri HEP. In antecedent condition, 400 KV Nathpa Jhakri(SJ)-Karcham Wangtoo(JSW)
5) 400/22 kV 25 MVA ST 1 at Nathpa Jhakri(SJ)
(HBPCL) Ckt-1, 400kV Nathpha Jhakri-Gumma Ckt-1 and 400 KV Nathpa Jhakri(SJ)-Rampur HEP(SJ) (PG) Ckt-1 all carrying
6) 400 KV Nathpa Jhakri(SJ)-Panchkula(PG) (PG) Ckt-1
47MW, 20MW & 120MW respectively.
1) 220 KV Gurgaon(PG)-GurgaonSec72(HV) (HVPNL) Ckt-2 As reported, 220 KV Gurgaon(PG)-GurgaonSec72(HV) (HVPNL) Ckt-1, Ckt-2, Ckt-2 & Ckt-4 all tripped on Bus bar protection
2) 220 KV Gurgaon(PG)-GurgaonSec72(HV) (HVPNL) Ckt-3 operated at 220kV GurgaonSec72(HV). As per PMU, R-N phase to earth fault followed by Y-N phase to earth fault is observed. Y(Har) Y(Har)
18 NR HVPNL 30-Apr-21 23:55 0 190 GD-1 0.14 Y(Har) Y(PG) 120
3) 220 KV Gurgaon(PG)-GurgaonSec72(HV) (HVPNL) Ckt-4 As per SCADA, load loss of approx. 190MW is observed in Haryana region. In antecedent condition, 220 KV Gurgaon(PG)- Y(PG) Y(PG)
4) 220 KV Gurgaon(PG)-GurgaonSec72(HV) (HVPNL) Ckt-1 GurgaonSec72(HV) (HVPNL) Ckt-1, Ckt-2, Ckt-2 & Ckt-4 carrying 102MW, 79MW, 104MW & 131MW respectively.
Northern Regional inter regional lines tripping for Mar-21 Annexure-B.V
# Fault Clearance time has been computed using PMU Data from nearest node available and/or DR provided by respective utilities ( Annexure- II)
*Yes, if written Preliminary report furnished by constituent(s)
R-Y-B phase sequencing (Red, Yellow, Blue) is used in the list content.All information is as per Northern Region unless specified.
^^ tripping seems to be in order as per PMU data, reported information. However, further details may be awaited.
Reporting of Violation of Regulation for various issues for above tripping
Fault Clearance time(>100ms for 400kV
1 1. CEA Grid Standard-3.e 2. CEA Transmission Planning Criteria
and >160ms for 220kV)
2 DR/EL Not provided in 24hrs 1. IEGC 5.2(r) 2. CEA Grid Standard 15.3
3 FIR Not Furnished 1. IEGC 5.9.6.a 2. CEA Grid Standard 12.2 (Applicable for SLDC, ALDC only)
4 Protection System Mal/Non Operation 1. CEA Technical Standard of Electrical Plants and Electric Lines: 43.4.A 2. CEA (Technical Standards for connectivity to the Grid) Regulation, 2007: Schedule Part 1.
5 A/R non operation 1. CEA Technical Standard of Electrical Plants and Electric Lines: 43.4.C 2. CEA Technical Planning Criteria
Annexure-B.VI
1st April 2021 - 30st April 2021
Disturbance Event
Tripping
S. No. First Information Disturbance Recorder Disturbance Event Logger Logger (NA) Event Logger Tripping Tripping
Report (NA)
Report (Not Recorder (Not (NA) as Recorder (Not (Not as (Not Report (Not Report (Not
Utility Total No. as informed
Received) Received) informed by Received) Received) informed Received) Received) Received)
of tripping by utility
utility by utility
1 AD HYDRO 4 0 0 0 2 0 0 1 0 0 1 0
2 ADANI 1 1 100 1 0 0 1 0 0 1 0 100
3 ANTA-NT 1 0 0 1 0 100 1 0 100 1 0 100
4 AURAIYA-NT 3 1 33 3 0 100 3 0 100 3 0 100
5 BAIRASUIL-NH 4 4 100 4 0 0 4 0 100 4 0 100
6 BBMB 39 18 46 24 7 75 25 5 74 20 2 54
7 BUDHIL 4 1 25 2 0 50 2 0 50 2 0 50
8 CHAMERA-III-NH 2 2 100 2 0 0 2 0 0 2 0 100
9 CPCC1 61 25 41 25 0 41 26 4 46 25 0 41
10 CPCC2 46 2 4 2 6 5 2 4 5 10 1 22
11 CPCC3 63 48 76 49 5 84 50 5 86 49 5 84
12 DADRI-NT 6 1 17 1 0 0 1 0 0 1 0 17
13 DHAULIGANGA-NH 2 1 50 1 0 50 1 0 50 1 0 50
14 DULHASTI-NH 1 0 0 0 0 0 0 0 0 0 0 0
15 FARIDABAD-NT 1 0 0 0 0 0 0 0 0 0 0 0
16 KARCHAM 2 1 50 1 0 0 1 0 0 2 0 100
17 KOLDAM-NT 3 3 100 3 0 0 3 0 0 3 0 100
18 NAPP 1 0 0 0 0 0 1 0 0 0 0 0
19 NJPC 7 1 14 2 0 29 2 0 29 1 0 14
20 NLDC 12 12 100 12 0 100 12 0 100 12 0 100
21 RAMPUR 1 0 0 0 0 0 0 0 0 0 0 0
22 RAPPA 7 3 43 6 1 100 6 1 100 6 0 86
23 RAPPB 7 5 71 5 0 71 5 0 71 7 0 100
24 RAPPC 3 0 0 3 0 100 3 0 100 3 0 100
25 SINGOLI 10 10 100 10 0 0 10 0 0 9 0 90
26 SINGRAULI-NT 2 2 100 0 0 0 0 0 0 0 0 0
27 SLDC-DV 23 5 22 11 3 55 11 3 55 11 1 50
28 SLDC-HP 13 2 15 2 6 29 2 6 29 1 0 8
Annexure-B.VII
1 THDC
07/01/2019 to 07/01/2019 to
TEHRI HPS( 4 * 250 ) Yes (Report shared vide email dt.19.01.2019)
10/01/2019 10/01/2019
17/03/2019 to 17/03/2019 to
KOTESHWAR HPS( 4 * 100 ) Yes (Report shared vide email dt.11.02.2021)
19/03/2019 19/03/2019
2 SJVNL
NATHPA-JHAKRI HPS( Unit1 #250) 10.03.2020 - No Excitation system upgraded in 2020
The existing excitation system is very old and obsoleted forwhich support for
PSS tuning is not available from OEM (Mls Voith Hydro), although NJHPS, SJVN
has placed work order on 08/12/201 5. Further being the critical component, it
NATHPA-JHAKRI HPS( Unit2 #250) 14.03.2013 - No is not possibIe”io get the PSS tuning done from any other vender except OEM
(Mls Voith Hydro) being the system and software specific job. Therefore,
prpposal for upgradation of the excitation system of this unit is under process
and PSS tuning shall be carried out during upgradation of excitation system.
NATHPA-JHAKRI HPS( Unit3 #250) 03.03.2020 - No Excitation system upgraded in 2020
The existing excitation system is very old and obsoleted forwhich support for
PSS tuning is not available from OEM (Mls Voith Hydro), although NJHPS, SJVN
has placed work order on 08/12/201 5. Further being the critical component, it
NATHPA-JHAKRI HPS( Unit4 #250) 14.03.2013 - NO is not possibIe”io get the PSS tuning done from any other vender except OEM
(Mls Voith Hydro) being the system and software specific job. Therefore,
prpposal for upgradation of the excitation system of this unit is under process
and PSS tuning shall be carried out during upgradation of excitation system.
NATHPA-JHAKRI HPS( Unit5 #250) 14.05.2016 14.05.2016 NO Excitation system upgraded in 2013
NATHPA-JHAKRI HPS( Unit6 #250) 14.05.2017 14.05.2017 NO Excitation system upgraded in 2013
PSS tuning was done at the time of commissioning of Excitation System by OEM
27.10.2020,10.02.201
RAMPUR HEP( 6 * 68.67 ) 29.11.2014 YES (M/s BHEL). Since then response of PSS is checked regularly and found
21
satisfactory.
3 HVPNL
PANIPAT TPS( unit1# 250 ) 29.03.2016 29.03.2016 YES --
PANIPAT TPS( unit2# 250 ) 15.01.2018 15.01.2018 YES --
DCRTPP (YAMUNA NAGAR)( unit1#300
19-12-2018 19-12-2018 YES (Report attached)
)
DCRTPP (YAMUNA NAGAR)( unit1#300
Will be carried out shortly
)
Report
attached.
No MW capacity addition after 2013 at RGTPP Khedar.
RGTPP( KHEDAR) (2*600) 5th to 6th July 2013 5th to 6th July 2013 Previous record
No new line addition in vicinity of station
being looked
into
JHAJJAR(CLP) (2*660) 20-05-2017 20-05-2017 YES --
4 NTPC
Rihand ( Unit1#500 ) 03-03-2017 03-03-2017 YES Next test will be done during re-commissioning of unit after O/H
Rihand ( Unit2#500 ) 02-07-2016 02-07-2016 YES Next test will be done during re-commissioning of unit after O/H
Rihand ( Unit3#500 ) 15-08-2015 15-08-2015 YES Next test will be done during re-commissioning of unit after O/H
Rihand ( Unit4#500 ) 25-05-2017 25-05-2017 YES Next test will be done during re-commissioning of unit after O/H
Rihand ( Unit4#500 ) 11-12-2014 11-12-2014 YES Next test will be done during re-commissioning of unit after O/H
Rihand ( Unit5#500 ) 11-12-2014 11-12-2014 YES Next test will be done during re-commissioning of unit after O/H
SINGRAULI STPS( Unit1#200 ) - - - Not done in last three years
SINGRAULI STPS( Unit2#200 ) - - - Not done in last three years
SINGRAULI STPS( Unit3#200 ) - - - Not done in last three years
SINGRAULI STPS( Unit4#200 ) - - - Not done in last three years
SINGRAULI STPS( Unit5#200 ) - - - Not done in last three years
SINGRAULI STPS( Unit6#500 ) 02.05.2018 02.05.2018 NO --
SINGRAULI STPS( Unit7#500 ) 15.07.2018 15.07.2018 NO --
UNCHAHAR I( 2 * 210 ) 29-03-2016 29-03-2016 YES --
UNCHAHAR II TPS( unit1# 210 ) 13-07-2019 13-07-2019 YES --
10-08-2018
UNCHAHAR II TPS( unit2# 210 ) 10-08-2018 YES --